Consider the flow in Figure 7–1 but assume that no patients require follow-upappointments. All patients first check in with the single receptionist, which takesan average of 6 minutes. They are then seen by one of two nurses who take weight,blood pressure, etc., which takes an average of 10 minutes. Finally, they are seenby a GP in an examination room, which takes an average of 16 minutes. There arethree GPs. The table below summarizes this data. Assume the clinic has no waitingroom or examination room constraints.Assume that there are eight patients arriving an hour during working hours.Resource Minutes per patient Number of resourcesReceptionist 6 1Nurse 10 2Doctor 16 3a. What is the capacity of each resource?b. Which resource is the bottleneck and hence what is the capacity of the system?
Critical Path Method
The critical path is the longest succession of tasks that has to be successfully completed to conclude a project entirely. The tasks involved in the sequence are called critical activities, as any task getting delayed will result in the whole project getting delayed. To determine the time duration of a project, the critical path has to be identified. The critical path method or CPM is used by project managers to evaluate the least amount of time required to finish each task with the least amount of delay.
Cost Analysis
The entire idea of cost of production or definition of production cost is applied corresponding or we can say that it is related to investment or money cost. Money cost or investment refers to any money expenditure which the firm or supplier or producer undertakes in purchasing or hiring factor of production or factor services.
Inventory Management
Inventory management is the process or system of handling all the goods that an organization owns. In simpler terms, inventory management deals with how a company orders, stores, and uses its goods.
Project Management
Project Management is all about management and optimum utilization of the resources in the best possible manner to develop the software as per the requirement of the client. Here the Project refers to the development of software to meet the end objective of the client by providing the required product or service within a specified Period of time and ensuring high quality. This can be done by managing all the available resources. In short, it can be defined as an application of knowledge, skills, tools, and techniques to meet the objective of the Project. It is the duty of a Project Manager to achieve the objective of the Project as per the specifications given by the client.
Consider the flow in Figure 7–1 but assume that no patients require follow-up
appointments. All patients first check in with the single receptionist, which takes
an average of 6 minutes. They are then seen by one of two nurses who take weight,
blood pressure, etc., which takes an average of 10 minutes. Finally, they are seen
by a GP in an examination room, which takes an average of 16 minutes. There are
three GPs. The table below summarizes this data. Assume the clinic has no waiting
room or examination room constraints.
Assume that there are eight patients arriving an hour during working hours.
Resource Minutes per patient Number of resources
Receptionist 6 1
Nurse 10 2
Doctor 16 3
a. What is the capacity of each resource?
b. Which resource is the bottleneck and hence what is the capacity of the system?