Concept explainers
ZEN Ltd signs a contract on 30 June 2019, agreeing to build a bridge for XYN at a contract price of $20 million. XYN will be in control of the asset throughout the construction process. ZEN estimates that construction costs will be as follows:
Year Ending Cost
30th June 2020 $ 5,000,000
30th June 2021 $ 8,000,000
30th June 2022 $ 3,000,000
Total $16,000,000
The contract provides that XYN will make payments on 30 June of each year as follows:
2020 $ 4,000,000
2021 $ 10,000,000
2022 $ 6,000,000
Total $20,000,000
The contract is completed as expected on 30 June 2022. Assume that actual costs and cash collections with expectations and that cost (an input measure) is used as the basis for assessing progress on the car contract.
Required:
(a) Calculate the income and gross profit recognised each year 2020, 2021, 2022.
(b) Prepare the
Step by stepSolved in 2 steps
- Rogers Ltd. has entered into a contract beginning in February 2020 to build two warehouses for ocean Ltd. The contract is a non-cancellable fixed price contract for $9.4 million. The following data pertain to the construction period. 2020 2021 2022 Costs for the year $3,285,000 4,015,000 1,800,000 Estimated costs to complete 4,015,000 1,825,000 -0- Progress billings for the year (non-refundable) 2,960,000 3,440,000 3,000,000 Cash collected for the year 2,605,000 3,490,000 3,305,000 a) Using the percentage-of-completion method, calculate the percent complete for each year of the contract. b) Calculate the amount of the gross profit to be recognized each year of the contract. c) Prepare the journal entries for 2020 and 2021. (Use Materials, Cash, Payables for costs incurred to date.) d) What is the balance in the Contract Asset/Liability account at December 31, 2020 and 2021? Show how the construction contract would be reported on the SFP…arrow_forwardIndiana Company began a construction project in 2024 with a contract price of $162 million to be received when the project is completed in 2026 During 2024 Indiana incurred $35 million of costs and estimates an additional $15 million of costs to complete the project Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed in 2025, Indiana incurred additional costs of $59 milion and estimated an additional $38 million in costs to complete the project indiana Note: Do not round intermediate calculations. Multiple Choice recognized $911 milion gross profe on the project in 2025 recognized $9.00 million gross prefit on the project in 2025 ced $3000 mon gress profe on the project in 2025arrow_forwardIn 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 3,344,000 $ 3,960,000 $ 1,645,600 Estimated costs to complete as of year-end 5,456,000 1,496,000 0 Billings during the year 2,800,000 4,504,000 2,696,000 Cash collections during the year 2,600,000 4,400,000 3,000,000 Assume that Westgate Construction’s contract with Santa Clara County does not qualify for revenue recognition over time.Required:1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred).2-b. In the journal below, complete the necessary journal entries…arrow_forward
- Chung Corp. thought of constructing their own building for P40,000,000 which they plan to start and finish until December 31, 2021. Chung made the following payments, based on the construction contract, during 2021.· January 31- P5,000,000· February 28- P8,000,000· July 1- P15,000,000· August 31- P10,000,000· November 30- P2,000,000Chung secured a 10%, 4-year noted dated January 1, 2021, specifically intended for the construction. The amount was P20,000,000.Also, the entity had other debts outstanding as follows:· 8%, 6-year note dated December 31, 2019- P18,000,000· 12%, 7-year noted dated December 31, 2018 - P22,000,000 What is the total cost of the building constructed?arrow_forwardAssume that Crane Construction Company has a non-cancellable contract to construct a $4,640,000 bridge at an estimated cost of $4,176,000. The contract is to start in July 2023, and the bridge is to be completed in October 2025. The following data pertain to the construction period. (Note that, by the end of 2024, Crane has revised the estimated total cost from $4,176,000 to $4,228,200.) Assume that progress billings are non-refundable. Costs to date (12/31) Estimated costs to complete (12/31) Progress billings during the year Cash collected during the year (a1) Account Titles and Explanation (To record cost of construction) (To record progress billings) (To record collections) (To record revenues) 2023 (To record construction expense) 3,173,760 $1,002,240 $2,959,740 $4,228,200 994,000 2024 834,960 1,268,460 2,483,000 Prepare all journal entries required for Crane to account for this contract for 2023. (Credit account titles are automatically indented when the amount is entered. Do not…arrow_forwardIn 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $2,581,000 $2,347,000 $3,049,200 Estimated costs to complete as of year-end 6,319,000 2,772,000 0 Billings during the year 2,090,000 2,838,000 5,072,000 Cash collections during the year 1,845,000 2,900,000 5,255,000 Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the…arrow_forward
- Assume that Cullumber Construction Company has a non-cancellable contract to construct a $4,600,000 bridge at an estimated cost of $4,140,000. The contract is to start in July 2023, and the bridge is to be completed in October 2025. The following data pertain to the construction period. Assume that progress billings are non-refundable. 2023 2024 2025 Costs to date (12/31) $1,076,400 $2,980,800 $4,657,500 Estimated costs to complete (12/31) 3,063,600 1,676,700 Progress billings during the year 957,000 2,422,000 1.221,000 Cash collected during the year 774,000 1,881,000 1,945,000 The revised estimates for the bridge contract are as follows. 2023 Original Estimates 2024 Revised Estimates Contract price $4,600,000 $4,600,000 Estimated total cost 4,140,000 4,657,500* Estimated gross profit $460,000 Estimated loss $(57,500) *$2,980,800+ $1,676,700 (a1) * Your answer is incorrect. Under the percentage-of-completion method, calculate the total loss in 2024. Total loss in 2024 $ LA 156400arrow_forwardShow all workings?arrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education