De León Engineering designs and constructs air conditioning and heating systems for hospitals and clinics. Currently, the company's staff is overloaded with design work. There is a major design project due in 8 weeks. The penalty for completing the design late is $14,000 per week because any delay will cause the facility to open later than anticipated and cost the client significant revenue. If the company uses its inside engineers to complete the design, it will have to pay them overtime for all work. Owner Roberta De León has estimated that it will cost $12,000 per week (wages and overhead), including late weeks, to have company engineers complete the design. Roberta is also considering having an outside engineering

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

I need help solving this problem.

OPTION
3) Once a product is defined, what documents are used to assist production personnel in its
manufacture?
Internal
Engineers
External
Engineers
4) De León Engineering designs and constructs air conditioning and heating systems for
hospitals and clinics. Currently, the company's staff is overloaded with design work. There is
a major design project due in 8 weeks. The penalty for completing the design late is $14,000
per week because any delay will cause the facility to open later than anticipated and cost the
client significant revenue. If the company uses its inside engineers to complete the design, it
will have to pay them overtime for all work. Owner Roberta De León has estimated that it
will cost $12,000 per week (wages and overhead), including late weeks, to have company
engineers complete the design. Roberta is also considering having an outside engineering
firm do the design. A bid of $90,000 has been received for the completed design. Yet another
option for completing the design is to conduct a joint design by having a third engineering
company complete all electromechanical components of the design at a cost of $50,000. De
León Engineering would then complete the rest of the design and control systems at an
estimated cost of $30,000.
Joint Design
Roberta has estimated the following probabilities of completing the project within various
time frames when using each of the three options. Those estimates are shown in the
following table:
ON
TIME
2
CHINES
1 WEEK
LATE
5
PRE
CO
PROBABILITY OF COMPLETING THE DESIGN
A
3
de chant
t
DO
2 WEEKS
LATE
3
3 WEEKS
LATE
What is the best decision based on an expected monetary value (EMV) criterion? (Note: You
want the lowest EMV because we are dealing with costs in this problem.
A manufacturer of disk drives for notebook computers wants an MTBF of at least 50.000
Transcribed Image Text:OPTION 3) Once a product is defined, what documents are used to assist production personnel in its manufacture? Internal Engineers External Engineers 4) De León Engineering designs and constructs air conditioning and heating systems for hospitals and clinics. Currently, the company's staff is overloaded with design work. There is a major design project due in 8 weeks. The penalty for completing the design late is $14,000 per week because any delay will cause the facility to open later than anticipated and cost the client significant revenue. If the company uses its inside engineers to complete the design, it will have to pay them overtime for all work. Owner Roberta De León has estimated that it will cost $12,000 per week (wages and overhead), including late weeks, to have company engineers complete the design. Roberta is also considering having an outside engineering firm do the design. A bid of $90,000 has been received for the completed design. Yet another option for completing the design is to conduct a joint design by having a third engineering company complete all electromechanical components of the design at a cost of $50,000. De León Engineering would then complete the rest of the design and control systems at an estimated cost of $30,000. Joint Design Roberta has estimated the following probabilities of completing the project within various time frames when using each of the three options. Those estimates are shown in the following table: ON TIME 2 CHINES 1 WEEK LATE 5 PRE CO PROBABILITY OF COMPLETING THE DESIGN A 3 de chant t DO 2 WEEKS LATE 3 3 WEEKS LATE What is the best decision based on an expected monetary value (EMV) criterion? (Note: You want the lowest EMV because we are dealing with costs in this problem. A manufacturer of disk drives for notebook computers wants an MTBF of at least 50.000
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.