Activities/Assessments:
Activity 8
Shown below are the tasks, times, and precedence requirements for the work required
to assemble a copier machine. Production time per day = 480 minutes. Desired output
per day - 40 units.
TASK TASK TIME, mins
IMMEDIATE PREDECESSOR/S
10
B
11
A
B
B
D
4
E
12
A
F
3
C, D
G
7
F
н
11
3
E
G, H
ΣΤt - 6ε
1. What's the cycle time for this production line?
2. What's the theoretical minimum number of workstations that should be set up?
3. List the paths for this problem.
4. Draw the precedence diagram for this problem.
5. How many workstations should be set up in this production line?
6. Which tasks should be performed in each workstation?
7. Draw the diagram of the production line.
8. Calculate the efficiency of the production line.
Note: You may use either clustering or heuristics in assigning tasks to workstations
expand button
Transcribed Image Text:22:09 1 Instagram Activities/Assessments: Activity 8 Shown below are the tasks, times, and precedence requirements for the work required to assemble a copier machine. Production time per day = 480 minutes. Desired output per day - 40 units. TASK TASK TIME, mins IMMEDIATE PREDECESSOR/S 10 B 11 A B B D 4 E 12 A F 3 C, D G 7 F н 11 3 E G, H ΣΤt - 6ε 1. What's the cycle time for this production line? 2. What's the theoretical minimum number of workstations that should be set up? 3. List the paths for this problem. 4. Draw the precedence diagram for this problem. 5. How many workstations should be set up in this production line? 6. Which tasks should be performed in each workstation? 7. Draw the diagram of the production line. 8. Calculate the efficiency of the production line. Note: You may use either clustering or heuristics in assigning tasks to workstations
Expert Solution
Check Mark
Knowledge Booster
Background pattern image
Similar questions
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.