ntenance costs for the past 6 months. July August September October November December Units Produced 18,00
Q: The controller of Wildhorse Industries has collected the following monthly expense data for use in…
A: High low method is used as an attempt to segregate the variable and fixed costs using a limited set…
Q: Ravena Company manufactures office furniture. During the most productive month of the year, 3,500…
A: There are two type of costs that are being incurred in business. These are fixed costs and variable…
Q: Company X is attempting to develop the cost function for repair costs. The following past data are…
A:
Q: Miss River Railroad decided to use the high-low method and operating data from the past six months…
A: High low method: Variable cost per unit = (Highest activity cost - Lowest activity cost) / (Highest…
Q: Pharoah Corp. has collected the following data concerning its maintenance costs for the past 6…
A: Highest activity = 48,200 units Lowest activity = 21,700 units
Q: The following are the Maintenance Costs incurred in a Machine Shop for six months with corresponding…
A: A high low method is used to separate the mixed cost into fixed cost and variable cost. In this…
Q: DoKnow Co. like to estimate the variable and fixed cost components of its maintenance cost and has…
A: “Since you have posted a question with multiple sub-parts, we will solve first three sub-parts for…
Q: bellfont company produces door stoppers. august production costs are below. door stoppers produced…
A: Calculate the bellfonts production cost per door stoppers in September: Step 1: Calculate total…
Q: Full Throttle Delivery Co provided the following information for costs of its delivery fleet. Month…
A: "Since you have posted a question with multiple sub parts, we will solve first three sub parts for…
Q: The controller of Norton Industries has collected the following monthly expense data for use in…
A: High low method: Variable cost per hour= (Highest activity cost - Lowest activity cost) / (Highest…
Q: ZS Co. has so far charged actual factory overhead to production. The system has not been proved…
A: Overhead costs refer to the costs which occur in operating activity in a business. It also termed as…
Q: Edina Co. manufactures a product that requires 3.5 machine hours per unit. The variable and fixed…
A: What are the standard variable and fixed overhead rates:::: Total.machine hours is::144000 units*3.5…
Q: The following Information is avallable for a company's maintenance cost over the last seven months.…
A: A high-low method is used to separate the mixed cost into fixed cost and variable cost. In this…
Q: Miss River Railroad decided to use the high-low method and operating data from the past six months…
A: working notes: Highest activity cost = $1,143,500 Lowest activity cost = $783,900 Highest…
Q: The controller of Norton Industries has collected the following monthly expense data for use in…
A: Compute the variable costs per machine hour using high low method:
Q: The following data relate to the Lisle Company for May and August of the current year: May 25,000…
A: Variable cost per unit = ($1,247,000 - $1,175,000) / (29,000 - 25,000) = $18 Fixed cost =…
Q: Given the following cost and activity observations for Smithson Company's utilities, use the…
A: Formula to calculate fixed cost under high-low method High cost - Low cost / High hours - Low hours
Q: Boston Railroad decided to use the high-low method and operating data from the past six months to…
A: Variable cost is the cost that changes with the change in the output. Whereas, fixed cost is the…
Q: The management of Casablanca Manufacturing Corporation believes that machine- hours is an…
A:
Q: Door Stoppers produced 70,000 Direct material (variable)…
A: given that, Bellfont Company produced 70000 units in the august month. In September, Bell font…
Q: Bellfort Co. produces door stoppers. August production costs are below. Door stoppers produced =…
A: Given the following information: Door stoppers produced = 71,000 Direct material (variable) =…
Q: Boston Railroad decided to use the high-low method and operating data from the past six months to…
A: Variable Cost as per high-low method = (Cost at highest level of activity - Cost at lowest level of…
Q: Boston Railroad decided to use the high-low method and operating data from the past six months to…
A: A high low method is used to separate the mixed cost into fixed cost and variable cost. In this…
Q: 139) At an activity level of 8,400 units in a month, Braughton Corporation's total variable…
A: Variable cost per unit = Total variable cost / Total units = $697284/8400 = $83.01 per unit
Q: At an activity level of 8,300 machine-hours in a month, B Company's total variable maintenance cost…
A: Formula: Variable maintenance cost per hour = Total Variable maintenance cost / Total activity level…
Q: Given the following cost and activity observations for Smithson Company’s utilities, use the…
A:
Q: The controller of Hall Industries has collected the following monthly expense data for use in…
A: A variable cost is a business expense that varies with how much a company produces or sells.…
Q: The manager of Trusty Car Inspection reviewed the monthly operating costs for the past year. The…
A: Cost accounting is useful since it can show where a company spends money, how much it generates, and…
Q: screen shot of full question attached
A: An activity variance is a variance between the flexible budget numbers and planning budget numbers A…
Q: Hapza cleaning services has opening hours that fluctuate from month to month. The electricity costs…
A: A high low method of cost estimation is used to calculate the variable cost and fixed cost of the…
Q: Miss River Railroad decided to use the high-low method and operating data from the past six months…
A: Fixed Costs: These are the costs that remain constant in total dollar amount irrespective to the…
Q: The following information is available for a company's maintenance cost over the last seven months.…
A: Lets understand the basics. In high low method, fixed cost and variable cost gets separated from…
Q: The following information is available for a company’s maintenance cost over the last seven months.…
A: A high low method is used to separate the mixed cost into fixed cost and variable cost. In this…
Q: Calculating and Using a Single Charging Rate The expected costs for the Maintenance Department of…
A: Traditional costing system: It is a method of allocation of overhead to the products. Under this…
Q: Voltar has collected the following data for recent months Month Miles Driven Total Cost March 41,000…
A: According to the above data The Highest Activity Cost occurs in the month of April i.e. 44234 and…
Q: Al-Firdaus Co. had the following information during 2019: Total Paint Costs R.O. 27,000 Month…
A: High- Low mentod is a way to separate out fixed cost and variable cost. In this method we select…
Q: The following information is available for a company’s maintenance cost over the last seven months.…
A:
Q: Gribble Company’s high and low level of activity last year was 60,000 units of product produced in…
A: Variable cost changes with the change in the level of activity. So if 60,000 units were produced in…
Q: Donner Company would like to estimate the variable and fixed components of its maintenance costs and…
A: Variable expenses are those expenses that change with the change in quantity. Direct materials,…
Q: At high level of activity in November, 8000 machine hours were run and power cost were $18,00. In…
A: High-Low Method: The high-low method is that method by which the variable component and the fixed…
Q: Boston Railroad decided to use the high-low method and operating data from the past six months to…
A: The high low method is used to separate the fixed cost and variable cost from the mixed cost of the…
Q: Blanco, Inc. provides computer processing services and relevant data set up by the firm's management…
A: In accounting standard cost is based on a prior estimation for a pre-decided level of production…
Q: A transit company has the maintenance costs and kilometers driven data for its fleet of buses over a…
A:
Q: Jake’s Roof Repair has provided the following data concerning its costs:Fixed Cost Cost perper Month…
A: Variance: Variance refers to the different level in the actual cost incurred and standard cost. The…
Q: Calculating and Using a Single Charging Rate The expected costs for the Maintenance Department of…
A: 1.Single charging rate = Total variable and fixed cost/Total maintenance hours
Q: The following is the details of the cost at 70% capacity of Aaron company. It is expected that the…
A: A budget is an estimation that is prepared for a future time period so as to determine the estimated…
Q: Boston Railroad decided to use the high-low method and operating data from the past six months to…
A: High-Low Method is used to segregate the Fixed cost and Variable cost.
Markowis Corp. has collected the following data concerning its maintenance costs for the past 6 months.
July
August
September
October
November
December
Units Produced
18,000 32,000 36,000 22,000 40,000 38,000
Total Cost
$36,000 48,000 55,000 38,000 74,500 62,000
Compute the variable- and fixed-cost elements using the high-low method.
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 1 images
- The following computer printout was generated, using regression, for use in estimating maintenance costs. Intercept 8300 X Variable 1 37 Multiple R 0.9500 R Square 0.9025 Activity variable machine hours An estimate of maintenance costs at an activity level of 100 machine hours would be:Healthfirst (HF) Ltd has recently started to produce a face shield and product's standard cost data are as follows: Cost per unit Direct materials Perspex (0.5 meters @ $15 per meter) $ 7.50 Direct materials Hardened Plastic (0.25 meters at $20.00 per meter) 5.00 Direct manufacturing labour (0.5 hr @ $30.00 per hr) Manufacturing overhead Total Cost 15.00 Required Should HF accept the offer. Show all computations. 30.00 $57.50 Additional information 45% of the Manufacturing overhead changes with the number of units produced. Additionally, if production of face shields is discontinued, 20% of the remaining fixed cost will be avoided. The budgeted production used to compute overheads is 10,000 units per quarter. HF has been approached by another company who is willing to supply the face shields at $50. Per unit. The space used to manufacture face shields can be used to Generate $ 120,000 in contribution margin per quarter.Determine fixed and variable costs using the high-low method and prepare graph. E2.26 (LO 3) The controller of Furgee Industries has collected the following monthly expense data for use in analyzing the cost behaviour of maintenance costs. Total Maintenance Costs Total Machine Hours Month January February March April May June $2,500 3,000 3,600 4,500 3,200 4,900 300 350 500 690 400 700 Instructions a. Determine the fixed and variable cost components using the high-low method. b. Prepare a graph showing the behaviour of maintenance costs, and identify the fixed and variable cost components. Use 100-hour increments and $1,000 cost increments.
- Connell Co. collects the following data concerning a mixed cost, using miles as the activity level. Miles Driven Total Cost January 10,000 $17,000 February 8,000 $13,500 March 9,000 $14,400 April 7,000 $12,500 Instructions: Compute the variable and fixed cost elements using the high-low method.Write a linear cost function equation for each of the following conditions. Use y for estimated costsand X for activity of the cost driver. Machine operating costs include $1,000 of maintenance per month, and $15.00 of coolant usagecosts for each day the machinery is in operation.Silven Company has identified the following overhead activities, costs, and activity drivers for the coming year: Silven produces two models of cell phones with the following expected activity demands: 1. Determine the total overhead assigned to each product using the four activity drivers. 2. Determine the total overhead assigned to each model using the two most expensive activities. The costs of the two relatively inexpensive activities are allocated to the two expensive activities in proportion to their costs. 3. Using ABC as the benchmark, calculate the percentage error and comment on the accuracy of the reduced system. Explain why this approach may be desirable.
- Stahman, Inc., estimates its hidden external failure costs using the Taguchi loss function. Stahlman produces plastic sheets that vary in thickness and grade. For one of its large-volume products, it was determined that k = 30,000 and T = 0.28 inches in diameter. A sample of four units produced the following values: Required: 1. Calculate the average loss per unit. 2. Assuming that 100,000 units were produced, what is the total hidden cost? 3. Assume that the multiplier for Stahmans hidden external failure costs is six. What are the measured external costs? Explain the difference between measured costs and hidden costs.Benjamin Company accumulates the following data concerning a mixed cost, using miles as the activity level. Miles Driven Total Cost January 7,500 $20,000 February 8,200 $21,100 March 8,500 $22,000 April 8,300 $21,750 Compute the variable- and fixed-cost elements using the high-low method.Single line text.Sensor Systems manufactures an optical switch that it uses in its final product. The switch has the following manufacturing costs per unit: LOADING... (Click the icon to view the costs.) Direct materials $7.00 Direct labor 2.00 Variable overhead 8.00 Fixed overhead 6.50____________________________ Manufacturing product cost $23.50__________________________ _________________________________ LOADING... (Click the icon to view additional information.) Another company has offered to sell Sensor Systems the switch for $19.00 per unit. If Sensor Systems buys the switch from the outside supplier, the idle manufacturing facilities cannot be used for any other purpose, yet none of the fixed costs are avoidable. Prepare an outsourcing analysis to determine whether Sensor Systems should make or buy the switch. (For the Difference column, use a minus sign or parentheses only when the cost of outsourcing…
- Mozaic Inc. has decided to introduce a new product, which can be manufactured by either a computer-assisted manufacturing system (CAM) or a labor-intensive production system (LIP). The manufacturing method will not affect the quality of the product. The estimated manufacturing costs by the two methods are as follows: www CAM System LIP System Direct Material $5.00 $5.60 Direct Labor (DLH) 0.5 DLH x $12 $6.00 0.8 DLH x $9 $7.20 Variable Overhead 0.5 DLH x $6 $3.00 0.8 DLH x $6 $4.80 Fixed Overhead* $2,440,000 $1,320,000 * These costs are directly traceable to the new product line. They would not be incurred if the new product were not produced. The company's marketing research department has recommended an introductory unit sales price of $30. Selling expenses are estimated to be $500,000 annually plus $2 for each unit sold. (Ignore income taxes.) Required: 1. Describe the circumstances under which the firm should employ each of the two manufacturing methods. 2. Identify some business…Mozaic Inc. has decided to introduce a new product, which can be manufactured by either a computer-assisted manufacturing system (CAM) or a labor-intensive production system (LIP). The manufacturing method will not affect the quality of the product. The estimated manufacturing costs by the two methods are as follows: CAM System LIP System Direct Material $5.00 $5.60 Direct Labor (DLH) 0.5 DLH x $12 $6.00 0.8 DLH x $9 $7.20 Variable Overhead 0.5 DLH x $6 $3.00 0.8 DLH x $6 $4.80 Fixed Overhead* $2,440,000 $1,320,000 * These costs are directly traceable to the new product line. They would not be incurred if the new product were not produced. The company's marketing research department has recommended an introductory unit sales price of $30. Selling expenses are estimated to be $500,000 annually plus $2 for each unit sold. (Ignore income taxes.) Required: 1. Calculate the estimated break-even point in annual unit sales of the new product if the company uses the (a) computer-assisted…Joha, an accountant for Jones, Inc., has decided to estimate the fixed and variable components associated with the company's repair activity. The following data for the past few months has been collected: Repair Hours Total Repair Costs 20 $ 1,000 25 1,250 30 1,400 40 1,550 Required: Estimate the fixed and variable components for the repair costs using the high-low method. Using the cost formula, predict the total cost of repair if 10 hours are used.