I. Gannt Chart. For the precedence relationships of the activities, assume the following: Contractors for a building restoration project will have to do the following: 1. Wall/Ceiling Activities The wall/ceiling activities, the flooring activities, and the exterior activities are listed in the order in which they are to be performed. A Strip the existing wall paper B Clean and repair the walls/ceilings C Paint the walls/ceilings 2. Cleaning and repairing the walls/ceilings, removing the old carpeting, and sanding and repairing the exterior must precede any painting activity (interior and exterior). Flooring Activities D Remove old carpeting E Lay a floor foundation 3. The walls/ceilings must be painted before the hardwood flooring is installed, stained, and sealed. F Install, stain, and seal hardwood flooring G Install rugs and carpet runners 4. All painting (interior and exterior) must be completed before new rugs and carpet runners are installed. Exterior Activities H Sand and repair outside wood surfaces I Paint the exterior 5. Stripping the wallpaper, removing the old carpeting, and sanding and repairing the exterior may all start at the same time. a. If the estimated time of each wall/ceiling activity is two weeks, the estimated time of each flooring activity is one week, and the estimated time of each exterior activity is three weeks, fill out the Immediate Predecessor/s column in the table below and draw the Gannt Chart corresponding to this project Weeks after start Immediate Predecessor/s 0 Activity 1 2 3 4 5 6 7 8 9 10 A B с D E F G H I b. What is the expected project completion time? c. Which are the critical activities?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
100%
Please answer the chart only. Help me pass my subject. Thank youuu!! :))
I. Gannt Chart.
For the precedence relationships of the activities,
assume the following:
Contractors for a building restoration project
will have to do the following:
Wall/Ceiling Activities
1. The wall/ceiling activities, the flooring activities,
and the exterior activities are listed in the order in
which they are to be performed.
A Strip the existing wall paper
B Clean and repair the walls/ceilings
C Paint the walls/ceilings
2. Cleaning and repairing the walls/ceilings,
removing the old carpeting, and sanding and
repairing the exterior must precede any painting
activity (interior and exterior).
Flooring Activities
D Remove old carpeting
E Lay a floor foundation
3. The walls/ceilings must be painted before the
hardwood flooring is installed, stained, and
sealed.
F Install, stain, and seal hardwood flooring
G Install rugs and carpet runners
4. All painting (interior and exterior) must be
completed before new rugs and carpet runners are
installed.
Exterior Activities
H Sand and repair outside wood surfaces
I Paint the exterior
5. Stripping the wallpaper, removing the old
carpeting, and sanding and repairing the exterior
may all start at the same time.
a. If the estimated time of each wall/ceiling activity is two weeks, the estimated time of each flooring activity is
one week, and the estimated time of each exterior activity is three weeks, fill out the Immediate
Predecessor/s column in the table below and draw the Gannt Chart corresponding to this project
Weeks after start
Immediate
Activity
Predecessor/s 0 1 2 3 4 5 6 7 8 9 10
A
B
C
D
E
F
G
H
I
b. What is the expected project completion time?
c. Which are the critical activities?
Transcribed Image Text:I. Gannt Chart. For the precedence relationships of the activities, assume the following: Contractors for a building restoration project will have to do the following: Wall/Ceiling Activities 1. The wall/ceiling activities, the flooring activities, and the exterior activities are listed in the order in which they are to be performed. A Strip the existing wall paper B Clean and repair the walls/ceilings C Paint the walls/ceilings 2. Cleaning and repairing the walls/ceilings, removing the old carpeting, and sanding and repairing the exterior must precede any painting activity (interior and exterior). Flooring Activities D Remove old carpeting E Lay a floor foundation 3. The walls/ceilings must be painted before the hardwood flooring is installed, stained, and sealed. F Install, stain, and seal hardwood flooring G Install rugs and carpet runners 4. All painting (interior and exterior) must be completed before new rugs and carpet runners are installed. Exterior Activities H Sand and repair outside wood surfaces I Paint the exterior 5. Stripping the wallpaper, removing the old carpeting, and sanding and repairing the exterior may all start at the same time. a. If the estimated time of each wall/ceiling activity is two weeks, the estimated time of each flooring activity is one week, and the estimated time of each exterior activity is three weeks, fill out the Immediate Predecessor/s column in the table below and draw the Gannt Chart corresponding to this project Weeks after start Immediate Activity Predecessor/s 0 1 2 3 4 5 6 7 8 9 10 A B C D E F G H I b. What is the expected project completion time? c. Which are the critical activities?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.