Your company is considering the replacing an old machine with a more efficient model. The new machine costs $39,500, will last for 7 years and save $12,900 per year in expenses. The discount rate is 18% and the tax rate is 26%. The machine will be depreciated on a straight line basis to zero. The old machine is fully depreciated and can be sold today for $2,700. A) what is the amount of initial investment required? B) what is the after-tax gain on the sale of the old machine? The old machine is fully depreciated. C) what is the amount of operating cash flow (OCF) per year? D) what is the NPV of the project?

EBK CONTEMPORARY FINANCIAL MANAGEMENT
14th Edition
ISBN:9781337514835
Author:MOYER
Publisher:MOYER
Chapter9: Capital Budgeting And Cash Flow Analysis
Section: Chapter Questions
Problem 10P
icon
Related questions
Question
Your company is considering the replacing an old machine with a more efficient model. The new machine costs $39,500,
will last for 7 years and save $12,900 per year in expenses. The discount rate is 18% and the tax rate is 26%. The machine
will be depreciated on a straight line basis to zero. The old machine is fully depreciated and can be sold today for $2,700.
A) what is the amount of initial investment required?
B) what is the after-tax gain on the sale of the old machine? The old machine is fully depreciated.
C) what is the amount of operating cash flow (OCF) per year?
D) what is the NPV of the project?
Transcribed Image Text:Your company is considering the replacing an old machine with a more efficient model. The new machine costs $39,500, will last for 7 years and save $12,900 per year in expenses. The discount rate is 18% and the tax rate is 26%. The machine will be depreciated on a straight line basis to zero. The old machine is fully depreciated and can be sold today for $2,700. A) what is the amount of initial investment required? B) what is the after-tax gain on the sale of the old machine? The old machine is fully depreciated. C) what is the amount of operating cash flow (OCF) per year? D) what is the NPV of the project?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
EBK CONTEMPORARY FINANCIAL MANAGEMENT
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:
9781337514835
Author:
MOYER
Publisher:
CENGAGE LEARNING - CONSIGNMENT
Fundamentals Of Financial Management, Concise Edi…
Fundamentals Of Financial Management, Concise Edi…
Finance
ISBN:
9781337902571
Author:
Eugene F. Brigham, Joel F. Houston
Publisher:
Cengage Learning
Intermediate Financial Management (MindTap Course…
Intermediate Financial Management (MindTap Course…
Finance
ISBN:
9781337395083
Author:
Eugene F. Brigham, Phillip R. Daves
Publisher:
Cengage Learning
Financial Management: Theory & Practice
Financial Management: Theory & Practice
Finance
ISBN:
9781337909730
Author:
Brigham
Publisher:
Cengage
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College