2. A small software development project at Krishna Dhir's firm has five major activities. The times (in days) are estimated and provided in the table below:
Activity
|
Immediate
Predecessor
|
a
|
m
|
b
|
A
|
−
|
2
|
5
|
8
|
B
|
−
|
3
|
6
|
9
|
C
|
A
|
4
|
7
|
10
|
D
|
B
|
2
|
5
|
14
|
E
|
C
|
3
|
3
|
3
|
Part 2
d) The probability that it will take more than 17 days to complete this projectbe is __ (keep two decimal places).
e) The due date that yields a 98% chance of completion is ____ days (keep two decimal places).
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 5 steps with 4 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The table below contains data for the installation of new equipment in a manufacturing process for a steel corporation. Your company is responsible for the installation project. Indirect costs are $6,000 per week, and a penalty cost of $10,000 per week will be incurred by your company for every week the project is delayed beyond week 15. Activity Immediate Predecessor(s) Normal Time (weeks) Crash Time (weeks) Normal Cost ($) Crash Cost ($) A None 2 1 7,000 10,000 B None 2 2 3,000 3,000 C A 3 1 12,000 40,000 D B 3 2 12,000 28,000 E C 1 1 8,000 8,000 F D, E 5 3 5,000 15,000 G E 3 2 9,000 18,000 H F, G 8 6 14,000 32,000 Construct a network diagram for the project. What are the project completion time and the total cost under normal conditions? What is the shortest time duration for this project regardless of cost? What is the resulting total cost? What is the…arrow_forwardexample 2. please show solution.arrow_forwardOnly typed explanation otherwise leave itarrow_forward
- B indicate critical path C what is expected completion for the project? D what is the probability that the project will take more than 30 days to complete?arrow_forward2. Joe and Noël have just gotten engaged. As they are both business students, they thought they'd try to plan their wedding preparation as a project. Here's the WBS they've determined is necessary for a simple but elegant wedding. Assume all durations are deterministic. Although perhaps not realistic to real wedding planning, by using the standard calendar in Project Libre (use default working days in software). Task ID Task Name Duration Predecessor 1 Begin Wedding Planning (milestone) 0 days --- 2 Select Site&Date 3 wks 1 3 Hire Officiant 1 wk 2 4 Hire Caterers 2 wks 1 5 Pick Menu 4 days 4 6 Order Invitations 2 wks 2,5 7 Sent Invitations to Guests 1 wk 6 8 Collect RSVPs 6 wks 7 9 Tell Caterer headcount & Order food 1 wk 8 10 Shop for Wedding Gown 4 wks 1 11 Select Bridesmaids Dresses 4 wks 10 12 Bride goes on Diet 6 wks 10 13 Get Wedding Gown altered 2 wks 12 14 Get Bridemaids' Dresses altered 4 wks 11 15 Order Flowers 2 wks 11 16…arrow_forward#9arrow_forward
- Consider the office renovation project data in the following table. A "zero" time estimate means that the activity could take a very small amount of time and should be treated as a numeric zero in the analysis. a. Based on the critical path, find the probability of completing the office renovation project by 39 days. Refer to the standard normal table (Make sure to round all intermediate calculations for te and variance to two decimal places.) The probability isarrow_forwardA T= 4 T= 3 F T= 3 T= 3 D E G T= 1 T= 2 T= 2 The network diagram of a project along with the activity durations (T) is given in the figure. Which activities form one of the critical paths? @orsdemir. Copyrighted Content. Cannot be posted. CDEG O ABF О СВF O CF O None of thesearrow_forwardI want this old school paper i want following required A,B and Carrow_forward
- 13arrow_forwardA renovation of the gift shop at Orlando Amway Center has six activities (in hours). For the following estimates of a, m, and b, calculate the expected time and the standard deviationfor each activity:arrow_forward2. Bjorn and Thor are plumbers who have been scheduled to work on the construction of a new school building. Just before the start of the project, Bjorn broke his arm and cannot work on the project. Now Thor has to handle his own activities as well as Bjorn's. Level the project Gantt chart so that Thor is responsible for activities 3, 4, 6, and 7. What is the new estimated completion date for the project? O 1 2 3 45 6 67 8 Task Task Name Mode * ✰ ✰ Activity 1 activity 2 Activity 3 activity 4 Activity 5 Activity 6 Activity 7 Activity 8 Feb 17, 19 SIMTIWITIFS |Feb 24, '19 SIMT|WT|FISSMITIWIT Bjorn Thor Mar 3, 19 Bjorn Thorarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.