1)
Introduction:
To prepare: The journal entry for development cost.
2)
Introduction: The accounting process of spreading an intangible asset's cost over the course of its useful life is known as amortization.
The amortization expense for 2022.
3)
Introduction: The organization creates an income statement to determine how much gross profit or net profit was made during the year. It is a financial statement that provides the details of revenue and expenses for a particular period.
The net amount reported in the
Want to see the full answer?
Check out a sample textbook solutionChapter 11 Solutions
Intermediate Accounting, 10 Ed
- Need part 2-c, 3, & 4 2-c. In the journal below, complete the necessary journal entries for the year 2023 (credit "Various accounts" for construction costs incurred).3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract.4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. 2021 2022 2023Cost incurred during the year $ 2,520,000 $ 3,860,000 $ 3,220,000 Estimated costs to complete as of year-end 5,720,000 3,220,000 0arrow_forwardInformation in the picture 1.Using the percentage-of-completion method, calculate the estimated gross profit that would be recognized during each year of the construction period 2020 $___________ 2021 $____________ 2022 $_____________ 2. Using the completed-contract method, calculate the estimated gross profit that would be recognized during each year of the construction period 2020 $___________ 2021 $___________ 2022 $___________arrow_forwardOn August 1, 2024, Reliable Software began developing a software program to allow individuals to customize their investment portfolios. Technological feasibility was established on January 31, 2025, and the program was available for release on March 31, 2025. Development costs were incurred as follows: August 1 through December 31, 2024 January 1 through January 31, 2025 February 1 through March 31, 2025 $ 6,300,000 1,200,000 1,600,000 Reliable expects a service life of five years for the software and total revenues of $8,000,000 during that time. During 2025, revenue of $2,000,000 was recognized. Required: 1. Prepare the journal entries to record the development costs in 2024 and 2025. 2. Calculate the required amortization for 2025. Complete this question by entering your answers in the tabs below. Required 1 Required 2 Prepare the journal entries to record the development costs in 2024 and 2025. Note: If no entry is required for a transaction/event, select "No journal entry…arrow_forward
- 1. Prepare a schedule showing the revenue, cost and gross profit earned each year using thepercentage of completion method, using the engineer’s estimate as a measure ofcompletion.2. Prepare all journal entries required to reflect the contract3. Prepare journal entries for 2020 assuming zero profit method is used.arrow_forwardPrepare consoldiation worksheet entries for December 31, 2020 and December 31, 2021.arrow_forwardPresent the assets in the statement of financial position on December 31, 2020.arrow_forward
- What is the management fee that should be paid to Phoenix for the 2019 year? Show your calculations.arrow_forwardIn February 2020, Sheridan Construction signed a contract and commenced construction on a parking garage. The total contract price was $88.3 million and was expected to be completed in July 2024 at a total estimated cost of $81.0 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. The customer was to have control over the parking garage and was able to make major changes to the project during the construction process. Sheridan’s year-end was September 30.By the end of September, 2020, Sheridan had incurred $20,250,000 in costs and had invoiced $7,600,000 in progress billings. $7,100,000 of the progress billings had been collected.By September 30, 2021, Sheridan had incurred $39,000,000 in total costs and had invoiced $45,100,000 in progress billings, including the progress billings in 2020. Of the total billings, $30,900,000 in total had been collected. Also, Sheridan reviewed its cost estimates…arrow_forwardSee the attached photo for the problem Required: a. Compute the total current liabilities on December 31, 2020 b. Determine the interest expense to be reported in 2020.arrow_forward
- In February 2020, Cullumber Construction signed a contract and commenced construction on a parking garage. The total contract price was $89.9 million and was expected to be completed in July 2024 at a total estimated cost of $82.6 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. The customer was to have control over the parking garage and was able to make major changes to the project during the construction process. Cullumber’s year-end was September 30.By the end of September, 2020, Cullumber had incurred $12,390,000 in costs and had invoiced $9,900,000 in progress billings. $8,000,000 of the progress billings had been collected.By September 30, 2021, Cullumber had incurred $39,600,000 in total costs and had invoiced $45,900,000 in progress billings, including the progress billings in 2020. Of the total billings, $30,800,000 in total had been collected. Also, Cullumber reviewed its cost…arrow_forwardPrepare a partial balance sheet showing the investment-related amounts to be reported at December 31, 2017 and December 31, 2018 (see attached picture)arrow_forwardIn February 2020, Sandhill Construction signed a contract and commenced construction on a parking garage. The total contract price was $90.8 million and was expected to be completed in July 2024 at a total estimated cost of $83.0 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. The customer was to have control over the parking garage and was able to make major changes to the project during the construction process. Sandhill’s year-end was September 30.By the end of September, 2020, Sandhill had incurred $20,750,000 in costs and had invoiced $10,400,000 in progress billings. $7,600,000 of the progress billings had been collected.By September 30, 2021, Sandhill had incurred $40,200,000 in total costs and had invoiced $45,500,000 in progress billings, including the progress billings in 2020. Of the total billings, $30,500,000 in total had been collected. Also, Sandhill reviewed its cost estimates…arrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education