Q4: Consider the following table summarizing the details of a project Activity Predecessor(s) Duration (weeks) Most likely time Pessimistic time 8. Optimistic time A 3 6. 9. 4. 4. 5. 6. 3 3. 9. 4. 11 8. C,D C,D.E F 9. 6. H 3. 9. (a) Construct the project network. (b) Find the expected duration and variance of each activity. (c) Find the critical path and the expected projeet completion time. (d) What is the probability of completing the project on or before 30 weeks'? (e) If the probability of completing the project is 0.85-090 find the expected project completion time.

Engineering Fundamentals: An Introduction to Engineering (MindTap Course List)
5th Edition
ISBN:9781305084766
Author:Saeed Moaveni
Publisher:Saeed Moaveni
Chapter19: Probability And Statistics In Engineering
Section: Chapter Questions
Problem 2P
icon
Related questions
Question
I need the answer as soon as possible
Q4: Consider the following table summarizing the details of a project
Predecessor(s)
Duration (weeks)
Most likely time
5
Activity
Optimistic time
3
6.
Pessimistic time
8
9.
4.
D
4.
5.
6.
3
8.
B.
3.
9.
F
4
11
6.
C,D
8.
6.
C,D.E
2.
(a) Construct the project network.
(b) Find the expected duration and variance of each activity.
(c) Find the critical path and the expected projeet completion time.
(d) What is the probability of completing the proiect on or before 30 weeks'?
(e) If the probability of completing the project is 0.85.090 find the expected project completion time.
Transcribed Image Text:Q4: Consider the following table summarizing the details of a project Predecessor(s) Duration (weeks) Most likely time 5 Activity Optimistic time 3 6. Pessimistic time 8 9. 4. D 4. 5. 6. 3 8. B. 3. 9. F 4 11 6. C,D 8. 6. C,D.E 2. (a) Construct the project network. (b) Find the expected duration and variance of each activity. (c) Find the critical path and the expected projeet completion time. (d) What is the probability of completing the proiect on or before 30 weeks'? (e) If the probability of completing the project is 0.85.090 find the expected project completion time.
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Asphalt binders and mixtures
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Engineering Fundamentals: An Introduction to Engi…
Engineering Fundamentals: An Introduction to Engi…
Civil Engineering
ISBN:
9781305084766
Author:
Saeed Moaveni
Publisher:
Cengage Learning