The project shown within details what is the possibility t finish the project in 38 days? And what's the time required to finish it with possibility of 99%? Act m

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
icon
Related questions
icon
Concept explainers
Topic Video
Question
The project shown within details what is the possibility to
finish the project in 38 days? And what's the time
required to finish it with possibility of 99%?
Act.
a
b
1-2
2
7
8.
2-3
6.
9.
2-4
3
7
8
2-5
4
6.
3-6
6.
9
10
4-7
8
11
5-7
4
6.
7
6-8
7
10
7-8
4
8.
9.
8-9
4
7
9
Transcribed Image Text:The project shown within details what is the possibility to finish the project in 38 days? And what's the time required to finish it with possibility of 99%? Act. a b 1-2 2 7 8. 2-3 6. 9. 2-4 3 7 8 2-5 4 6. 3-6 6. 9 10 4-7 8 11 5-7 4 6. 7 6-8 7 10 7-8 4 8. 9. 8-9 4 7 9
Expert Solution
steps

Step by step

Solved in 4 steps with 4 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS