The closest value to the pessimistic project completion time is

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
icon
Related questions
Question
I need the answer quickly
Before answering the following questions, you must draw
the arrow diagram, rectangles, network calculations, and
the project diagram, the details of which are shown in the
table below.
Time (week)
Activity Dependency
Resource
b
a
1.5
2
2.5
2
2.5
6
1
2
А, В
B
1.5
2.5
2
0.5
1.5
2
F
D
1
3
D, E
C, F, G
C, G
G
3
3.5
3
3
4
1.5
2
2.5
10- The closest value to the pessimistic
project completion time is
21.4
19.4
17.2
All options are incorrect
19.2
13.9
11.7
17.1
14.9
375
221
ABCDEECHI
Transcribed Image Text:Before answering the following questions, you must draw the arrow diagram, rectangles, network calculations, and the project diagram, the details of which are shown in the table below. Time (week) Activity Dependency Resource b a 1.5 2 2.5 2 2.5 6 1 2 А, В B 1.5 2.5 2 0.5 1.5 2 F D 1 3 D, E C, F, G C, G G 3 3.5 3 3 4 1.5 2 2.5 10- The closest value to the pessimistic project completion time is 21.4 19.4 17.2 All options are incorrect 19.2 13.9 11.7 17.1 14.9 375 221 ABCDEECHI
Expert Solution
steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,