KAYAK Corporation makes a kayak with the following standard costs per unit produced: Standard Quantity/Efficiency 3.5 lbs per unit produced Standard Price/Rate Direct Materials Direct Labor Mfg OH Actual Results: 1.25 hrs per unit produced 1.25 hrs per unit produced $3.50 per lb $20.00 per hr $3.10 per hr 12,250 units produced Direct material-Actually purchased and used 35,000 lbs for a total cost of $131,250. Direct Labor - Actually worked 14,000 hours at an average labor rate of $20.25/hr. Variable Overhead Cost - Actual variable overhead costs were $42,000 allocated on direct labor hours dele ksp Required: a. Compute total production costs, standard and actual, and calculate total production cost variance b. Compute the total materials cost variance and determine how much is driven by quantity variance and how much by price variance. d. Compute the total overhead cost variance and determine how much is driven by overhead efficiency variance and how much by rate variance c. Compute the total labor cost variance and determine how is driven by efficiency variance and how much by rate variance. KAYAK Corporation makes a kayak with the following standard costs per unit produced Standard Quantity/Efficiency 3.5 lbs per unit produced 1.25 hrs per unit produced 1.25 hrs per unit produced Direct Materials Direct Labor Mfg OH Actual Results: 12,250 units produced Direct material-Actually purchased and used 35,000 lbs for a total cost of $131,250. Direct Labor-Actually worked 14,000 hours at an average labor rate of $20.25/hr. Variable Overhead Cost-Actual variable overhead costs were $42,000 allocated on direct labor hours Show Transcribed Text Required: a. Compute total production costs, standard and actual, and calculate total production cost variance b. Compute the total materials cost variance and determine how much is driven by quantity variance and how much by price variance. c. Compute the total labor cost variance and determine how is driven by efficiency variance and how much by rate variance. d. Compute the total overhead cost variance and determine how much is driven by overhead efficiency variance and how much by rate variance Standard Price/Rate Direct Materials Direct Labor Mfg OH $3.50 per lb $20.00 per hr $3.10 per hr KAYAK Corporation makes a kayak with the following standard costs per unit produced: Standard Quantity/Efficiency 3.5 lbs per unit produced Standard Price/Rate Actual Results: 1.25 hrs per unit produced 1.25 hrs per unit produced $3.50 per lb $20.00 per hr $3.10 per hr 12,250 units produced Direct material - Actually purchased and used 35,000 lbs for a total cost of $131,250. Direct Labor-Actually worked 14,000 hours at an average labor rate of $20.25/hr. Variable Overhead Cost-Actual variable overhead costs were $42,000 allocated on direct labor hours Required: a. Compute total production costs, standard and actual, and calculate total production cost variance b. Compute the total materials cost variance and determine how much is driven by quantity variance and how much by price variance. c. Compute the total labor cost variance and determine how is driven by efficiency variance and how much by rate variance. d. Compute the total overhead cost variance and determine how much is driven by overhead efficiency variance and how much by rate variance

Principles of Accounting Volume 2
19th Edition
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax
Chapter5: Process Costing
Section: Chapter Questions
Problem 2PB: The following product costs are available for Kellee Company on the production of eyeglass frames:...
icon
Related questions
icon
Concept explainers
Topic Video
Question
KAYAK Corporation makes a kayak with the following standard costs per unit produced: Standard Quantity/Efficiency 3.5 lbs per unit
produced Standard Price/Rate Direct Materials Direct Labor Mfg OH Actual Results: 1.25 hrs per unit produced 1.25 hrs per unit produced
$3.50 per lb $20.00 per hr $3.10 per hr 12,250 units produced Direct material - Actually purchased and used 35,000 lbs for a total cost of
$131,250. Direct Labor - Actually worked 14,000 hours at an average labor rate of $20.25/hr. Variable Overhead Cost - Actual variable
overhead costs were $42,000 allocated on direct labor hours dele ksp Required: a. Compute total production costs, standard and actual,
and calculate total production cost variance b. Compute the total materials cost variance and determine how much is driven by quantity
variance and how much by price variance. d. Compute the total overhead cost variance and determine how much is driven by overhead.
efficiency variance and how much by rate variance c. Compute the total labor cost variance and determine how is driven by efficiency
variance and how much by rate variance.
KAYAK Corporation makes a kayak with the following standard costs per unit produced:
Standard
Quantity/Efficiency
3.5 lbs per unit produced
Standard
Price/Rate
1.25 hrs per unit produced
1.25 hrs per unit produced
Direct Materials
Direct Labor
Mfg OH
Actual Results:
12,250 units produced
Direct material - Actually purchased and used 35,000 lbs for a total cost of $131,250.
Direct Labor-Actually worked 14,000 hours at an average labor rate of $20.25/hr.
Variable Overhead Cost-Actual variable overhead costs were $42,000 allocated on direct labor
hours
Required:
a. Compute total production costs, standard and actual, and calculate total production cost variance
b. Compute the total materials cost variance and determine how much is driven by quantity variance
and how much by price variance.
c. Compute the total labor cost variance and determine how is driven by efficiency variance and how
much by rate variance.
d. Compute the total overhead cost variance and determine how much is driven by overhead
efficiency variance and how much by rate variance
Show Transcribed Text
$3.50 per lb
$20.00 per hr.
$3.10 per hr
KAYAK Corporation makes a kayak with the following standard costs per unit produced:
Standard
Standard
Quantity/Efficiency
3.5 lbs per unit produced
Price/Rate
Direct Materials
Direct Labor
Mfg OH
Actual Results:
1.25 hrs per unit produced
1.25 hrs per unit produced
$3.50 per lb
$20.00 per hr
$3.10 per hr
12,250 units produced
Direct material - Actually purchased and used 35,000 lbs for a total cost of $131,250.
Direct Labor-Actually worked 14,000 hours at an average labor rate of $20.25/hr.
Variable Overhead Cost-Actual variable overhead costs were $42,000 allocated on direct labor
hours
Required:
a. Compute total production costs, standard and actual, and calculate total production cost variance
b. Compute the total materials cost variance and determine how much is driven by quantity variance
and how much by price variance.
c. Compute the total labor cost variance and determine how is driven by efficiency variance and how
much by rate variance.
d. Compute the total overhead cost variance and determine how much is driven by overhead
efficiency variance and how much by rate variance
Transcribed Image Text:KAYAK Corporation makes a kayak with the following standard costs per unit produced: Standard Quantity/Efficiency 3.5 lbs per unit produced Standard Price/Rate Direct Materials Direct Labor Mfg OH Actual Results: 1.25 hrs per unit produced 1.25 hrs per unit produced $3.50 per lb $20.00 per hr $3.10 per hr 12,250 units produced Direct material - Actually purchased and used 35,000 lbs for a total cost of $131,250. Direct Labor - Actually worked 14,000 hours at an average labor rate of $20.25/hr. Variable Overhead Cost - Actual variable overhead costs were $42,000 allocated on direct labor hours dele ksp Required: a. Compute total production costs, standard and actual, and calculate total production cost variance b. Compute the total materials cost variance and determine how much is driven by quantity variance and how much by price variance. d. Compute the total overhead cost variance and determine how much is driven by overhead. efficiency variance and how much by rate variance c. Compute the total labor cost variance and determine how is driven by efficiency variance and how much by rate variance. KAYAK Corporation makes a kayak with the following standard costs per unit produced: Standard Quantity/Efficiency 3.5 lbs per unit produced Standard Price/Rate 1.25 hrs per unit produced 1.25 hrs per unit produced Direct Materials Direct Labor Mfg OH Actual Results: 12,250 units produced Direct material - Actually purchased and used 35,000 lbs for a total cost of $131,250. Direct Labor-Actually worked 14,000 hours at an average labor rate of $20.25/hr. Variable Overhead Cost-Actual variable overhead costs were $42,000 allocated on direct labor hours Required: a. Compute total production costs, standard and actual, and calculate total production cost variance b. Compute the total materials cost variance and determine how much is driven by quantity variance and how much by price variance. c. Compute the total labor cost variance and determine how is driven by efficiency variance and how much by rate variance. d. Compute the total overhead cost variance and determine how much is driven by overhead efficiency variance and how much by rate variance Show Transcribed Text $3.50 per lb $20.00 per hr. $3.10 per hr KAYAK Corporation makes a kayak with the following standard costs per unit produced: Standard Standard Quantity/Efficiency 3.5 lbs per unit produced Price/Rate Direct Materials Direct Labor Mfg OH Actual Results: 1.25 hrs per unit produced 1.25 hrs per unit produced $3.50 per lb $20.00 per hr $3.10 per hr 12,250 units produced Direct material - Actually purchased and used 35,000 lbs for a total cost of $131,250. Direct Labor-Actually worked 14,000 hours at an average labor rate of $20.25/hr. Variable Overhead Cost-Actual variable overhead costs were $42,000 allocated on direct labor hours Required: a. Compute total production costs, standard and actual, and calculate total production cost variance b. Compute the total materials cost variance and determine how much is driven by quantity variance and how much by price variance. c. Compute the total labor cost variance and determine how is driven by efficiency variance and how much by rate variance. d. Compute the total overhead cost variance and determine how much is driven by overhead efficiency variance and how much by rate variance
Expert Solution
steps

Step by step

Solved in 5 steps

Blurred answer
Knowledge Booster
Costing Systems
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
Managerial Accounting
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub
Financial And Managerial Accounting
Financial And Managerial Accounting
Accounting
ISBN:
9781337902663
Author:
WARREN, Carl S.
Publisher:
Cengage Learning,