Consider the following tasks that must be assigned to four workers on a conveyor-paced assembly line (i.e., a machine-paced line flow). Each worker must perform at least one task. There exists unlimited demand unless stated otherwise. Time to Complete Task (seconds): Task 1: 30 Task 2: 25 Task 3: 15 Task 4: 20 Task 5: 15 Task 6: 20 Task 7: 50 Task 8: 15 Task 9: 20 Task 10: 25 Task 11: 15 Task 12: 20 The current conveyor-paced assembly-line configuration assigns the workers in the following way: • Worker 1: Tasks 1, 2, 3 • Worker 2: Tasks 4, 5, 6 • Worker 3: Tasks 7, 8, 9 • Worker 4: Tasks 10, 11, 12 Assume a demand rate of 20 units per minute. What would be the takt time of the process (in seconds per unit)?
Consider the following tasks that must be assigned to four workers on a conveyor-paced assembly line (i.e., a machine-paced line flow). Each worker must perform at least one task. There exists unlimited
Time to Complete Task (seconds):
Task 1: 30
Task 2: 25
Task 3: 15
Task 4: 20
Task 5: 15
Task 6: 20
Task 7: 50
Task 8: 15
Task 9: 20
Task 10: 25
Task 11: 15
Task 12: 20
The current conveyor-paced assembly-line configuration assigns the workers in the following way:
• Worker 1: Tasks 1, 2, 3
• Worker 2: Tasks 4, 5, 6
• Worker 3: Tasks 7, 8, 9
• Worker 4: Tasks 10, 11, 12
Assume a demand rate of 20 units per minute. What would be the takt time of the process (in seconds per unit)?