
Concept explainers
Constrained Optimization: One Internal Binding Constraint
Patz Company produces two types of machine parts: Part A and Part B, with unit contribution margins of $100 and $200, respectively. Assume initially that Patz can sell all that is produced of either component. Part A requires two hours of assembly, and B requires five hours of assembly. The firm has 100 assembly hours per week.
Required:
1. Express the objective of maximizing the total contribution margin subject to the assembly-hour constraint.
Objective function: Max Z = $100 A + $200 B
Subject to: fill in the blank 1 A + fill in the blank 2 B ≤ fill in the blank 3
2. Identify the optimal amount that should be produced of each machine part. If none of the components should be produced, enter "0" for your answer.
Component A | fill in the blank 4 | units |
Component B | fill in the blank 5 | units |
Identify the total contribution margin associated with this mix.
$fill in the blank 6
3. What if market conditions are such that Patz can sell at most 25 units of Part A and 20 units of Part B? Express the objective function with its associated constraints for this case.
Objective function: Max Z = $100 A + $200 B
Assembly-hour constraint | fill in the blank 7 A + fill in the blank 8 B ≤ fill in the blank 9 |
Demand constraint for Part A | A ≤ fill in the blank 10 |
Demand constraint for Part B | B ≤ fill in the blank 11 |
Identify the optimal mix and its associated total contribution margin.
Component A $fill in the blank 12 units
Component B $fill in the blank 13 units
Total contribution $fill in the blank 14

Trending nowThis is a popular solution!
Step by stepSolved in 3 steps

- You have developed the following simple product structure of items needed for your gift bag for a rush party for prospective pledges in your organization. You forecast 200 attendees. Assume that there is no inventory on ha nd of any of the items. Explode the bill of material. (Subscripts indicate the number of units required.)arrow_forwardThe president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next 8 months as follows: 2,200 January 1,400 May February 1,600 June 2,200 March April 1,800 1,800 July August 1,800 1,400 Her operations manager is considering a new plan, which begins in January with 200 units of inventory on hand. Stockout cost of lost sales is $100 per unit. Inventory holding cost is $25 per unit per month. Ignore any idle-time costs. The plan is called plan C. Plan C: Keep a stable workforce by maintaining a constant production rate equal to the average gross requirements excluding initial inventory and allow varying inventory levels. Conduct your analysis for January through August.arrow_forwardSolve the problem about linear programming subparts A,B,C with the step and no reject. Im needed in 60 minutes thank u. This problem q&a 8. A group of students are planning to sell Takjil Iftar. The results of their joint venture collected capital of IDR 600,000. The cost to make Ice is IDR 4000 Per Cup while Cake IDR 2,000 per piece. Due to limitations they decided to only sell a maximum of 200 cakes. They estimate that one cup of fruit ice will generate a profit of IDR 500 and Cake IDR 300 per piece. So : A. Create a linear function B. calculate how much profit you get C. Make Linear Programming Grapharrow_forward
- Prevar Corporation currently purchases components from one of its suppliers. The current purchase price is $1500 per component, with annual purchase volume of 750 units. The ops manager believes that this component could be made inhouse with some minor modifications to the current factory set up. Fixed cost for dedicating a line for this component is estimated at $50,000. Raw materials for the component is estimated at $900, overhead at $200 and it would take 10 hours of labor (at $20 per hour) to produce each component.arrow_forwardRipeka, the warehouse manager at Hine would like to update the company’s inventory locator system so that the picking operation can be streamlined. While conceptually simple to do, she knows that there will be several steps to the update process that will have to be carefully managed. She needs to complete upgrade and train her staff in operating the new system before the busy season, which is only 4 months away. She identifies the various activities, expected time duration, predecessors and costs, as shown in the table. Draw the AON Network, and then determine the critical path. [Show your workings, using the grid network.] Identify the project duration – is this project feasible within the required timeframe?arrow_forwardA JIT system schedules ______. Parts Capacity MPS Operationsarrow_forward
- (1) This DC value-adding activity allows it to receive full truckloads of one product and ship full truckloads of various products to customers. a. allocation b. mixing c. assembly d. kitting (2) As Q increases for EOQ, the cost per order: a. increases b. decreases c. stays the same d. cannot be determinedarrow_forwardA factory has just received an order for 95 units of an end item, which are to be shipped at the start of week 8. Relevant information of the end item and the components is as follows. Lead Time On Hand Scheduled Item Order Direct (weeks) Inventory receipts Policy Components End item 15 lot for lot A(3), B(2) A 2 10 33 at week 3 lot for lot C(1), D(4) B. 2 20 15 at week 4 lot for lot D(2) min. of 500 lot for lot 100 20 Develop the material requirements plan (please print out an empty MRP table to work with), and determine how many units of component Care needed in the "planned order release". Input should be an exact number.arrow_forwardQty Standard Labor Hour Raw Material В Standard Labor 2 Hours Raw Material INDEPENDENT DEMAND Period 1 2 3 4 5 6 Total Product A 1,000 1,000 1,000 1,000 1,000 1,000 6,000 Product B 500 500 ,500 500 16. Products A and B are produced on two different dedicated production lines. If both lines work on the same shift schedule, the ratio of workers on line A to workers on line B is A. 2:1 В. 2:3 С. 2:5 D. 4:1arrow_forward
- . Terminator, Inc., manufactures a motorcycle part in lots of 250 units. The raw materials cost for the part is $150, and the value added in manufacturing 1 unit from its components is $300, for a total cost per completed unit of $450. The lead time to make the part is 3 weeks, and the annual demand is 4,000 units. Assume 50 working weeks per year. a. How many units of the part are held, on average, as cycle inventory? What is its value? b. How many units of the part are held, on average, as pipeline inventory? What is its value?arrow_forwardThe demand for subassembly Sis 100 units in week 7.Each unit ofS requires 1 unit ofT and 2 units ofU. Each unit ofT requires I unit ofY, 2 units ofW, and 1 unit of X. Finally, eachunit of U requires 2 units of Y and 3 units of Z. One firm manufacturesall items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make Y, 3 weeks to make W,I week to make X, 2 weeks to make Y, and I week to make Z.a) Construct a product structure. Identify all levels, parents, and components.b) Prepare a time-phased product structure.arrow_forward4. Terminator, Inc., manufactures a motorcycle part in lots of 250 units. The raw materials cost for the part is $170, and the value added in manufacturing 1 unit from its components is $320, for a total cost per completed unit of $490. The lead time to make the part is 4 weeks, and the annual demand is 4,200 units. Assume 50 working weeks per year. a. How many units of the part are held, on average, as cycle inventory? ___ units. (Enter your response as an integer.) What is its value? $______ (Enter your response as an integer.) b. How many units of the part are held, on average, as pipeline inventory? _____units. (Enter your response as an integer.) What is its value? $______ (Enter your response as an integer.)arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.





