You are working on a construction project. You, your team, and your
senior manager all feel that the work is complete. However, one of your
stakeholders disagrees, and feels that one deliverable is not acceptable. What
is the BEST way to handle this conflict?
A. Renegotiate the contract
B. File a lawsuit to force the stakeholder to accept the deliverable
C. Follow the administrative and contract closure procedures
D. Consult the contract and follow its claims administration procedure
One way contract closure differs from administrative closure is:
A. “Administrative closure involves the stakeholders and the team; contract closure
involves only the team but not
the stakeholders”
B. Administrative closure defines actions the team must take; contract closure defines
legal commitments
C. Administrative closure means verifying that the project is complete or terminated;
contract closure means verifying that the contract terms were satisfied
D. Administrative closure is performed by the seller; contract closure is performed by
the buyer
Trending nowThis is a popular solution!
Step by stepSolved in 2 steps
- Ben London owns and operates Fantastic Footage, a film-editing company in Los Angeles that does contract work mostly for production companies in Hollywood. Not long ago, a local landscaping business completed nearly $8,500 worth of work around London's offices. While the initial bid seemed a little high for the amount of work that was actually done, there is no question that the work completed was of high quality, and London finally feels comfortable inviting potential clients to meet him at his office to discuss possible deals. However, because of an apparent oversight, the landscaping contractor never submitted a bill. It's been more than 15 months since the completion of the project, and London has come to conclude that the contractor somehow lost track of the project. He is thinking about calling the company to ask for a final invoice so that he can settle up, but business has been really slow over the last year or so, and it hasn't been easy to pay all of the bills as it is.…arrow_forwardTWENTY-THREE. Cost reimbursable contracts are most often used when the scope of work or the costs for performing the work are well known. True Falsearrow_forwardA Delaware LLC wanted to acquire a 300,000 square foot class “A” office building in Philadelphia for $150 per square foot that was 77% leased. Wells Fargo agreed to fund a purchase money mortgage loan with a maximum LTV of 60%. What is the minimum amount of equity that would be needed to close the acquisition? a. $45,000,000 b. $9,000,000 c. $18,000,000 d. $27,000,000arrow_forward
- 82) Which of the following is an example of an action done by a firm to conduct structuring? a) Stock buy-back b) Leveraged buy-out c) Either A and B d) Neither A nor barrow_forwardNed works for a ride share service. By contract with his boss, he must work at least 35 hours per week in the borough of Manhattan; can only give rides to people through the company app; must use the route set forth on the company GPS program; cannot work for another rideshare operator. He is paid on commission – 60% of fares. Can Ned be properly categorized as an independent contractor?arrow_forwardBailey is a limited partner in his company. A general partner in his company is going on an extended vacation and has asked Bailey to run the company while he is gone. If Bailey agrees to do so, he will no longer qualify as a limited partner. ( a) True b) Falsearrow_forward
- Which of the following remedies may be provided for in a contract? Question 6Answer a. liquidated damages, deposits, down payments b. rescission, specific performance, injunction c. all of the above d. none of the abovearrow_forwarda) List the five requirements for contract formation and give a short (approximately 1–2 sentences) description of each requirement.b) Choose one of the requirements from your answer to (a). Write a short (approxi- mately 5–10 sentences) example of a contract that does not satisfy this requirement and explain why.arrow_forwardIf the New York Philharmonic records Beethoven's 5t Symphony on DG records. And, DG records pays for the recording, musicians and expenses of the recording, WHO owns the "pertormance" of the work: A. The NY Philharmonic B.DG Records C.The Conductor of the Orchestra D.Beethovenarrow_forward
- Give typed explanation not a single word hand written otherwise leave it 49. Which of the following is an example of a void contract? Missy orally agrees to lease Bob's house for $950 a month. Jamal, who is 15, agrees to buy a stereo from Stereo World for $5,000. Kallie agrees in writing to pay Will $400,000 to mug her uncle. Roberto orally agrees to buy Jim's art collection for $150,000.arrow_forwardPartnership agreements can be modified: (A) Only with prior approval from the IRS. (B) At any time if agreed to by all partners, for both formal written agreements or informal agreements. (C) Only in writing, regardless of whether the partnership agreement is formal or informal. (D) If more than 75% of the partners agree to the modifications to the agreementarrow_forwardWhat is a no-damage-for delay clause, what type of clause is this, and what is its purpose?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.