The trim line at PW is a small subassembly line that, along with other such lines, feeds into the final chassis line. The entire assembly line, which consists of more than 900 workstations, is to make PW’s new E cars. The trim line itself involves only 13 work elements and must handle 20 cars per hour. Work-element data are as follows:
Work Element | Time (Sec) | Immediate Predecessor(s) |
A B C D F G H I J K L M |
1.8 0.4 1.6 1.5 0.7 0.5 0.8 1.4 1.4 1.4 0.5 1.0 0.8 |
None None None A A E B C D F,G H J I,K,L |
a. Draw a precedence diagram.
b. What cycle time (in minutes) results in the desired output rate?
c. What is the theoretical minimum number of stations?
d. Use the longest work element decision rule to balance the line and calculate the efficiency of your solution.
e. Use the most followers work element decision rule to balance the line and calculate the efficiency of your solution.
Trending nowThis is a popular solution!
Step by stepSolved in 3 steps with 3 images
d. Use the longest work element decision rule to balance the line and calculate the efficiency of your solution.
e. Use the most followers work element decision rule to balance the line and calculate the efficiency of your solution.
Please answer both questions following on from the above working out
d. Use the longest work element decision rule to balance the line and calculate the efficiency of your solution.
e. Use the most followers work element decision rule to balance the line and calculate the efficiency of your solution.
Please answer both questions following on from the above working out
- What components are required to assemble a control unit with vertical coding, and how is it constructed?arrow_forwardA manufacturing plant has the process displayed below. The drilling operation occurs separately from and simultaneously with the sawing and sanding operations. The product only needs to go through one of the three one of the three assembly operations (the assembly operations are ‘parallel’). a) What is the bottleneck operation? b) What is the throughput time for the overall system? c) If the firm operates 10 hours a day, 21 days a month, what is the monthly and yearly capacity of the manufacturing process? d) Supposed that a second drilling machine is added, and it takes the same time as the original drilling machine. What is the new bottleneck time of the system? e) What is the new throughput time if the second drilling machine is added?arrow_forwardExplain the differences between one-worker, multiplemachine (OWMM) and group technology (GT) approaches to lean system layouts.arrow_forward
- These four phases make up a machine cycle, which is also known as a process loop. What percentage of a machine's cycle time do you value the most? Should I be concerned about replacing parts of the machine cycle when they wear out? Is the problem of switching modules improved by adding a second module?arrow_forwardThe following diagram represents a process where two components are made at stations A1 and A2 (one component is made at A1 and the other at A2). These components are then assembled at station B and moved through the rest of the process, where some additional work is completed at stations C, D, and E. Assume that one and only one person is allowed at each station. Assume that the times given for each station represent the amount of work that needs to be done at that station by that person, with no processing time variation. Assume that inventory is not allowed to build in the system. What is the average hourly output of the process when it is in normal operation?arrow_forwardHP Computer's primary consumer business takes orders from customers for specific configurations of desktop and laptop computers. Customers must select from a certain model line of computer and choose from available parts, but within those constraints may customize the computer as they desire. Once the order is received, hp assembles the computer as ordered, and delivers it to the customer. What type of manufacturing process is described here?arrow_forward
- How is six sigma, theory of constraints, and lean similar?arrow_forwardRick Wing has a repetitive manufacturing plantproducing automobile steering wheels. Use the following datato prepare for a reduced lot size. The firm uses a work year of305 days. a) What is the setup cost, based on the desired lot size?b) What is the setup time, based on $40 per hour setup labor?arrow_forwardConsider an assembly line with a single shift per day and each shift runs 8 hours with 2 tea breaks that each tea break takes 12 minutes, and 20 minutes lunch break. The downtime and ideal cycle time are 45 minutes and 1.2 seconds respectively. The total produced items and reject items are 18,570 and 455 respectively. Calculate the OEE.arrow_forward
- The bill of materials shows all the parts required to make Select one: a work-in process inventory b. the MPR c.raw materials inventory d.one itemarrow_forwardBased on the following BPMN diagram: -List the main elements in the diagram-Illustrate the model scenario and situation Note: please make it a unique answer.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.