Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
4th Edition
ISBN: 9781337399395
Author: Pratt, David J.
Publisher: Cengage,
Bartleby Related Questions Icon

Related questions

bartleby

Concept explainers

Question

V7

RIBNA has estimated 200 m³ concrete and 800
dowels to complete a concrete paving project. 60
work hours is estimated to make dowel baskets
and anchor them to the base course. A slipform
paver, in 40 work hours, spreads, consolidates,
and finishes the concrete slab. On a study date,
600 dowels in 45 work hours and 120 m³ concrete
in 30 work hours are used.
In the above scenario, the SPI for the project is:
O 0.85
O unknown. more information is required.
O 1.15
O the same as its CPI
expand button
Transcribed Image Text:RIBNA has estimated 200 m³ concrete and 800 dowels to complete a concrete paving project. 60 work hours is estimated to make dowel baskets and anchor them to the base course. A slipform paver, in 40 work hours, spreads, consolidates, and finishes the concrete slab. On a study date, 600 dowels in 45 work hours and 120 m³ concrete in 30 work hours are used. In the above scenario, the SPI for the project is: O 0.85 O unknown. more information is required. O 1.15 O the same as its CPI
Expert Solution
Check Mark
Knowledge Booster
Background pattern image
Civil Engineering
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Cengage,