Question
The free-haul distance in a highway construction contract is 150m and the
overhaul price is $15/m3 .station. determine the extra compensation that must be paid to the contractor to balance the cut and fill between balance points (A) and (B) and (B) and (C).
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 2 steps with 2 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Similar questions
- A Highway contractor has four locations A, B, C, and D on a road contract which crushed stone is to be delivered. The stone, which is all of the same quality is to be supplied from three quarries 1, 2, and 3. The table below shows the relative transportation cost per cubic meter of transporting stone from each quarry to each site. However, the contractor discovered a technical problem in the third quarry, which results in a temporary shutdown of the facility. Based on this new condition, the contractor must deliver the crushed stone from the first and the second quarries only. Any shortage in the required crushed stone has to be covered from an external source. a) What is the optimal allocation of the crushed stone from each quarry to each location under the new circumstances? b) What is the transportation cost corresponding to the solution obtained in part a? c) Which of the four sites are affected by the shortage that results from the shutdown of the third quarry?arrow_forwardLion heen construcied belweh the mainland and an island The total cost areluding tolls) to travel across the bridge is expressed as C- 50+0.5V, where Visthe ber o veh/h and C'is thc cost/veh in cents. The demand for travel across the bridue is V 2500-10C O Determine the volume of traffle across the bridge. a toll of 25 cents is added, what s the volume across the bridge? What volume Would be expected with a 50 cent increase Aelbooth is to be added, thus reducing the travel time to cross the bridge. The new nction is C- 50 + 0.2V. Determine the volume of traffic that would cross the bridge. d Determine the toll to yicld the highest revenue for demand and supply function in part (a), and the associated demand and revenue.arrow_forwardunderwhat condition would you preferborrowing new materials from a borrow pit for highwayembankmentarrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- Structural Analysis (10th Edition)Civil EngineeringISBN:9780134610672Author:Russell C. HibbelerPublisher:PEARSONPrinciples of Foundation Engineering (MindTap Cou...Civil EngineeringISBN:9781337705028Author:Braja M. Das, Nagaratnam SivakuganPublisher:Cengage Learning
- Fundamentals of Structural AnalysisCivil EngineeringISBN:9780073398006Author:Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel LanningPublisher:McGraw-Hill EducationTraffic and Highway EngineeringCivil EngineeringISBN:9781305156241Author:Garber, Nicholas J.Publisher:Cengage Learning
Structural Analysis (10th Edition)
Civil Engineering
ISBN:9780134610672
Author:Russell C. Hibbeler
Publisher:PEARSON
Principles of Foundation Engineering (MindTap Cou...
Civil Engineering
ISBN:9781337705028
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Cengage Learning
Fundamentals of Structural Analysis
Civil Engineering
ISBN:9780073398006
Author:Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:McGraw-Hill Education
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning