Fast Burger Inc. is building a new restaurant near a college football stadium. The restaurant will be open 16 hours per day, 360 days per year. Managers have concluded that the restaurant should have the capacity to handle a peak hour demand of 120 customers. Assume front-counter service personnel can take and assemble orders at the service rate of 14 customers per hour and the target labor utilization rate for this job is 70 percent. According to the information, determine the the number of front-service counter people that should be assigned to this peak demand period. Only for non-integer results, round your answer UP to the nearest integer. For example, if your answer is 5.05, type 6; if your answer is 5, type 5.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter12: Queueing Models
Section: Chapter Questions
Problem 59P
icon
Related questions
Question
100%
Fast Burger Inc. is building a new restaurant near a college football stadium. The
restaurant will be open 16 hours per day, 360 days per year. Managers have
concluded that the restaurant should have the capacity to handle a peak hour
demand of 120 customers. Assume front-counter service personnel can take and
assemble orders at the service rate of 14 customers per hour and the target labor
utilization rate for this job is 70 percent. According to the information, determine
the the number of front-service counter people that should be assigned to this peak
demand period. Only for non-integer results, round your answer UP to the nearest
integer. For example, if your answer is 5.05, type 6; if your answer is 5, type 5.
Your Answer:
Answer
Transcribed Image Text:Fast Burger Inc. is building a new restaurant near a college football stadium. The restaurant will be open 16 hours per day, 360 days per year. Managers have concluded that the restaurant should have the capacity to handle a peak hour demand of 120 customers. Assume front-counter service personnel can take and assemble orders at the service rate of 14 customers per hour and the target labor utilization rate for this job is 70 percent. According to the information, determine the the number of front-service counter people that should be assigned to this peak demand period. Only for non-integer results, round your answer UP to the nearest integer. For example, if your answer is 5.05, type 6; if your answer is 5, type 5. Your Answer: Answer
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Lean manufacturing
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,