Question 50 At 7.7%, a bridge cost P 210M with a life of 21 years. The bridge must be partially rebuilt at a cost of P 100 M at the end of each 21 years, Calculate the capitalized dost if an annual maintenance of P 510,000 is required. Express your answer in whole number. Question 50 of 50
Question 50 At 7.7%, a bridge cost P 210M with a life of 21 years. The bridge must be partially rebuilt at a cost of P 100 M at the end of each 21 years, Calculate the capitalized dost if an annual maintenance of P 510,000 is required. Express your answer in whole number. Question 50 of 50
Traffic and Highway Engineering
5th Edition
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Garber, Nicholas J.
Chapter13: Evaluating Transportation Alternatives
Section: Chapter Questions
Problem 10P
Related questions
Question
100%
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 1 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning