B. What is the expected project completion time? 7 weeks 8 weeks 9 weeks 6 weeks C. Which are the critical activities? A, B, C, F, G and I A, B,C, G and I A, B, C, D, E, F and I A, B, C,D, F, G and I
Q: Calculate the critical path for this project The Critical path is _______________ and the project…
A: The critical path is the path that takes the longest time to complete the project network.
Q: example of cost control for project
A: Cost Control A tool which is used by the organization’s management in controlling and regulating the…
Q: Which activity should be crashed to reduce the project completion time by one day? -Activity E…
A: In this given problem, first, calculate the project completion time. There are two possible paths.…
Q: 13.39 Activity A is worth $500, is complete, and actually cost $500. Activity B is worth $1.000, is…
A: Earned Value (EV) is the sum of percentage completed multiplied by the task budget. The calculation…
Q: 1- Total project finishing time 2- Critical path, 3- Free float for each task. • 4- If Activity B is…
A: The critical path is the path with the longest duration.
Q: The following six activities constitute an overall bar chart portrayal of 4-month project. Two…
A: This question is related to the topic of Project Management and this topic falls under the…
Q: What is the To Complete Performance Index if the project budget is $8,000, 40% of the project has…
A: With the give data, the calculations with formula are: Budget at completion (BAC) = $8000
Q: A company's information security blueprint is a project strategy, but how does this happen?
A: A security blueprint can be defined as a comprehensive plan that manages an organization's security…
Q: a) What is the probability that the project can be completed in 25 days or fewer?
A: The expected activity time is the time taken by the particular activity to complete the project…
Q: 44. What activities make up the critical path? In crashing this project, which activity is the first…
A: Project crashing is the process of reducing the activity duration using additional cost through…
Q: Which process involves measuring against the project schedule baseline by looking to see what things…
A: Project schedule A project schedule can be explained as a plan for completing a project…
Q: ffing related to each stage of the project life cycle?
A: Phases may be used by project managers or the organization as a way to better manage projects and…
Q: Q1: Draw the allocation of resources chart on the earliest and latest start time for the project…
A: In given network diagram critical path will pass the activities B−E−G−K duration of the…
Q: 15F - Estimate how long (total time in months from start to finish, not how many months remain -…
A: THE ANSWER IS AS BELOW:
Q: Q1:- The timetable for one of the projects was as in Table No. (1), answer the following: 1- Draw…
A: Below is the solution:-
Q: What is not from the following a part of project phases a. Execution O b. Planning O c. Initiation O…
A: "Since, you have asked multiple questions so we will solve the first question for you. If you want…
Q: A chart that shows both the time and sequence for completing the activities in a project is?…
A: A chart that shows both the time and sequence for completing the activities in a project is a Gantt…
Q: a. Determine the project completion time if no activity is crashed. What would be the total cost of…
A: Below is the solution:-
Q: Who creates the project schedule?
A: Project scheduling refers to creating a schedule containing the activities, milestones, and…
Q: of the project, the same principles of project management (2) Whatever the apply. (a) quality (b)…
A: Project management: It is the utilization of methodologies, devices, and methods to progressively…
Q: d. Determine the probability that the team and the contractor will be in place and the project…
A: Based on the 3-time estimates given, we find the Expected duration and Variance for each activity as…
Q: (f) What is the largest number of weeks allotted to finish the electrical wirings without delaying…
A: Below is the solution:-
Q: A4 A3 A6 A8 (A7 A2 A5 19 days The activity times are 2, 5, 2, 4, 9, 1, 2, and 3 days for activities…
A: The critical path method is the technique to find the least duration of the project. It is the path…
Q: PERT analysis computes the variance of the total projectcompletion time as:a) the sum of the…
A: Leadership style is the approach of providing direction, plans implementation, and motivating…
Q: a) What is the expected time to complete the project?
A: The expected activity time is the time taken by the particular activity to complete the project…
Q: What is project management software and what are the advantages and disadvantages? Diagrams?
A: Project management is not an easy task. There are a lot of steps and functions involved in project…
Q: A project to build a new bridge seems to be going very well since the project is well ahead of…
A: Budget cost 1 = $1,420,000 Budget cost 2 = $10,500,000 Budget cost 3 = $8,500,000*50% =$4,250,000…
Q: Month 1 Month 2 Month 4 Month 5 Month 6 Activity A Cost $100 $200 $ 60 $ 80 $ 40 $150 $300 $100 $ 50…
A: The Cost Performance Index or called (CPI) is a process for estimating the cost efficiency &…
Q: 1. A project was planned using PERT with three-time estimates. The expected completion time of the…
A: Given- Expected completion time (x) = 40 weeksDesired completion time (μ) = 40 weeks or…
Q: the working of the t
A: The triple constraint theory in project management states that undertaking works inside the limits…
Q: 1. A project was planned using PERT with three-time estimates. The expected completion time of the…
A: Given- Expected completion time (μ)= 40 weeksDesired completion time (x) = 46 weeks or…
Q: To properly evaluate, project managers were asked to prepare AON and AOA of the project based on the…
A: Given data is
Q: Nhat is the overall duration of the project (in weeks)? 32 weeks Nhat is the earliest week you could…
A:
Q: cts to implement in project man
A: To be a good project manager, one must have a wide range of abilities. It requires a variety of…
Q: challenges in assessing the scope of a project? What is “scope creep” and how do you ensure that it…
A: Scope of project is set of work which is necessary to complete the project. Project might be a to…
Q: c) What is the critical path for this project and how long is it?
A: Below is the solution:-
Q: G This exercise contains only parts b, c, and d. b) The critical activities for the leadership…
A: The critical activities are the activities that lie on the critical path of a project. In a project,…
Q: Based on the diagram in question 3, what happens to the project duration if Activity C is done at…
A: If Activity C is done at the same time as Activity D, then both the activities will done in 4 days…
Q: Below is the details about a. What is the maximum and minimum human resource that would be required…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: After the first month of a project, the Actual Cost was $400 and the planned cost for the first…
A: Given, Actual cost, AC= $400 Planned cost or Budget, BAC = $500 Work complete= 50% a) Cost…
Q: [Project Management] Because a housing project is running late, the developer will need to complete…
A: Given Activity prior normal days crash days A - 9 9 B A 9 9 C B 14 12 D B 18 11 E…
Q: We reduce Activity B to 4 weeks on each of the six houses. What affect will that have on the project…
A: There are 6 identical houses to be built. One house requires 15 weeks and involves 3 activities A,…
Q: Assess the planning, monitoring, and controlling of projects using the Program Evaluation and Review…
A: The Program Evaluation Review Technique (PERT) is a technique used in project management to…
Q: To ensure project can be done with the available resources, time and budget is termed as
A: Introduction In human resource management , while creating plan for project there are various roles…
Q: snip
A: The critical path method is a project management method that evaluates the time required to complete…
Q: What is the effect of overlapping activities that are not on the critical path?a. An earlier project…
A: The correct answer is (c)
B. What is the expected project completion time?
7 weeks
8 weeks
9 weeks
6 weeks
C. Which are the critical activities?
A, B, C, F, G and I
A, B,C, G and I
A, B, C, D, E, F and I
A, B, C,D, F, G and I
Step by step
Solved in 2 steps with 1 images
- 1.The chief engineer of firm XYZ is responsible for supervising the construction work of a road. He has identified the activities and their durations for each stage of operation. Activity Duration (days) Preceding activities A 5 - B 10 - C 1 - D 8 B E 10 B F 9 B G 3 A,D H 7 A,D I 4 F J 3 F K 5 C,J L 8 H,E,I,K M 4 CJ Draw a network diagram (AOA) for this road construction project. Which are the critical activities? How long the project will take?I. Gannt Chart. Contractors for a building restoration project will have to do the following: For the precedence relationships of the activities, assume the following: 1. The wall/ceiling activities, the flooring activities, and the exterior activities are listed in the order in which they are to be performed. 2. Cleaning and repairing the walls/ceilings, removing the old carpeting, and sanding and repairing the exterior must precede any painting activity (interior and exterior). 3. The walls/ceilings must be painted before the hardwood flooring is installed, stained, and sealed. 4. All painting (interior and exterior) must be completed before new rugs and carpet runners are installed. 5. Stripping the wallpaper, removing the carpeting, and sanding and repairing the exterior may all start at the same time. Wall/Ceiling Activities A Strip the existing wall paper B Clean and repair the walls/ceilings C Paint the walls/ceilings Flooring Activities D Remove old carpeting E Lay a floor…Task A. High Level Analysis B. Selection of Hardware Platform C. Installation and Commissioning of hardware D. Detailed Analysis of core modules E. Detailed Analysis of supporting Modules F. Programming of core modules 3 H. 1 G. Programming of supporting Modules Quality Assurance of core modules Quality Assurance of supporting Modules J. Core module training I. 1 1 K. 1 1 Development and QA of accounting Report L. Development and QA of Management reporting M. Development of Management Information System N. Detailed Training 1 L 1 I, J, K, M Create a Gantt Chart starting May 1, 2022. No day-offs Duration 1 1 2 2 2 2 Prerequisite A B A D D E F G C, H E E
- 2. Chris received new word proces which she intends to purchase a next week. Chris decided that sh of the activities she will need to a. Arrange the activities into tw b. (1) Construct an AOA netwo: (2) Construct an AON diagra c. Determine the critical path an d. What are some possible reasc8. A manufacturer of sails for small boats has a group of custom candles awaiting the latest two processing operations before they are sent to customers. Operation 1 must be performed before operation 2, and the tasks have requirements for different times for each operation. The required hours are the following: assignment: 1 2 3 4 5 6 7 8 9 10 Operation 1: 1 5 8 3 9 4 7 2 4 9 Operation 2: 8 3 1 2 8 6 7 2 4 1 A. Use Johnson's rule to determine the sequence excellent. B. Draw a Gantt chart for each operation.5. During the construction of a house, six joists of 24 ft each must be trimmed to the correct length of 23 ft. The operations for cutting a joist involve the following sequence: Operation 1. Place joist on saw horses 2. Measure correct length (23 ft) 3. Mark cutting line for circular saw 4. Trim joist to correct length 5. Stack trimmed joist in a designated area Time (seconds) 15 5 5 20 20 Three persons are involved: Two loaders must work simultaneously on operations 1,2, and 5, and one cutter handles operations 3 and 4. There are two pairs of saw horses on which untrimmed joists are placed in preparation for cutting, and each pair can hold up to three side-by-side joists. Suggest a good schedule for trimming the six joists.
- 1. Using Microsoft Excel TM prepare a Gantt Chart for the following project. Activity Predecessor(s) Duration (Days) 1. Forming the problem statement 2. Identifying functional requirements 3. Identifying constraints and limitations 4. Defining a schedule 5. Defining the design parameters 6. Identifying alternatives 7. Evaluating and analyzing alternatives 8. Select a solution 9. Gather supplies 10. Construct prototype 11. Test performance 12. 1 1 1 1 1 2,3 1 2 1 2 7 1 8 4 10 1 Redesign 13. 11 2 Demonstrate solution to 12 1 class 5 CO2. Bjorn and Thor are plumbers who have been scheduled to work on the construction of a new school building. Just before the start of the project, Bjorn broke his arm and cannot work on the project. Now Thor has to handle his own activities as well as Bjorn's. Level the project Gantt chart so that Thor is responsible for activities 3, 4, 6, and 7. What is the new estimated completion date for the project? O 1 2 3 45 6 67 8 Task Task Name Mode * ✰ ✰ Activity 1 activity 2 Activity 3 activity 4 Activity 5 Activity 6 Activity 7 Activity 8 Feb 17, 19 SIMTIWITIFS |Feb 24, '19 SIMT|WT|FISSMITIWIT Bjorn Thor Mar 3, 19 Bjorn ThorStudents shall, with a point of view of him/herself as project manager (PM), submit a Project Management Plan (PMP) for the given engineering project below: - “Procurement & Installation of Emergency Generator at Fire station” Students are allowed to propose their own project, given that the projects shall have enough scale to address the element described below:- a. Student should produce a project definition statement regarding the proposed project. b. Student should propose a suitable project team to carry out the project. Student should in the PMP describe the duties and power of different team memebrs in the project. c. The PMP shall include a risk management plan, which student shall identify, analyse and proposed mitigations measures for smooth delivery of the project deliverables. The risk manamgenet plan shall include a risk register d. The PMP shall include a quality management plan, which student shall propose a method statement to control the quality of the delivery of…
- 1. Define the purpose of the sequence and activity diagramsEX6-12 (Algo) You are creating a customer database... You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Given the information below, complete the forward and backward pass, compute activity slack, and identify the critical path. How long will this project take? ABCDACHSX K L Description Systems Subsystem A design Subsystem B design Subsystem C design Program A Program B Program C Subsystem A test Subsystem B test Subsystem C test Integration Integration test days. Predecessor None A A A B с D E F G H, I, J K Time (days) 7 3 1 3 5 15 5 3 3 5 31. The activities involved in the construction of a certain project are given in Table 1. One resource type will be used during the contract. Determine minimum level of the resource required to complete the project. a) Draw the precedence network and perform the CPM calculations. b) Prepare the Bar chart, Resource load table and and resource histogram (for both Early start time and Late start time) c) Allocate the required resources, then level them so that the contractor does not use more than six laborers at any time. Preceded Duration by Activity Laborers (Days) A 5 7 4 А D A,B 5 C,D 2 2. m3 3. 2. B.