A 16 U ∞ OA. 44 B. 35 C. 38 OD. 30 E. 16 B 14 What is the LF (Latest finish time) for activity B? E4 H 6 G 15 F 10 End Time Remaining:
Q: Global freight transportation activities have been rising due to opening of global markets. As such,…
A: The global marketplace has witnessed a significant surge in freight transportation activities in…
Q: quired: 1. Using the high-low method, estimate the fixed cost of electricity per month and the…
A: Here, for each month, I am given the occupancy days data and Electrical costs data, I will apply the…
Q: Describe the challenges and strategies associated with global IT resource acquisition for…
A: Global IT resource acquisition for multinational organizations includes the process of procuring…
Q: Explain the concept of orchestration in systems management. How does it differ from automation, and…
A: Orchestration in systems management refers to the coordination and management of multiple automated…
Q: What are the key components of a business continuity plan (BCP)?
A: A business continuity plan is a document that states how an organization will continue its critical…
Q: What is the significance of iterative prototyping, and how does it improve product development?
A: Iterative prototyping, which offers a systematic way to improve and upgrade goods or systems, is a…
Q: Discuss the concept of service discovery and its importance in a distributed service-oriented system
A: Service-oriented systems refer to a design paradigm where systems are built around independent but…
Q: What are the primary components of the Wilson approach, and how do they contribute to inventory…
A: The Wilson approach contributes to inventory optimization by keeping a major focus on reducing the…
Q: You are hired by Moyer, Inc., a U.S. manufacturing company, to consult on management's consideration…
A: Companies like Moyer, Inc. are continually assessing opportunities for development and expansion in…
Q: Critical Path: Minimal Project Time: 12 hows 10 hours Can activity D be delayed without affecting…
A: For this question, I am given the time data and the immediate predecessor data, I will construct the…
Q: How does the choice of prototyping method impact the cost and time required for product development?
A: The choice of prototype technique is crucial in determining a project's course in the dynamic world…
Q: Activity A B с D E F GH G Immediate predecessors A A B C, D D, E F, G Time (Days) a mb 1 36 1 1 2 3…
A: The critical path refers to the longest sequence of activities or tasks in a project that must be…
Q: Analyze the role of IT procurement in ensuring security and compliance within an organization. How…
A: IT procurement plays an essential role in providing security and compliance within an organization.…
Q: Plant B, because it has the lower variable cost per unit Plant B, because it is cheaper than Plant A…
A: The total cost is the summation of the fixed and total variable costs. Fixed costs are the costs…
Q: why it is exciting to own a restaurant?
A: Note: As per the guidelines, the solution has been authored in a generalized manner and no personal…
Q: Explain the Wilson approach in supply chain management and discuss its key principles.
A: The Wilson Approach, also known as the Economic Order Quantity (EOQ) Model, is a fundamental concept…
Q: How can organizations prioritize and manage conflicting requirements during the analysis phase? What…
A: Prioritizing and managing conflicting requirements during the analysis phase of a project is crucial…
Q: During the __________ stage of the project lifecycle, there is no significant difference in the…
A: Project management involves various stages in project's lifecycle, each with its unique…
Q: Explain the concept of resource allocation in IT. How does it impact the efficiency of an…
A: Resource allocation in IT is the strategic distribution of computing resources, to different tasks,…
Q: a. The estimated learning rate is%. (Enter your response as a whole number.)
A: Learning rate is a concept used in production management. It helps to analyze the gaps in the…
Q: Kilgore's Deli is a small delicatessen located near a major university. Kilgore does a large walk-in…
A: Note:Since you have posted a question with multiple sub parts, we will provide the…
Q: Explain why services marketing are important to satisfy the customers in a service oriented…
A: Services are intangible offerings that play a very important role in society. Services help in the…
Q: What challenges can arise when transitioning from a prototype to full-scale production, and how can…
A: Businesses face several difficulties when they go from prototyping to full-scale production,…
Q: Kindly draft at least 5 SMART Work Objectives from the following below. 1. Perform the Human…
A: SMART is a framework used in project management regarding objectives. SMART stands for;S- SpecificM-…
Q: What are the key factors to consider when evaluating IT vendors for resource acquisition?
A: An important initial step when beginning the process of obtaining IT resources, whether they be…
Q: Determine the capacity efficiency of the shop. O A. The capacity efficiency is 83.75%. OB. The…
A: First, Let me state the given data,for the given data, I will determine the capacity efficiency,
Q: ack Simpson, contract negotiator for Nebula Airframe Company, is currently involved in bidding on a…
A: Labor Hour data for the first three units is given below,UnitsLabor Hours120002160031500Here, I will…
Q: Gubser Welding, Inc., operates a welding service for construction and automotive repair jobs. Assume…
A: Arrival rate = 5 jobs / 8 hours = 0.625 jobs per hourService rate = 1 job / 1.3 hour = 0.7692 jobs…
Q: Security clearances (none, confidential, secret, top secret)? Group of answer choices: Nominal…
A: Business information helps the organization in identifying as well as mitigating risks. The risk can…
Q: Company Z is just starting to make a brand new product it has never made before. It has completed…
A: Time taken by the First unit =29 hoursTime taken by the Second unit =22 hours
Q: Schedule the Following Activities using CPM: 15 Duration of the project is: ID A B C D E F G H None…
A: The critical path is a fundamental concept in project management, It refers to the longest sequence…
Q: Discuss the importance of employee training and awareness in implementing a continuity plan.
A: In human resource management, employee development is essential for an organization's success and to…
Q: What are the key components of an effective system management strategy?
A: A system management strategy includes measures for monitoring, maintaining, and optimising an…
Q: Explain how service quality is measured and its importance in customer satisfaction and retention
A: Service quality is the critical concept in the operations management, especially in industries where…
Q: Explain the process of IT resource acquisition in an organization. What are the key considerations…
A: The process of IT resource acquisition in an organization involves getting the required hardware,…
Q: What role does demand variability play in the Wilson Approach, and how can it be managed…
A: Demand variability plays a significant role in the Wilson Approach, also known as the Economic Order…
Q: The diner owner has room for 55 containers of shredded Parmesan cheese. He has 5-oz and 10-oz…
A: The number of 5-oz and 10-oz containers = 55Total cheese = 450 -oz5-oz containers sell for $7 and…
Q: Give typed full explanation Industrial Products, Inc. has two alternatives for manufacturing…
A: Unit produced = 12,000In house,Fixed cost = $2,100,000Variable cost per unit = $6,800Outsourcing…
Q: The stationary shop estimates that the average demand for a popular ball-point pen is 12,000 pens…
A: In this situation, I will determine the safety stock,
Q: There is an 81 percent chance the project below can be completed in X weeks or less. A B с D E
A:
Q: Which of the following is demerit of Decision tree approach? It displays the logical relationship…
A: The decision tree approach depicts choices and their potential outcomes in a graphical…
Q: Analyze a real-world case study where a company successfully implemented the Wilson approach in…
A: The Wilson EOQ (Economic Order Quantity) Model is a fundamental concept in supply chain management…
Q: Granos, Inc. purchased new automated coffee vending machines, the Preso 2000. This Preso 2000…
A: Arrival Rate = Service Rate =
Q: Discuss the ethical considerations and regulatory compliance challenges in database management,…
A: Effective database administration is not only a key component of organisational success in today's…
Q: Explore the concept of reorder point (ROP) within the Wilson Approach. How is it calculated, and why…
A: The reorder point (ROP) is a fundamental concept within inventory management, including the Wilson…
Q: John's Operations manager has received production forecasts of Company sales for the next year. He…
A: Firstly, Formula:Cycle Time = Given that:Production units per week = 1200 UnitsOperating Time = 40/…
Q: Examine the future trends in prototyping, such as the integration of artificial intelligence and…
A: Product innovation helps companies differentiate their products in a crowded marketplace. By…
Q: Explore the role of technology and data analytics in enhancing the Wilson approach's performance in…
A: The Wilson Approach, also known as the Economic Order Quantity (EOQ) model, has long been used as a…
Q: In the context of continuity planning, what are the legal and regulatory compliance requirements…
A: Continuity planning is a structured technique in which organisations plan strategies and activities…
Q: Discuss the importance of scanning the opportunities and threats to business. Also explain the…
A: Scanning the opportunities and threats to business is an important part of strategic analysis and…
Trending now
This is a popular solution!
Step by step
Solved in 3 steps
- Example 2.39 Table 2.119 provides normal and crash times as well as normal and crash costs for the activities of a project. Table 2.119 Project activity details Activity Normal Time (Weeks) Normal Cost (Lakhs) Crash Time (Weeks) 1-2 3 5 2-3 4 8 2-4 3 4 2-5 8 S 3-6 4 3 4-6 6 2 5-7 5 10 6-7 3 7 1 3 2 7 2 4 4 1 Crash Cost (Lakhs) 9 14 6 6 5 3 14 10 Project Network Analysis-1 | 141 (a) Draw the network and find the critical path. (b) Using the above information, crash or shorten the activities step by step until the shortest duration is reached. MMM, VI Sem, Mumbai Univ, 2006AutoSave Off H₂C= PDPMT_PL102_06 June 2023_1 No Label ✓ File Home Insert Draw Design Layout References X CA W Paste Clipboard Page 6 of 7 ■ Arial B|I U U 12 of 956 words Q Search ✓12 ab ab x₂ x Font A A Aa A A x ADA А Α English (South Africa) 9° Review Paragraph interpret facts and events differently. Question: 3.1 3.2 View Mailings Help EE F✓ = = £↓¶ ≡ ≡ ≡ ~ 4 Text Predictions: On Search 5 Adapted from Kloppenborg TJ, Anantatmula V and Wells KN (2019) Contemporary Project Management 4th edition Cengage Accessibility: Unavailable Normal 5 No Spacing Explain what is meant by the notion that "some conflicts on projects are useful..." Discuss the strategies a project manager can employ to discourage or minimise 'destructive' conflict in a project management environment. W Styles Heading 1 5 A Thembi Mdepa TM Editing Focus Comments Editing Dictate Voice Sensitivity Sensitivity Editor ENG US Editor 4x Share Reuse Files Reuse Files V + 100% 08:33 2023/06/06 &nity College | Pima x B Module 12 Practice Assignment 6 Question 1- Module 12 Practice x A ezto.mheducation.com/ext/map/index.html?_con=con&external_browser=D0&launchUrl=https%253A%252F%252Flms.mheducation.com%252Fmghmiddleware%252Fr ediStay v4 E New Scorpion O Redistay - (Unknown) U Ulitpro -New e Scorpion (UAT) 5) Springfield - Home inContact Dashboards RediStay v4 (UAT) -... lodule 12 Practice Assignment_Ch.17 i Saved 1 Challenge Problem 17-25 (Static) [LU 17-2 (2)] A delivered price (including attachments) of a crawler dozer tractor is $135,000 with a residual value of 35%. The useful life of the tractor is 7,700 hours eBook Print a. What is total amount of depreciation allowed? References Total amount b. What is the amount of depreciation per hour? (Round your answer to the nearest cent.) Amount of depreciation per hour
- Activity Normal_time Crash_time Normal_cost Crash_cost Slack 28 22 5800 6700 0 30 4200 4200 1 13 4500 4500 0 25 4300 6700 1 18 5700 6700 2 20 5200 6500 2 AB C D E F 30 13 33 29 Previous 34 The table shows normal time (in days), crash time (in days), normal cost (in dollars), crash cost (in dollars) and slack time (in days) of activities in a small construction project. According to this table which activity must be crashed first? Assume there is only one critical path. (Only type the name of the activity, Example: A. NextActivity Normal_time Crash_time Normal_cost Crash_cost Slack A 31 28 4500 6700 2 13. 13 5800 5800 0 27 27 5000 5000 0 27 16 4000 6900 2 24 24 5500 5500 0 34 13 4500 6900 0 B C D E F The table shows normal time (in days), crash time (in days), normal cost (in dollars), crash cost (in dollars) and slack time (in days) of activities in a small construction project. According to this table which activity must be crashed first? Assume there is only one criticalOne case is missing. 5 cases are req
- Lenovo Barmaining Time: 30 minutes, 26 seconds. Question Completion Status: Consider the following payoff Table Decision Alternative D1 D2 The State of Nature 0.79 1-0.79- S1 52 5 8 8 4 D3 14 4 What is the payoff value for the D2 under S2 should be to keep the optimal solution always optimal?(Do not writ the sign > or <) (Round your answer to 2 decimal places) Save and Submit to save and submit. Click Save All Answers to save all answers. Save All AnswersOngoing Clients 75 Client Attrition Rate for MRR: 30% Avg MRR from New Business per Rep $ 15,000 Average Deal Size (MRR) $ 12,000 % of SQLs that Close 16% % MQLs that Become SQLs 9% # of Reps on Team 5 Avg Growth Deals per Rep per Month 2 Avg MQL per Month 600 Avg MRR from Growth Deals per Rep $ 20,000 What is the NEW BUSINESS MRR Current Year $ per Rep?time (hours) pH 7.00 7.30 6.99 7.00 Assignment 1 2 7.12 7.25 7.12 7.20 3 720 7.16 720 7.16 4 6.98 7.00 6.94 7.00 5 6.99 6.99 6.99 6.98 6 7.00 6.93 7.02 6.93 7 6.92 7.00 6.92 7.02 Construct the X-Bar charts and R- charts 6.88 6.82 6.94 6.99 7.10 7.00 7.00 7.00 for reporting your results 10 721 7.02 721 7.04 11 7.01 6.86 7.01 6.90 12 6.86 6.98 6.90 6.98 13 6.90 7.00 6.87 7.00 14 7.01 7.04 7.01 7.05 15 7.00 6.95 7.00 6.99 16 7.09 7.20 7.03 7.20 17 6.89 7.14 6.87 7.15 18 6.98 6.80 6.98 6.89 19 7.00 6.90 7.00 6.90 20 7.20 7.00 723 7.00 21 7.04 7.03 7.08 7.00 22 6.90 6.92 6.98 6.92 23 7.00 7.00 7.00 7.00 24 7.00 6.97 7.01 6.98
- #3 Question 30 WBS stands for which of the following project management tools? O work break schedule O work breakdown schedule O work break status work breakdown structure O work breakdown status * Previous MacBook Air 000 F2 08 000 F5 DD F8 $ 4 %23 % & 5. 9 8.EX6-12 (Algo) You are creating a customer database... You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Given the information below, complete the forward and backward pass, compute activity slack, and identify the critical path. How long will this project take? ABCDACHSX K L Description Systems Subsystem A design Subsystem B design Subsystem C design Program A Program B Program C Subsystem A test Subsystem B test Subsystem C test Integration Integration test days. Predecessor None A A A B с D E F G H, I, J K Time (days) 7 3 1 3 5 15 5 3 3 5 3Input Area Cost Per Hour $1500.00 Outage Duration (hours) 3 Output Area Total Cost for Outage $4500.00 One-Variable Data Table: Cost Outage Impact Analysis Duration (hr) (Cost) 1 $1500.00 1.5 $2250.00 2 $3000.00 2.5 $3750.00 3 $4500.00 3.5 $5250.00 4 $6000.00 4.5 $6750.00 5 $7500.00 Given the data above Which What If Analysis tool is the worksheet using? Provide a description of the What If Analysis tool and why it was used in the worksheet. Interpret what the data means. Discuss what it means for the business.