Given the table below, calculate the total cost for all the items needed. What would be the total estimate with a 15 percent contingency? If a 10 percent reserve is added, what would be the total estimate?
Given the table below, calculate the total cost for all the items needed. What would be the total estimate with a 15 percent contingency? If a 10 percent reserve is added, what would be the total estimate?
Engineering Fundamentals: An Introduction to Engineering (MindTap Course List)
5th Edition
ISBN:9781305084766
Author:Saeed Moaveni
Publisher:Saeed Moaveni
Chapter20: Engineering Economics
Section: Chapter Questions
Problem 19P
Related questions
Question
- Given the table below, calculate the total cost for all the items needed. What would be the total estimate with a 15 percent contingency? If a 10 percent reserve is added, what would be the total estimate?
Items |
Cost/Unit |
Quantity |
Wheel |
$500 |
12 |
Bearing |
$25 |
400 |
Clamp |
$5 |
40 |
Nozzle |
$7 |
30 |
Nut |
$2 |
40 |
Caster |
$55 |
120 |
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
Engineering Fundamentals: An Introduction to Engi…
Civil Engineering
ISBN:
9781305084766
Author:
Saeed Moaveni
Publisher:
Cengage Learning
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,
Engineering Fundamentals: An Introduction to Engi…
Civil Engineering
ISBN:
9781305084766
Author:
Saeed Moaveni
Publisher:
Cengage Learning
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,