EXAMPLE 2.6 Determination of Aggregate Requirement for a Roadway Aggregates from a gravel pit are required for constructing a road embankment. The porosity of the aggregates at the gravel pit is 60%. The desired porosity of the compacted aggregates in the embank- ment is 25%. For a section of the embankment 7.5m wide x 0.6m compacted thickness x 1 km long, (a) calculate the volume of aggregates required. (b) Just before the construction of the embank- ment, a re-check of the porosity of the aggregates at the gravel pit was conducted. The porosity was 65% rather than 60% (an error of +8.3%), what extra percentage of aggregates would be required to construct the embankment. Assume a swell factor of 1.

Fundamentals of Geotechnical Engineering (MindTap Course List)
5th Edition
ISBN:9781305635180
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Braja M. Das, Nagaratnam Sivakugan
Chapter3: Weight-volume Relationships And Plasticity
Section: Chapter Questions
Problem 3.1P
icon
Related questions
Question
EXAMPLE 2.6 Determination of Aggregate Requirement for a Roadway
Aggregates from a gravel pit are required for constructing a road embankment. The porosity of the
aggregates at the gravel pit is 60%. The desired porosity of the compacted aggregates in the embank-
ment is 25%. For a section of the embankment 7.5m wide x 0.6m compacted thickness x 1 km
long, (a) calculate the volume of aggregates required. (b) Just before the construction of the embank-
ment, a re-check of the porosity of the aggregates at the gravel pit was conducted. The porosity was
65% rather than 60% (an error of +8.3%), what extra percentage of aggregates would be required
to construct the embankment. Assume a swell factor of 1.
Transcribed Image Text:EXAMPLE 2.6 Determination of Aggregate Requirement for a Roadway Aggregates from a gravel pit are required for constructing a road embankment. The porosity of the aggregates at the gravel pit is 60%. The desired porosity of the compacted aggregates in the embank- ment is 25%. For a section of the embankment 7.5m wide x 0.6m compacted thickness x 1 km long, (a) calculate the volume of aggregates required. (b) Just before the construction of the embank- ment, a re-check of the porosity of the aggregates at the gravel pit was conducted. The porosity was 65% rather than 60% (an error of +8.3%), what extra percentage of aggregates would be required to construct the embankment. Assume a swell factor of 1.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Knowledge Booster
Calculation of settlement
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals of Geotechnical Engineering (MindTap…
Fundamentals of Geotechnical Engineering (MindTap…
Civil Engineering
ISBN:
9781305635180
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning