The closest value to the optimistic time to complete the project is *
Q: The greater percentage of the project budget is spent in which stage of the project life cycle?…
A: Operation management in an organization aims at providing the highest efficiency possible. It…
Q: Calculate the critical path for this project The Critical path is _______________ and the project…
A: The critical path is the path that takes the longest time to complete the project network.
Q: Which activity should be crashed to reduce the project completion time by one day? -Activity E…
A: In this given problem, first, calculate the project completion time. There are two possible paths.…
Q: You are an engineer working for a large manufacturing company. You have recently been promoted to…
A: Project management responsibilities are, Activity and resource planning. Organizing and motivating…
Q: How can a Project Manager strike a balance and catch up control the budget and resources?
A: With regards to cost control in project management, it tends to be trying to figure and oversee…
Q: You are the project manager on a $1,000,000 housing development project that has an estimated…
A: Total budget = $1,000,000 Duration of the project = 5 months Estimated project completion at the end…
Q: a) What is the probability that the project can be completed in 25 days or fewer?
A: The expected activity time is the time taken by the particular activity to complete the project…
Q: To what extent do agile and predictive techniques aim to fulfill the project client's needs?
A: Agile technology refers to managing a project by breaking the overall project in numerous stages.…
Q: ffing related to each stage of the project life cycle?
A: Phases may be used by project managers or the organization as a way to better manage projects and…
Q: (d) What is the shortest possible time it will take to complete the project?
A: Below is the solution:-
Q: Q1: Draw the allocation of resources chart on the earliest and latest start time for the project…
A: In given network diagram critical path will pass the activities B−E−G−K duration of the…
Q: What is a Pareto analysis, and how does a project manager use it during quality control?
A: The term Pareto analysis refers to the use of a statistical approach in the decision-making process…
Q: In a predictive project team and an agile project team, what is the function of the project leader?
A: Project management involves the planning and organization of business resources to carry out a…
Q: Your project MUST meet the deadline but you are slightly over budget at this point. The original…
A: Budget at completion (BAC) is given as $125,000, actual cost (AC) is $80,000, and planned value (PV)…
Q: a. What is the probability the project will be finished weeks or less? b. What is the probability…
A: Project management is the management in which different types of knowledge and skills are needed to…
Q: What could the project manager do differently the next time he or she is involved in a project where…
A: Project management: It is the process of managing the overall work of the project to achieve some…
Q: MODELLING AND SIMULATION 1. Is it possible to conduct all the orientation activities in a single…
A: Modeling and simulation (M&S) is the utilization of models (e.g., physical, numerical, or…
Q: What are the key steps in the implementation of a project plan?
A: The project management framework includes the phases of planning, execution, tracking, and closure.…
Q: The majority of the project budget is expended upon: Select one: O a. Project termination. b.…
A: A project budget is the total projected costs needed to complete a project over a defined period of…
Q: a. Determine the project completion time if no activity is crashed. What would be the total cost of…
A: Below is the solution:-
Q: 1- Reducing project time Direct costs Normal Crash ID Time Cost Time Cost E 5. $500 4. $G00 10 9. 10…
A: At first we have to find out the critical path. Please follow the attached image for the same;
Q: of the project, the same principles of project management (2) Whatever the apply. (a) quality (b)…
A: Project management: It is the utilization of methodologies, devices, and methods to progressively…
Q: d. Determine the probability that the team and the contractor will be in place and the project…
A: Based on the 3-time estimates given, we find the Expected duration and Variance for each activity as…
Q: One of the tasks available to companies for the purpose of knowing what is appropriate and what is…
A: A project is nothing but a temporary endeavor or venture to manufacture a new and different or…
Q: O A-B-D-F-G-H O A-C-E-H O A-B-D-E-H O A-C-E-F-G-H c. How many weeks will it take to complete the…
A: The critical path method is a project management tool that is used to help plan and schedule the…
Q: a) What is the expected time to complete the project?
A: The expected activity time is the time taken by the particular activity to complete the project…
Q: When will the project be completed?
A: Project network diagram is the diagram that visually represent the project activities and their…
Q: Nhat is the overall duration of the project (in weeks)? 32 weeks Nhat is the earliest week you could…
A:
Q: y is project management the core of every project? 2. Why would you like to become a project…
A: Project management is important because it ensures what is being delivered, is right, and will…
Q: How do agile and predictive project methodologies attempt to meet the project client's requirements?
A: Project management is the process of putting policies, plans, skills, knowledge, and experience into…
Q: "-1" SV indicate the project is behind schedule. Select one: True False
A: Positive shows that the undertaking is running in front of endorsed plan. Negative implies that the…
Q: (4) involved in the project. (a) Activity plan (b) factors plan (c) budget plan (d) none of these…
A: Planning includes all the activities needed to pick a analytic thinking team, assign members of the…
Q: Describe three aspects of a project that might involve some degree of uncertainty
A: As we all know that there are various business and marketing organizations. Also, there are…
Q: Below is the details about a. What is the maximum and minimum human resource that would be required…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: 1- Reducing project time Direct costs Normal Crash ID Time Cost Time Cost E 5. $500 $600 10 B. 10…
A: Find the Given details below: Activity Normal duration (NT) Normal cost (NC) ($) Crash duration…
Q: hat should be done by upper management to assist the new project manager?
A: In an organization, there are different roles and responsibilities based on the degree of skills and…
Q: Who needs to be involved in assessing the cost of a project?
A: To use parametric estimating, first divide a project into units of work. Then, you must determine…
Q: 1/ For the project data shown in the table below. Find the expected time to achieve 45% (Assume that…
A: ANSWER IS AS BELOW:
Q: After the first month of a project, the Actual Cost was $400 and the planned cost for the first…
A: Given, Actual cost, AC= $400 Planned cost or Budget, BAC = $500 Work complete= 50% a) Cost…
Q: How do we estimate the likelihood of a project being finished by a certain date? In this…
A: Project Evaluation and Review Technique (PERT) is a technique for evaluating and reviewing projects.…
Q: How are the principles of project management applied to manage a time ?
A: Using time effectively is the administration of the time spent, and progress made, on project…
Q: 2. You are asked to manage an upcoming project for a client based in Chicago. Your supervisor,…
A: Note: - Since we answer only up to 3 questions, we will answer questions 1, 2, and 3 for your…
Q: How can a lesson learned to be documented and made available to other project teams?
A: The lesson learned during the project should be documented in a formal way. It can be identified and…
Q: 1- The number of critical paths in the project is All options are incorrect O
A: One of the methods to find the longest duration that a project would take to complete is the…
Step by step
Solved in 3 steps with 3 images
- The following represents a project that should be scheduled using CPM: ACTIVITY ABCDEFGH А с IMMEDIATE PREDECESSORS IAABUDR C,D D,E F,G TIMES (DAYS) b a 1 1 3 - NTTTTE 1 1 1 1 2 m 5 WaNNASNU 2 5 4 2 2 6 3 ∞∞NWO3770 9 10 12 8You are in charge of a project at the local community center. The center needs to remodel one ofthe rooms in time for the start of a new program. Delays in the project mean that the center mustrent other space at a nearby church at additional cost. Time and cost data for your project arecontained in below table. Your interest is in minimizing the cost of the project to the communitycenter.Using the normal times for each activity, what is the earliest date you can complete the project?Suppose the variable overhead costs are $50 per day for your project. Also, suppose that thecenter must pay $40 per day for a temporary room on day 15 or beyond. Find the minimum-costproject schedule using below format.The AON diagram for the community center project is below. Crash 4 times and find total cost.PERT/CPM HOMEWORK (MOD 10) In the table below, you will see activities and times associated with each activity. Review the PowerPoint slides in Module 10 , before you start this assignment. Task Preceding Tasks to (optimistic) tm (most likely) tp (pessimistic) A NONE 2 3 10 B NONE 2 3 4 C A 1 2 3 D A 4 6 14 E B 4 5 12 F C 3 4 5 G D,E 1 1 7 1.) Draw the network using the table above. Make sure all 4 values (ES, EF, LS, LF) are listed on the network. 2.) What is the slack for each activity? What is the critical path? Show ALL of your work! 3.) Find the expected project completion time. What is the project variance? 4.) What is the probability that it would be in more than 14 days? Show ALL of your work. *The circle diagram picture is just an example of how it should look it is not apart of the problem in the chart
- Using your results from Problem 6,(a) Calculate the probability that the project will be completedin 38 weeks.(b) Calculate the probability that the project will be completedin 42 weeks2:30 PM ě 0.3KB/s 1ll 54 4G+ 00:15:12 Remaining Multiple Choice The primary difference between PERT and CPM is that CPM uses probabilities on the activity times and PERT does not. O. PERT considers activity costs and CPM does not. PERT can assign probabilities to activity times and CPM does not. CPM considers activity costs and PERT does not. 5 of 20 IIc. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 2 decimal places.) Project completion time d. What is the probability of completing this project within 16 days? (Use Excel's NORMSDIST() function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round "2" value to 2 decimal places and final answer to 4 decimal places.) Probability 10 00 days 09994
- Management Firm is a consulting company that specializes in the development of decision support systems. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Report generation 2 8 12 B Web scraping 4 9 11 C Testing A, B 1 1 1 (b) Using all paths through the project network, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.)Mueller & Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the 45-week completion date requested by the owner. The Mueller project manager prepared the following project network. Start A B F H 0 D E Finish Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities are as follows. Activity Optimistic Most Probable A 4 8 Pessimistic 12 B 6 7 8 C 6 12 18 D 3 5 7 E 6 9 18 F 5 8 17 G 10 15 20 H 5 6 13What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Normal Cost $800 $200 $600 $750 $1,200 Normal Crash Activity Time (days) Time (days) 4 3 8 6 The total cost of crashing the project by 4 days is $ ABCDE 487 355 (Enter your response as a whole number.) Total Cost with Crashing Immediate Predecessor(s) $1,500 $1,650 By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.) Each Activity Should be Reduced BY (days) Activity A B C D E $1,100 $600 $650 A C
- A project consists of five activities as shown in the following table. Activity Floor sanding Floor buffing Paint mixing Wall painting Ceiling painting Optimistic Time (hr) Most Probable Time (hr) 4 4 0.5 2 3 5 5 Сл 1 3 7.5 Pessimistic Time (hr) 6 6 1.5 10 9 Naturally, the paint mixing precedes the painting activities. Also, both ceiling painting and floor sanding must be done prior to floor buffing. (a) Construct the PERT/CPM network for this problem.Due to population growth in the area, the new Liberty High School has just opened in a local school district. The athletic director at Liberty High is planning the launch of the school's track and field team. The first team practice is scheduled for April 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are listed in the following table. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Meet with board 1 1 2 B Hire coaches A 4 6 8 C Conduct fundraiser A 2 4 6 D Announce program B, C 1 2 3 E Meet with coaches B 2 3 4 F Order team equipment A 1 2 3 G Register athletes D 1 2 3 H Reserve buses for meets G 1 2 3 I Plan first practice E, H, F 1 1 1 (a) Draw a project network. A project network with 11 activities and 13 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B, to activity C, and to activity F. Activity B…Due to population growth in the area, the new Liberty High School has just opened in a local school district. The athletic director at Liberty High is planning the launch of the school's track and field team. The first team practice is scheduled for April 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are listed in the following table. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Meet with board 1 1 2 B Hire coaches A 4 6 8 C Conduct fundraiser A 2 4 6 D Announce program B, C 1 2 3 E Meet with coaches B 2 3 4 F Order team equipment A 1 2 3 G Register athletes D 1 2 3 H Reserve buses for meets G 1 2 3 I Plan first practice E, H, F 1 1 1 (a) Draw a project network. (b) Develop an activity schedule. (Round your answers to two decimal places.) (c) What are the critical activities? (Enter your answers as a comma-separated list.) What is the expected project…