Question
After the first month of a project, the Actual Cost was $400 and the planned cost for the first month was $500. Currently, only 50% of the work have been completed. Based on this information, calculate the following:
a.Cost Performance Index
b.Estimate to Complete
c.Estimate at Completion
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by stepSolved in 2 steps
Knowledge Booster
Similar questions
- d) What is the critical path and project completion time? e) What is the probability that the job will finish in 33 days or less? f) Submit your excel filearrow_forwardA project manager reports a project with a CPI of 1.08 and a SPI of .98. What do these metrics tell you about their project?arrow_forwardAssume you are the project manager and based on your customer's requirements you have determined there are four main tasks in a Dream Backyard project and have assigned each a TBC. Specifically, the customer wants the backyard leveled (Task 1 $15,000); wants a covered outdoor kitchen with a hot tub and firepit (Task 2 - $20,000), a retaining wall with fencing built- in (Task 3-$25,000), and a pool with waterfall (Task 4- $60,000). You estimate this will take 5 weeks to complete. The costs are budgeted as follows: Budgeted Per Week (in 000's) TBC 1 2 3 4 5 Task 1 6 6 3 4 Task 2 2 3 10 4 1 8 7 8 6 4 Task 3 25 Task 4 60 10 25 20 5 What is the total cumulative TBC? What is TBC at the end of week 4? The total TBC is $120,000 The TBC at the end of the week 4 is $110,000 ssume 4 weeks have passed and these are the actual costs per week: Actual Costs Per Week (in 000's) 1 2 3 4 Task 1 12 5 3 Task 2 4 7 16 4 Task 3 10 5 Task 4 11 17 What is the CAC at the end of week 4? 1228 15 20 6 15arrow_forward
- You are the project manager of the softwaration project in the table below. You would like to find the minimum-cost schedule for your project. There is a $500-per-week penalty for each week the prop delayed beyond week 25. In addition, your project team determined that indirect project costs are $2,000 per week. 9 Normal Activity Immediate Predecessor(s) Time (weeks) 1 A B C D E F G H 1 a. What would be your target completion week? The target completion week is week A A, B B D E. F G C.F (Enter your response as an integer.) b. How much would you save in total project costs with your schedule? Total Savings S (Enter your response as an integer) 79832N 10 12 8 Normal Cost (S) 3,000 3,000 10,000 3,000 4,000 2,000 3,000 5,000 2,000 Crash Time (weeks) 1 58829136 Crash Cost ($) 3,000 6,000 12,000 9,000 5,000 5,000 9,000 7,000 8,000arrow_forwardI need solve this question in project managerarrow_forwardCase study is attached. Please read the Case study Manchester United Soccer Club answer the following Questions: 1.Make a list of the major deliverables for the project and use them to develop a draft of the work breakdown structure for the tournament that contains at least three levels of detail. What are the major deliverables associated with hosting an event such as a soccer tournament?2.How would developing a WBS alleviate some of the problems that occurred during the first meeting and help Nicolette organize and plan the project?3.Where can Nicolette find additional information to help her develop a WBS for the tournament?4.How could Nicolette and her task force use the WBS to generate cost estimates for the tournament? Why would this be useful information? Note: - Note that each question should be answered in a minimum of 300 words.- Be typed, double spaced, using Times New Roman font (size 12), with one inch margins on all sides and heading; citations and references must…arrow_forward
- If we used AW analysis instead of PW analysis to select a project, it will give us a different selection . True or false ?arrow_forwardThe managers at AllBirds have operations in multiple countries, which operate on different financial management systems. This has been increasingly challenging for the company, so the Justin is looking to consolidate and integrate the financial management across all locations into a single software system that can operate across the national boundaries. This is a new, complicated and lengthy project, so Justin has identified a set of activity categories that will need to be carefully managed, as noted in the table. What is the probability that project can be completed two months early?arrow_forwardProblem 3: Kelly Melford Kelly Melford and her team are working on redesigning a client's home. The client requested Kelly for the project to be completed sooner. Kelly asked her assistant to collect information from her team on the project. Her assistant organized the information she got into a table. The information is given in weeks. Based on the information below, prepare a comprehensive report that includes the following: 3. Your insights on the cost-time trade-off for this project. 4. Your recommended strategy for crashing the project.arrow_forward
- Based on the diagram in question 3, what happens to the project duration if Activity C is done at the same time as Activity D? The duration is shortened by 1 day The duration is lengthened by 1 day The duration is shortened by 4 days The duration is not affectedarrow_forward13.42 Activity A is worth $100, is complete, and actually cost $150 Activity B is worth $500, is 75% complete, and has actually cost $400 so far Activity C is worth $500, is 25% complete, and has actually cost $200 so far. What is the estimated cost to completion for the project?arrow_forwardThe following eight activities constitute an overall bar chart portrayal of a 4-month project. Two months after the start of the project. Activities A, C, D are completed, E is 50% complete and B is 25% complete. The total cost that has been spent is $10,500. For this project, using earned value concepts, determine the schedule and cost variance. Is the project ahead or behind schedule? Over or under budget? Activity A B VAHE с D F Cost $2,000 $8,000 $2,000 $5,000 $1,000 $15,000 Month 1 Month 2 Month 3 Month 4arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.