Draw the AON Network, and then determine the critical path. [Show your workings, using the grid network.] Identify the project duration – is this project feasible within the required timeframe?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Ripeka, the warehouse manager at Hine would like to update the company’s inventory locator system so that the picking operation can be streamlined. While conceptually simple to do, she knows that there will be several steps to the update process that will have to be carefully managed. She needs to complete upgrade and train her staff in operating the new system before the busy season, which is only 4 months away. She identifies the various activities, expected time duration, predecessors and costs, as shown in the table.

  1. Draw the AON Network, and then determine the critical path. [Show your workings, using the grid network.]

  2. Identify the project duration – is this project feasible within the required timeframe?

Activities Immediate
Predecessors
A
B
с
D
E
F
G
H
A
A
B, C
B
D
с
E, F, G
Normal Time
(weeks)
3
2
3
7
2
2
2
1
Crash Time Activity
Cost ($)
(weeks)
2125
2
1
1
2
1
3000
4000
2500
9000
2400
4000
1200
500
Crash
Cost ($)
4000
5600
4500
12500
4900
8500
1200
500
Transcribed Image Text:Activities Immediate Predecessors A B с D E F G H A A B, C B D с E, F, G Normal Time (weeks) 3 2 3 7 2 2 2 1 Crash Time Activity Cost ($) (weeks) 2125 2 1 1 2 1 3000 4000 2500 9000 2400 4000 1200 500 Crash Cost ($) 4000 5600 4500 12500 4900 8500 1200 500
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.