Question
Question 3
Given the information of a project information is given in Table 2 and the project diagram showing precedence relationships of the activities.
Table 2
Activity |
Dependency |
Time (weeks) |
A |
- |
3 |
B |
- |
3 |
C |
A |
2 |
D |
A |
8 |
E |
C,B |
5 |
F |
C,B |
5 |
G |
D,E |
7 |
1. Find the activity
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 2 steps with 3 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A project has activities, durations, costs, and precedence relationships as shown in the following table. Accelerated Duration (Weeks) Immediate Predecessor Path A-C-E A-D-H-I B-F-H-I Activity B-G-I A B с D E F GJ H I Present Duration (Weeks) Project is reduced from Activity Crashed (1 week) Additional Cost for Crashing 8 13 8 18 13 15 10 7 5 $ to B B 7 I 11 4 16 8 13 8 6 4 $14,000 Develop a time-cost trade-off analysis. Detail the steps that you would use to accelerate or crash the project to its minimum duration at the lowest cost. Determine each step's cost and the duration of the project. Length of Path (weeks) H D, F A weeks at an additional cost (in $) of $ A U B B D, F G, H Present Cost D, F $11,000 $20,000 $9,000 $25,000 $20,000 $20,000 $15,000 $12,000 $10,000 Accelerated Cost $16,000 $26,000 $21,000 $29,000 $34,000 $31,000 $24,000 $17,000arrow_forwardQ1. Table 1 shows the activities involving a grant related project at national level that recommended for second year students of the Faculty of Defense Engineering, Universiti Pertahanan Malaysia. (a) Construct a project network diagram for Table 1 using the Arrow-On-Nodes (AON) method with all related calculations on the activities of Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF), and Slack (SL). (b) Determine the total completion time and the critical path of the project network diagram. (c) Discuss the impacts on the project completion, if the activity E is delayed. Table 1: Activity Time Estimates and Dependencies Immediate ID Activity Description Time (days) Predecessor(s) A Planning Determine the theme, select supervisor, select team Designing the product 75 None В Design 150 Planning Simulation and product analysis Procurement Purchasing raw materials and standard components Cutting, welding and manufacturing Fitting and components assembly Product…arrow_forwardUsing Microsoft Excel TM prepare a Gantt Chart for the following project. Activity Predecessor(s) Duration (Months) 1. Proposal 2. Client meeting 3. Develop airframe spec. 4. Develop engine spec. 5. Client meeting 6. Design fuselage 7. Design wings 8. Design engine 9. Client meeting 10. Build fuselage 11. Build wings 12. Build engines 13. Integrate airframe 14. Client meeting 15. Test engines 16. Integrate engines 17. Test flight 18. Client meeting 4 1 1 2 3 2 2 3,4 1 5 8 13 6,7.8 1 16 10 12 10,11,12 5 13 1 12 8 4 16 10 17 1 N567 2.arrow_forward
- Consider the project information in the table below: Immediate Activities Duration (days) Predecessors 8. 6. C 8. 11 A 6. A F 6. H. 4 F, G, H D, E, I Draw and analyze a project network diagram to answer the following questions: What is the most that Activity E can be delayed in starting, without delaying the project? OA. 22 В. 21 OC. 19 O D. 20 O E. 18 5. A Barrow_forwardActivities, preceding activities, normal and crashed completion times of each of the activities and crashed costs of activities per week of a project are given in the following table. Activity Preceding Activity Crashed Completion time (week) Normal Crashed Cost Completion Time (week) 7 per week A 7 6. 5 $500 $700 $600 $800 $400 C A 4 3 A, C В, D D, E D 9 E 10 9. F 9 II. Find the slack time of each of the activities and the critical activities. Find the minimum possible completion time of the project by considering the crashed completion times and the minimal total cost of crashing the project. iv.arrow_forwardBM HL Assignment 1- Due Date 24 March 2022 5. Construct an activity-on-arrow precedence diagram for each of the following cases. Note that each case requires the use of a dummy activity. ja) Draw AON diagram of the activity above! b) Determine the critical path! Activity Precedes Activity Duration (weeks) A В 3 C 4 D A E А, В F C 7 G D,E 4 H F,G 5 65Narrow_forward
- 4 01:34:47 The network diagram and task times for a project are shown below. A₁ A2 Late start time A3 Task A₁ A₂ A3 A₁ A5 What is the late start time for activity A3 ? Duration (days) 7 6644 A4 days A5arrow_forward1. Activity Activity Activity Slack Predecessor Duration (In weeks) a 3 b a d b,c 1 e 3 d,e g d, f 4 h G 1 a) Draw an Activity on Node Diagram. Compute the early and Latest starting and finish time. Compute slack times. b) Find out the possible paths and the critical path. What are the critical activities? c) If we delay activity 'd' and 'e' by 3 days, how would it impact the project completion time? 2. 2. 2.arrow_forwardplease only anwer the C partarrow_forward
- *(b.) (in Microsoft Project) create the network diagram and task schedule table and then provide (in Microsoft Word) the critical path for the project and give in a table the ES, EF, LS, and LF, free float and total slack for each activity (taking information from Microsoft Project).arrow_forwardTextbook PB Question 1A/BD: a) Draw a project network from the table above b) What activity(s) is a burst activity? What activity(s) is a merge activity? 3. What is the length of the project? 4. What is the critical path? c) Make the Gantt chart d) Build the project network using expected activity times based on the new table below e) What would be the expected length of the project? f) What would be the project standard deviation? g) Using a z-table (one can be found here: https://statisticsbyjim.com/hypothesis-testing/z-table/ ), what is the probability that the project can be completed in 28 weeks?arrow_forwardActivity Predecessor Duration A - 6 B A 8 C A 6 D C 4 E B 6 F b.d 7 G C 5 H F,G 6 I E, H 4 Construct the network diagram Find each activity’s ES, EF, LS and LF. Calculate the slack for each activity. How long will it take to complete the projectarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.