Tej Dhakar's company wants to establish kanbans to feed a newly established work cell. The following data have been provided.
Note:
This is a level production system.
Daily demand
|
200
units |
Production lead time
|
2.00
days |
Safety stock
|
1.00
day |
Kanban size
|
50
units |
How many kanbans are needed?
enter your response here
kanbans (round your response to the nearest whole number).Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 3 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- It takes Aaron 15 minutes to produce 10 widgets to fill acontainer and 5 minutes to transport the container to thenext station, where Maria works. Maria’s process takesabout 30 minutes. The factory uses a safety factor of 20%.Currently, five kanbans rotate between Aaron and Maria’sstations. What is the approximate demand for widgets?arrow_forwardneed kanban size as well as the bumber of kanbans please! Need only handwritten solution only (not typed one).arrow_forwardProblem 14-2 (Algo) A JIT system uses kanban cards to authorize movement of incoming parts. In one portion of the system, a work center uses an average of 99 parts per hour while running. The manager has assigned an inefficiency factor of 29 to the center. Standard containers are designed to hold 7 dozen parts each. The cycle time for parts containers is about 110 minutes. How many containers are needed? (Round up your answer to the next whole number.) Number of containersarrow_forward
- Cletus and Spike Company is implementing a Kanban system for a heated water bowl manufacturing line that produces 1,500 units in an eight-hour day. The heating element has a waiting time of 30 minutes and a processing time of one hour. The container size is 40 heating elements, and the safety factor is 15 percent. How many Kanban cards should be used? a. 9 b. 12 c. 2 d. 27arrow_forward22 A bottling plant fills 1,200 bottles every two hours. The lead time is 30 minutes and a container accommodates 140 bottles. The safety stock is 20 percent of expected demand. How many kanban cards are needed? Note: Round up your answer to the next whole number.arrow_forwardBipinarrow_forward
- Lou's Bakery has established that JIT should be used for chocolate chips due to the high probability of the kitchen heat melting the chips. The average demand is 140 cups of chocolate chips per week. The average setup and processing time is 1/8 day. Each container holds exactly 2 cups. The current safety stock factor is 9 percent. The baker operates five days per week. a. How many Kanbans are required for the bakery? Round your answer up to the whole number. Kanbans b. What is the maximum authorized inventory? Use the rounded value from the previous question. Round your answer to the nearest whole number. cups C. If the average setup and processing time is increased to 3/4 of a day due to a process change, how many Kanbans are required for the bakery? Round your answer up to the whole number. Kanbans What is the maximum authorized inventory under new conditions? Use the rounded value from the previous question. Round your answer to the nearest whole number. cupsarrow_forwardexplain how containers or cards are used in kanban systemarrow_forwardTooltron Manufacturing uses a Kanban system for a component. Daily demand is 410 units. Each container has a combined waiting and processing time of 1.6 days. If the container size is 30 and the alpha value (a) is 17 percent, how many Kanban card sets should be authorized? Round your answer up to the whole number. Kanban cards What is the maximum authorized inventory? Use the rounded value from the previous question. Round your answer to the nearest whole number. unitsarrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.