Operations Manager of PT Radio Gaga is calculating production costs
a telecommunication radio taking into account the following needs:
i. Week 1 : 20 units
ii. Week 2 : 36 units
iii. Week 3 : 46 units
iv. Week 4 : 45 units
v. Week 5 : 20 units
vi. Week 6 : 26 units
It is known that there is inventory from the previous week as many as 20 units. Assuming 52
week per year, lead time booking for 1 week, setup cost of $40 and
holding cost of $0.75 per week, you are required to assist the Operations Manager of PT
Radio Gaga to calculate the estimated production cost as follows:
a. Calculate EoQ
b. Create a 6-week MRP Lot Sizing Table with EoQ method
c. Calculate Total Production Cost using EoQ method
d. Create a 6-week MRP Lot Sizing Table using the Lot method
for Lot
e. Calculate Total Production cost by using Lot for Lot method
F. Which method will PT Radio Gaga's Operations Manager take?
Trending nowThis is a popular solution!
Step by stepSolved in 2 steps
- The partially completed inventory record for the rotor subassembly in the table below shows gross requirements, scheduled receipts, lead time, and current on-hand inventory. a. Complete the last three rows of the record for an FOQ of 160 units. (Enter your responses as integers. A response of "0" is equivalent to being not applicable) Item: Rotor subassembly Gross requirements Scheduled receipts Projected on-hand inventory Planned receipts 15 1 65 160 H 2 10 3 50 4 35 Lot Size: FOQ-160 units Lead Time: 2 weeks Week 5 80 6 80 7 80 8 80 000 0000 0000arrow_forwardYou have developed the following simple product structure of items needed for your gift bag for a rush party for prospective pledges in your organization. You forecast 200 attendees. Assume that there is no inventory on ha nd of any of the items. Explode the bill of material. (Subscripts indicate the number of units required.)arrow_forwardThe president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next 8 months as follows: 2,200 January 1,400 May February 1,600 June 2,200 March April 1,800 1,800 July August 1,800 1,400 Her operations manager is considering a new plan, which begins in January with 200 units of inventory on hand. Stockout cost of lost sales is $100 per unit. Inventory holding cost is $25 per unit per month. Ignore any idle-time costs. The plan is called plan C. Plan C: Keep a stable workforce by maintaining a constant production rate equal to the average gross requirements excluding initial inventory and allow varying inventory levels. Conduct your analysis for January through August.arrow_forward
- Ripeka, the warehouse manager at Hine would like to update the company’s inventory locator system so that the picking operation can be streamlined. While conceptually simple to do, she knows that there will be several steps to the update process that will have to be carefully managed. She needs to complete upgrade and train her staff in operating the new system before the busy season, which is only 4 months away. She identifies the various activities, expected time duration, predecessors and costs, as shown in the table. Draw the AON Network, and then determine the critical path. [Show your workings, using the grid network.] Identify the project duration – is this project feasible within the required timeframe?arrow_forwardA factory has just received an order for 95 units of an end item, which are to be shipped at the start of week 8. Relevant information of the end item and the components is as follows. Lead Time On Hand Scheduled Item Order Direct (weeks) Inventory receipts Policy Components End item 15 lot for lot A(3), B(2) A 2 10 33 at week 3 lot for lot C(1), D(4) B. 2 20 15 at week 4 lot for lot D(2) min. of 500 lot for lot 100 20 Develop the material requirements plan (please print out an empty MRP table to work with), and determine how many units of component Care needed in the "planned order release". Input should be an exact number.arrow_forwardSolve fro Material Requirement Planningarrow_forward
- Qty Standard Labor Hour Raw Material В Standard Labor 2 Hours Raw Material INDEPENDENT DEMAND Period 1 2 3 4 5 6 Total Product A 1,000 1,000 1,000 1,000 1,000 1,000 6,000 Product B 500 500 ,500 500 16. Products A and B are produced on two different dedicated production lines. If both lines work on the same shift schedule, the ratio of workers on line A to workers on line B is A. 2:1 В. 2:3 С. 2:5 D. 4:1arrow_forwardPlease do not give solution in image format thankuarrow_forward4. Terminator, Inc., manufactures a motorcycle part in lots of 250 units. The raw materials cost for the part is $170, and the value added in manufacturing 1 unit from its components is $320, for a total cost per completed unit of $490. The lead time to make the part is 4 weeks, and the annual demand is 4,200 units. Assume 50 working weeks per year. a. How many units of the part are held, on average, as cycle inventory? ___ units. (Enter your response as an integer.) What is its value? $______ (Enter your response as an integer.) b. How many units of the part are held, on average, as pipeline inventory? _____units. (Enter your response as an integer.) What is its value? $______ (Enter your response as an integer.)arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.