Alebwelelapo is planning a soccer tournament for the weekend of May 29–30. The club’s officers know that by April 30 they must send out acceptances to teams that have applied to enter, and by April 20 they must send out the tournament game
Activity |
Description |
Predecessor |
Duration (Days) |
A |
Send application forms |
– |
7 |
B |
Get volunteer workers |
– |
18 |
C |
Line up referees |
– |
10 |
D |
Reserve fields |
– |
21 |
E |
Receive and process forms |
A |
30 |
F |
Determine age divisions |
B, C, D, E |
9 |
G |
Assign fields to divisions |
F |
7 |
H |
Sell program ads |
B |
2 |
I |
Acquire donated items for team gift bags |
B |
20 |
J |
Schedule games |
G |
14 |
K |
Design ads |
H |
80 |
L |
Fill gift bags |
I |
12 |
M |
Process team t-shirt orders |
E |
10 |
N |
Send acceptance letters |
F |
7 |
O |
Design and print programs |
J, K, L, N |
18 |
P |
Put together registration boxes (programs, gifts, etc.) |
O |
7 |
Q |
Send out game schedules |
J, K, L, N |
8 |
R |
Assign referees to games |
J, K, L, N |
7 |
S |
Get trophies |
F |
8 |
T |
Silk-screen t-shirts |
M |
17 |
U |
Package team t-shirt orders |
T |
8 |
a) Develop a project network Activity-on-Arrow (AOA) for the club’s tournament preparation process and show all activity schedule and duration of the project [show clearly all dummy activities]
kindly help in drawing a clear network please.
Step by stepSolved in 2 steps with 1 images
- With refrences solve. For your final project, you are to present a Supply Chain Management plan for a new coffee manufacturing/supply/distribution company. The company will be a producer of high-end coffee, which is to be pre-packaged and sold to high-end retailers, and distributed for use in high-end coffee shops. For the purposes of this assignment, you are to assume that the company is new, and does not have a pre-established location. This company will not have it’s own retail presence. Based on your research, you will propose sites for physical facilities, transport routes, inventory strategies etc. In developing your proposed plan, the following elements are to be considered: 1. Economies of scale 2. Source and destination 3. Product value 4. Company growth (using examples from established companies) 5. Demand projections and forecasts (including assumptions on global buy-in and presence) 6. Production flexibility 7. Storage and transport issues 8. Inventory management 9.…arrow_forwardsniparrow_forwardEvent Design is critical to the organization of every successful event. What is event design? Identify and explain three types of event designs and discuss its relevance to the event planning process.arrow_forward
- The Student Affairs Department at UCC has developed a sequence of activities for the University’s Sports Day. The Director has published the activities as shown in the table. All students are expected to participate and all activities are expected to be completed. The activities and immediate predecessors appear in the following table. Develop a network for this problem. ACTIVITY IMMEDIATE PREDECESSOR A -- B -- C -- D B E A, D F C G E, F Copy the following table in your answer booklet. Determine the values for the gray spaces hence complete the copied table. Activity Completion Times Early Start Early Finish Late Start Late Finish Slack On Critical Path A 2 B 5 C 1 D 3 E 2 F 6 G 8 CRITICAL…arrow_forwardThe Virginia Department of Transportation is undertaking a construction project to widen a large section of interstate highway near Wahington, DC. The project includes the construction of a number of new bridges, interchanges and overpasses. The first step in the process is to appoint a project manager and develop a project team, whose members will be departmental employees and private consultants and operatives. The team for a project of this size also requires a large support staff with a variety of technical skills. Once the team is selected and the staff is in place, the next task is to select a primary contractor to manage and oversee the construction. The following activities are standard for the planning and scheduling of this process: Activity Activity description Time predecessor estimates (weeks) Activity a | b Select project management 2 2 a b Develop team recruitment process 3 a. Implement team recruitment process by 3. 6. Staff needs assessment 3 Staff recruitment…arrow_forwardAlebwelelapo is planning a soccer tournament for the weekend of May 29-30. The club's officers know that by April 30 they must send out acceptances to teams that have applied to enter, and by April 20 they must send out the tournament game schedule to teams that have been selected to play. Their tentative plan is to begin the initial activities for tournament preparation, including sending out the application forms to prospective teams, on January 20. Following is a list of tournament activities, their precedence relationships, and their duration in days. Activity Description A B с D E F G H | J K L M N O P Q R S T U Send application forms Get volunteer workers Line up referees Reserve fields Receive and process forms Determine age divisions Assign fields to divisions Sell program ads Acquire donated items for team gift bags Schedule games Design ads Fill gift bags Process team t-shirt orders Send acceptance letters Design and print programs Put together registration boxes (programs,…arrow_forward
- Quorex is evaluating two mutually exclusive projects. Project A has a net investment of $50,000 and net cash flows over a six-year period of $13,000 per year (NOTE: that project requires a reinvestment with the same cost and cash flow for another six years). Project B has a net investment of $48,500, but its net cash flows of $8,740 per year will occur over a 12-year period. If Quorex has a cost of capital of 14% for these projects, which project, if either, should be chosen, and what is its NPV?arrow_forwardRare Agri-Products Ltd. is considering a new project with a projected life of seven (7) years. The project falls under the government’s subsidy program for encouraging local agricultural products and is eligible for a one-time rebate of 25% on any initial equipment installed for the project. The initial equipment (IE) will cost $41,000,000. An additional equipment (AE) costing $3,500,000 will be needed at the end of year 3. At the end of seven (7) years, the original equipment, IE, will have no resale value but the supplementary equipment, AE, can be sold for $50,000. A working capital of $1,350,000 will be needed. The project is forecast to generate sales of agri-products over the seven years as follows: Year 1 70,000 units Year 2 100,000 units Years 3-5 250,000 units Years 6-7 325,000 units A sale price of $150 per unit for the first two years is expected and then decline to $90 per unit thereafter as the newness of the product loses some sheen. The variable expenses will amount to…arrow_forwardFowle Marketing Research has four project leaders available for the assignment of project leaders to clients that will minimize the total time to complete all projects. The estimated project completion times in days are as follows: PROJECT LEADER CLIENT 1 2 3 ADAM 10 15 9 BOB 9 18 5 CARL 6 14 3 DAN 8 16 6 Formulate the complete LP model.arrow_forward
- Text: We can develop the CSR activities for Nestle company of planting trees and cleaning the lakes. This can be done by partnering with NGOs who are already working in these areas. The company can target several trees to be planted, for example, 100,000 in a quarter and take care of them till growth. To clean the lake, it can take the help of the National scientist of environmental science and fund the project to clean some of the lakes with the target number of again 50. A long-term solution must be used by them in cleaning the lakes, like stopping the sewage inflow and creating a small recycling plant before throwing water into the water bodies. The government, municipality, NGO, and environmental scientists are the main stakeholders involved. Here, the competition must not be created, but collaboration was be done between the competitors to help the society. The competitors will be other brands like Unilever and P&G. Progress indicators can be used as the number of trees…arrow_forwardThe answer is not "0"arrow_forward1.What is the point at which an owner can begin to occupy a building or use it for its intended purpose? At the end of the warranty period After final completion When the payment bond is terminated After substantial completion 2.What is used to determine periodic payment amounts on unit price contracts? Submitted invoices, receipts, and timesheets plus the contractor's fee. A fixed, monthly installment negotiated at the start of the project. Schedule of Values and percentage completion on each pay item Unit prices originally bid and quantities measured.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.