Winston's assembly unit has decided to use a p-Chart with an a risk of 1 % to monitor the proportion of defective metal shafts produced by their production process. The production manager randomly samples 200 metal shafts at 16 successively selected time periods and counts the number of defective metal shafts in the sample. Table Answer How to enter your answer Step 8 of 8: You, acting as the production manager, have concluded that the process is "Out of Control". What is the probability that the process is really "In Control" and you have made a Type I Error? Round your answer to three decimal places. Sample Defects 1 2 3 4 5 6 7 8 9 10 11 9 8 12 12 11 13 7 12 11 11 8 7 Control Chart 12 13 10 14 13 15 7 16 10 Copy Table The average of the selected cell(s) is9.000. Copy Value X

MATLAB: An Introduction with Applications
6th Edition
ISBN:9781119256830
Author:Amos Gilat
Publisher:Amos Gilat
Chapter1: Starting With Matlab
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
Winston's assembly unit has decided to use a p-Chart with an a risk of 1% to monitor the proportion of defective metal shafts produced by their production process.
The production manager randomly samples 200 metal shafts at 16 successively selected time periods and counts the number of defective metal shafts in the sample.
Table
Answer
How to enter your answer
Step 8 of 8: You, acting as the production manager, have concluded that the process is "Out of Control". What is the probability that the process is really "In Control"
and you have made a Type I Error? Round your answer to three decimal places.
Sample Defects
1
2
3
4
5
6
9
8
12
12
11
13
7
8
9
10
11 8
12 7
13
14
15
16
7
12
11
11
Control Chart
10
13
7
10
The average of the selected cell(s) is9.000.
Copy Value
Copy Table
↓
X
Transcribed Image Text:Winston's assembly unit has decided to use a p-Chart with an a risk of 1% to monitor the proportion of defective metal shafts produced by their production process. The production manager randomly samples 200 metal shafts at 16 successively selected time periods and counts the number of defective metal shafts in the sample. Table Answer How to enter your answer Step 8 of 8: You, acting as the production manager, have concluded that the process is "Out of Control". What is the probability that the process is really "In Control" and you have made a Type I Error? Round your answer to three decimal places. Sample Defects 1 2 3 4 5 6 9 8 12 12 11 13 7 8 9 10 11 8 12 7 13 14 15 16 7 12 11 11 Control Chart 10 13 7 10 The average of the selected cell(s) is9.000. Copy Value Copy Table ↓ X
Expert Solution
steps

Step by step

Solved in 3 steps with 15 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
MATLAB: An Introduction with Applications
MATLAB: An Introduction with Applications
Statistics
ISBN:
9781119256830
Author:
Amos Gilat
Publisher:
John Wiley & Sons Inc
Probability and Statistics for Engineering and th…
Probability and Statistics for Engineering and th…
Statistics
ISBN:
9781305251809
Author:
Jay L. Devore
Publisher:
Cengage Learning
Statistics for The Behavioral Sciences (MindTap C…
Statistics for The Behavioral Sciences (MindTap C…
Statistics
ISBN:
9781305504912
Author:
Frederick J Gravetter, Larry B. Wallnau
Publisher:
Cengage Learning
Elementary Statistics: Picturing the World (7th E…
Elementary Statistics: Picturing the World (7th E…
Statistics
ISBN:
9780134683416
Author:
Ron Larson, Betsy Farber
Publisher:
PEARSON
The Basic Practice of Statistics
The Basic Practice of Statistics
Statistics
ISBN:
9781319042578
Author:
David S. Moore, William I. Notz, Michael A. Fligner
Publisher:
W. H. Freeman
Introduction to the Practice of Statistics
Introduction to the Practice of Statistics
Statistics
ISBN:
9781319013387
Author:
David S. Moore, George P. McCabe, Bruce A. Craig
Publisher:
W. H. Freeman