Concept explainers
On February 1, 2024, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,375,000. During 2024, costs of $2,150,000 were incurred, with estimated costs of $4,150,000 yet to be incurred. Billings of $2,680,000 were sent, and cash collected was $2,400,000.
In 2025, costs incurred were $2,680,000 with remaining costs estimated to be $3,825,000. 2025 billings were $2,930,000, and $2,625,000 cash was collected. The project was completed in 2026 after additional costs of $3,950,000 were incurred. The company’s fiscal year-end is December 31. This project does not qualify for revenue recognition over time.
3. Prepare a partial
Trending nowThis is a popular solution!
Step by stepSolved in 3 steps with 4 images
- In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: 2024 $1,400,000 2025 2026 $3,150,000 $2,695,000 Cost incurred during the year Estimated costs to complete as of year-end 5,600,000 2,450,000 0 Billings during the year 1,000,000 3,550,000 5,450,000 Cash collections during the year 800,000 2,600,000 6,600,000 Assume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time. Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.arrow_forwardIn 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 3,344,000 $ 3,960,000 $ 1,645,600 Estimated costs to complete as of year-end 5,456,000 1,496,000 0 Billings during the year 2,800,000 4,504,000 2,696,000 Cash collections during the year 2,600,000 4,400,000 3,000,000 Assume that Westgate Construction’s contract with Santa Clara County does not qualify for revenue recognition over time.Required:1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred).2-b. In the journal below, complete the necessary journal entries…arrow_forwardOn February 1, 2023, Sandhill Contractors agreed to construct a building at a contract price of $3,460,000. The total estimated construction costs would be $1,890,000 and the project would be finished in 2025. Information relating to the costs and billings for this contract is as follows: Total costs incurred to date Estimated costs to complete Customer billings to date Collections to date 2023 Gross profit/ (loss) 689,850 1,200,150 1,100,000 1,000,000 2023 2024 573050 $1,162,000 $ 2,365,000 913,000 1,890,000 1,750,000 2025 Calculate the gross profit / (loss) that should be recognized for 2023, 2024, and 2025 using the percentage completion method. (Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45). Round percentage complete to 1 decimal place, e.g. 15.2% and final answers to O decimal places, e.g. 5,125.) 2024 -0- 3,460,000 2,950,000 -107450 $ LA 2025 40450arrow_forward
- Sagararrow_forwardSheridan Construction Company has entered into a contract beginning January 1, 2025, to build a parking complex. It has been estimated that the complex will cost $596,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $902,000. The following data pertain to the construction period. Costs to date Estimated costs to complete Progress billings to date Cash collected to date (a) $256,280 339,720 270,000 Gross profit recognized in 2025 Gross profit recognized in 2026 2025 Sok and Media 240,000 Gross profit recognized in 2027 $ GA $ LA 2026 Using the percentage-of-completion method, compute the estimated gross profit that would be recognized during each year of the construction period. (If answer is 0, please enter O. Do not leave any fields blank.) 5 $429,120 166,880 555,000 505,000 2027 $606,000 902,000 902.000arrow_forwardsarrow_forward
- In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $2,581,000 $2,347,000 $3,049,200 Estimated costs to complete as of year-end 6,319,000 2,772,000 0 Billings during the year 2,090,000 2,838,000 5,072,000 Cash collections during the year 1,845,000 2,900,000 5,255,000 Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the…arrow_forwardIn 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: 2026 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2024 $ 2,624,000 5,576,000 2,200,000 2025 $ 3,690,000 1,886,000 4,114,000 $ 2,074,600 3,686,000 2,000,000 3,800,000 4,200,000 Assume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time. Cost incurred during the year Estimated costs to complete as of year-end 2024 $ 2,420,000 5,620,000 2025 2026 $ 3,810,000 3,120,000 $ 3,220,000 в 5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs incurred and costs to complete Information. 2024 2025 2026 Cost incurred during the year Estimated costs to complete as of…arrow_forwardIn 2021, Montana Corp. entered into a contract to begin work on a two-year project. Montana recognizes revenue over time according to percentage of completion for this contract, and provides the following information (dollars in millions): Accounts receivable, 12/31/2021 (from construction progress billings) $37.5 $140 Actual construction costs incurred in 2021 Cash collected on project during 2021 $105 Construction in progress, 12/31/2021 $210 Estimated percentage of completion during 2021 Selected Amounts O $70,000,000 What is the amount of gross profit on the project recognized by Montana during 2021? O $60,000,000 $35,000,000 O $105,000,000 50 %arrow_forward
- In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: 2024 2025 2026 Cost incurred during the year $ 2,523,000 $ 3,177,000 $ 1,980,000 Estimated costs to complete as of year-end 6,177,000 1,800,000 0 Billings during the year 2,070,000 3,630,000 4,300,000 Cash collections during the year 1,835,000 3,400,000 4,765,000 Westgate recognizes revenue over time according to percentage of completion. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. Note: Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.arrow_forwardIn 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $ 10,000,000. The road was completed in 2026. Information related to the contract is as follows: 2024 2025 2026 Cost incurred during the year $ 2,184,000 $3,510,000 $2,316, 600 Estimated costs to complete as of year-end 5,616,000 2,106, 000 0 Billings during the year 1,800,000 3,894,000 4,306, 000 Cash collections during the year 1,600,000 3,400,000 5,000,000 Assume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time. Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. 2-a. In the journal below, complete the necessary journal entries for the year 2024 (credit" Cash, Materials, etc." for construction costs incurred). 2-b. In the journal below, complete the necessary journal entries for the year 2025 (credit "Cash, Materials, etc." for construction costs…arrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education