Question
Jugular Company started construction on a building on January 1 of
the current year and completed construction on December 31 of the same year.
The entity had only two interest-bearing notes outstanding during the year, and both of these notes were outstanding for all 12 months of the year.
The following information is available:
Average accumulated expenditures 2,500,000
Ending balance in construction in progress before
capitalization of interest 3,600,000
6% note incurred specifically for the project 1,500,000
9% long-term note 5,000,000
What is the total cost of the building?
a. 3,780,000
b. 3,680,000
c. 3,750,000
d. 3,825,000
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 2 steps

Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Alpesharrow_forwardUser In February 2024, Cullumber Corp, began the construction of a 10-storey building. The construction is expected to be completed by January 2025. during 2024, the following payments were made: Apr. 1: 1010000 Jun. 1: 1500000 Aug. 1: 840000 Oct. 1: 890000 No asset specific debt was incurred. During 2024, Cullumber's general debt consisted of the following: $1.8 million, 5%, 2-year note, $1.1 million, 4.5%, 2-year note, $0.50 million, 3%, 5-year note. Calculate the avoidable borrowing costs. Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.arrow_forwardElf Hotels began construction of the Snowflake Hotel on January 1st. During the first year of construction of the Snowflake Hotel, Elf Hotels had the following:arrow_forward
- Vishnuarrow_forwardA company constructs a building for its own use. Construction began on January 1 and ended on December 30. The expenditures for construction were as follows: January 1, $680,000; March 31, $780,000; June 30, $580,000; October 30, $1,140,000. To help finance construction, the company arranged a 9% construction loan on January 1 for $1,060,000. The company's other borrowings, outstanding for the whole year, consisted of a $4 million loan and a $6 million note with interest rates of 10% and 8%, respectively. Assuming the company uses the specific interest method, calculate the amount of interest capitalized for the year. Note: Enter your answers in whole dollars and not in millions. Do not round intermediate calculations. Round your percentage answers to 2 decimal places (i.e. 0.1234 should be entered as 12.34%). Date January 1 March 31 June 30 October 30 Accumulated expenditures Average accumulated expenditures Expenditure Amount X X X Weight Interest Rate % % "1 II = = Average…arrow_forwardKlutlan Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Klutlan does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $2,000,000, 8% note $8,000,000, 5% bonds Construction expenditures incurred were as follows: July 1, 2018 $520,000 September 30, 2018 600,000 November 30, 2018 600,000 January 30, 2019 540,000 The company's fiscal year-end is December 31. Question The total value of the warehouse at the end of construction would be: a $2,288,000 b $2,317,702 c $1,745,760 d $2,260,000arrow_forward
- Wolfpack Corp. has determined it should record depreciation expense of $40,000 for the year ending 12/31/X7. Required: In the general journal below, complete the year-end entry to record depreciation. Debit Credit Dec 31 ? 40,000 ? 40,000arrow_forwardWhispering Ltd. is constructing a building. Construction began on February 1 and was completed on December 31. Expenditures were HK$ 1,470,000 on March 1, HK$984,000 on June 1, and HK$ 2,406,000 on December 31. Whispering Ltd. had outstanding all year a 12%, 5-year, HK$ 3,840,000 note payable and on 13 %, 4-year, HK$3,360,000 note payable. Determine the amount of borrowing cost that Whispering Ltd. would capitalize. Use the capitalization rate used for borrowing cost capitalization purposearrow_forwardOn January 1, 2024, the Marjlee Company began construction of an office building to be used as its corporate headquarters. The building was completed early in 2025. Construction expenditures for 2024, which were incurred evenly throughout the year, totaled $6,000,000. Marjlee had the following debt obligations which were outstanding during all of 2024: Construction loan, 11% Long-term note, 10% Long-term note, 7% Required: Calculate the amount of interest capitalized in 2024 for the building using the specific interest method. Interest capitalized $ 1,500,000 2,000,000 4,000,000 $ 255,000arrow_forward
- The following information is from Bowin Inc. for a long-term constructio project that is expected to be completed in January 2021. The construction project is for a building intended for the company's own use. Bowin Inc. borrowed $800,000 at 12% on January 1 to help finance the construction. All debt was outstanding for the full year. Capital Expenditures for 2020 Date Jan. 1, 2020 Mar. 1, 2020 June 30, 2020 Dec. 31, 2020 Amount $2,220,720 300,000 500,000 500,000 Outstanding Debt in 2020 Asset Debt Note payable Note payable Bond payable Note payable Construction loan Debt Amount Interest Rate $1,000,000 600,000 150,000 600,000 800,000 13% 8% 10% 12% 12% The weighted-average accumulated expenditures in 2020 is $arrow_forwardIsko Company had the following general borrowings during 2021 which were used to finance the construction of the entity's new building. Principal 2,800,000 Borrowing Cost 280,000 10% bank loan 10% short-term note 1,600,000 160,000 2,000,000 6,400,000 The construction began on January 1, 2021 and the building was completed on December 31, 2021. In the first phase of the construction, there were idle funds which the entity invested and earned interest 12% long-term loan 240,000 680,000 income of P62,500. Expenditures on the building were made as follows: January 1 March 31 400,000 1,000,000 June 30 1,200,000 September 30 1,000,000 December 31 400,000 What is the amount of capitalizable borrowing cost? (Use 3 decimal places for capitalization rate.)arrow_forwardCulver Inc. has a fiscal year ending April 30. On May 1, 2023, Culver borrowed $10 million at 11% to finance construction of its own building. Repayments of the loan are to begin the month after the building's completion. During the year ended April 30, 2024, expenditures for the partially completed structure totalled $7 million. These expenditures were incurred evenly throughout the year. Interest that was earned on the part of the loan that was not expended amounted to $482,000 for the year. For situation 3, how much should be shown as capitalized borrowing costs on Culver's financial statements at April 30, 2024? (If an answer is zero, please enter O. Do not leave any fields blank.) Capitalized borrowing $arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education


Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,

Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,

Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON

Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education

Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education