The gross requirements for Item X are specified for the beginning of weeks 1 through 8 in the table that follows. The product structure for the item is given in the figure: The lead time of each item is specified within square brackets. For example, the lead time for Item X is 1 week. The number of units required for each lower level part is specified within parentheses. For example, each unit of Item B requires 1 unit of Part C and 2 units of Part D. Product Structure for Item X Level 0 Level 1 + A Level 2 + Level 3 + C (1) [LT 1] H (1) [LT 1] K (1) [LT 3] B (1) [LT 1] Gross Requirement On-hand Inventory Planned Order Release D (2) [LT 2] M (2) [LT 1] X [LT 1] Z (2) [LT 1] N (1) [LT 1] What is planned order release for Item H in Week 3? 310 Specify the number of units. C (4) [LT 1] Item X Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 0 0 0 0 0 55 90 55 What is planned order release for Item H in Week 4? 415 Specify the number of units. H (1) [LT 1] There are no units in inventory and no scheduled receipts. Complete the MRP calculations to determine the planned order releases for Item H. (Note that Item H occurs twice on the product structure. Note also that you will need to complete the calculations for other items on the Product Structure.) What is planned order release for Item H in Week 5? 220 Specify the number of units. K (1) [LT 3]

Intermediate Algebra
19th Edition
ISBN:9780998625720
Author:Lynn Marecek
Publisher:Lynn Marecek
Chapter12: Sequences, Series And Binomial Theorem
Section12.3: Geometric Sequences And Series
Problem 12.57TI: What is the total effect on the economy of a government tax rebate of $1,000 to each household in...
icon
Related questions
Question
The gross requirements for Item X are specified for the beginning of weeks 1 through 8 in the table that follows. The
product structure for the item is given in the figure: The lead time of each item is specified within square brackets. For
example, the lead time for Item X is 1 week. The number of units required for each lower level part is specified within
parentheses. For example, each unit of Item B requires 1 unit of Part C and 2 units of Part D.
Product Structure for Item X
Level 0
+
Level 1
+
4
Level 2
+
Level 3
+
C (1)
[LT 1]
H (1)
[LT 1]
K (1)
[LT 3]
B (1)
[LT 1]
Gross Requirement
On-hand Inventory
Planned Order Release
D (2)
[LT 2]
M (2)
[LT 1]
X
[LT 1]
Z (2)
[LT 1]
N (1)
[LT 1]
What is planned order release for Item H in Week 3?
310 Specify the number of units.
C (4)
[LT 1]
Item X
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8
0
0
0
0
0
55
90
55
What is planned order release for Item H in Week 4?
415 Specify the number of units.
H (1)
[LT 1]
There are no units in inventory and no scheduled receipts.
Complete the MRP calculations to determine the planned order releases for Item H. (Note that Item H occurs twice on the
product structure. Note also that you will need to complete the calculations for other items on the Product Structure.)
What is planned order release for Item H in Week 5?
220 Specify the number of units.
K (1)
[LT 3]
Transcribed Image Text:The gross requirements for Item X are specified for the beginning of weeks 1 through 8 in the table that follows. The product structure for the item is given in the figure: The lead time of each item is specified within square brackets. For example, the lead time for Item X is 1 week. The number of units required for each lower level part is specified within parentheses. For example, each unit of Item B requires 1 unit of Part C and 2 units of Part D. Product Structure for Item X Level 0 + Level 1 + 4 Level 2 + Level 3 + C (1) [LT 1] H (1) [LT 1] K (1) [LT 3] B (1) [LT 1] Gross Requirement On-hand Inventory Planned Order Release D (2) [LT 2] M (2) [LT 1] X [LT 1] Z (2) [LT 1] N (1) [LT 1] What is planned order release for Item H in Week 3? 310 Specify the number of units. C (4) [LT 1] Item X Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 0 0 0 0 0 55 90 55 What is planned order release for Item H in Week 4? 415 Specify the number of units. H (1) [LT 1] There are no units in inventory and no scheduled receipts. Complete the MRP calculations to determine the planned order releases for Item H. (Note that Item H occurs twice on the product structure. Note also that you will need to complete the calculations for other items on the Product Structure.) What is planned order release for Item H in Week 5? 220 Specify the number of units. K (1) [LT 3]
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 1 images

Blurred answer
Recommended textbooks for you
Intermediate Algebra
Intermediate Algebra
Algebra
ISBN:
9780998625720
Author:
Lynn Marecek
Publisher:
OpenStax College
Holt Mcdougal Larson Pre-algebra: Student Edition…
Holt Mcdougal Larson Pre-algebra: Student Edition…
Algebra
ISBN:
9780547587776
Author:
HOLT MCDOUGAL
Publisher:
HOLT MCDOUGAL