Question

Consider the activities, durations, and predecessor relationships in the following network. Draw the network and answer the questions that follow. 

 

Activity Description

Immediate

Predecessor(s)

Optimistic

(Weeks)

Most Likely

(Weeks)

Pessimistic

(Weeks)

A

---

4

7

10

B

A

2

8

20

C

A

8

12

16

D

B

1

2

3

E

D, C

6

8

22

F

C

2

3

4

G

F

2

2

2

H

F

6

8

10

I

E, G, H

4

8

12

J

I

1

2

3

 

  1. What is the expected time for activity B? 
  2. What is the variance for activity B? 
  3. Based on the calculation of estimated times, what is the critical path? 
  4. What is the estimated time of the critical path? 
  5. What is the activity variance along the critical path? 
  6. What is the probability of completion of the project before week 42?
Expert Solution
steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Marketing
Marketing
Marketing
ISBN:
9780357033791
Author:
Pride, William M
Publisher:
South Western Educational Publishing