Question
Consider a system containing three periodic tasks: T1 = (10,3), T2 = (30,5), and T3 = (60,6), handled by Rate Monotonic. Solve the scheduling produced by a sporadic server with Ts = 20, Cs = 5, which is scheduled with the other tasks according to the RMA principle. Suppose there are three sporadic jobs S1 = (10,7,30) and S2 = (15,3,60), and S3 = (20,8,70). Work out a timing diagram showing the schedule of the system. Would any deadline be broken?
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 2 steps
Knowledge Booster
Similar questions
- Consider a computer system which has four identical units of a resource R. There are three processes each with a maximum claim of two units of resource R. Processes can request these resources in any way that is, two in one shot or one by one. The system always satisfies a request for a resource if enough resources are available. If the processes don't request any other kind of resource, show that the system never deadlocks?arrow_forwardGIPSY (General Intensional Programming System) is a Demand-Driven Execution System that is based on Demand Generators (DGs) that determine the control process by generating functional demands and workers that execute them. These workers are potentially remote ones, in which case the demands are migrated via the network from the generator to the worker. In that sequence, the problem statement is the need of GIPSY Demand Migration System (DMS) that connects the GIPSY’ execution nodes.The model of our DMS consists of two major contributors called Demand Dispatcher (DD) and Transport Agents (TAs). They both run independently, but form together the overall behavior of DMS. The DD acts like an event-driven message storage mechanism that uses the TAs to deliver the messages to their recipients. The DMS relies on these two contributors to form a communication system similar to the e-mail systems, i.e. the messages are delivered when they are asked, but until that moment, they are…arrow_forwardIn a computer system five processes are attempting to proceed with three resource types. The total units of system resources are: (8,9,7). The maximum demands for every process are: P1(3,1,1), P2(3,3,2), P3(5,3,2), P4(5,1,2), P5(8,4,3). The current allocation is: P1 (0,1,1), P2 (2,1,1), P3 (3,1,2), P4 (1,1,1), and P5 (2,3,2). Is this state a safe state? Explain your answer. Please explain in great detail so i can understand .arrow_forward
- Suppose that an operating system supports two kinds of sequential processes: high-priority interactive processes, and low-priority non-interactive processes. The behavior of the high-priority processes is to alternate between periods of computation of duration Tc and periods of blocking (waiting for input) of duration Tb. The behavior of the low-priority processes is to compute constantly, with no blocking. The operating system’s scheduling policy is round-robin with a quantum q, where Tc < q. Scheduling decisions are made only when a quantum expires, or when the running process blocks. The scheduler selects a low-priority process to run only if no high-priority processes are ready. Suppose there is one high-priority process and one low-priority process in the system, and that both processes will run for a long time. For what fraction of the time does the low-priority process run?arrow_forwardCan you provide me the step-by-step solution for this activity to understand more on how to solve this activity?arrow_forwardConsider a memory of size 8KB (8192 bytes) that allows dynamic, variable sized partitioning among processes and uses a linked list to keep track of free spaces (hereafter referred to as the free list) in the memory at any given time. Assume that there are 6 processes and assume that their memory size requirements (in bytes) are as given below: Р1: 500, Р2: 600, Р3: 1300, Р4: 2000, Р5: 100, Р6: 200 Assume that the initial state of the free list is as shown below (BA is the base address and Sz is the size of each free space): ВА: 0; Sz: 1100 — ВА: 1200; Sz: 600 > BА: 2000; Sz: 1800> ВА: 6000%; Sz 400arrow_forward
- Consider a single-server queueing system with arrival and service details as: Interarrival times 3 2 6 2 45 Service times 2 5 5845 Prepare simulation table using Event Scheduling / Time Advance Algorithm for the given data. Stop simulation when the clock reaches 20. In the simulation table, include the following: 1) B: Cumulative Busy Time 2) MQ: Cumulative Maximum number of Customers in Queue 3) F: Cumulative number of Customers who spent more than 3 minutes in the system. 1arrow_forward1 Problem : Interarrival Time and Service Time in a simulation study for a bank system are shown in the following table: Interarrival Time (min) 2 1 6 3 6 4 2 4 1 Service Time (min) 4 3 4 5 1 5 3 2 4 If the simulation runs for 1 hour, build the simulation table and the scheduling table for first 20mins. You need to perform, FEL, Service Time, Idle/Busy Status, Queue Length, and so on.arrow_forwardConsider the following set of processes (a smaller priority number implies a higher priority). The processes are assumed to have arrived in the order P1, P2, P3, P4, P5 all at time 0. Process Priority Burst Time P1 1 20 P2 3 25 P3 4 25 P4 2 15 P5 5 30 What is the waiting time of each process for each of the scheduling algorithms FCFS, SJF (if two jobs have the same burst time, schedule them following priority), non-preemptive priority? Process FCFS SJF Priority P1 P2 P3 P4 P5arrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- Computer Networking: A Top-Down Approach (7th Edi...Computer EngineeringISBN:9780133594140Author:James Kurose, Keith RossPublisher:PEARSONComputer Organization and Design MIPS Edition, Fi...Computer EngineeringISBN:9780124077263Author:David A. Patterson, John L. HennessyPublisher:Elsevier ScienceNetwork+ Guide to Networks (MindTap Course List)Computer EngineeringISBN:9781337569330Author:Jill West, Tamara Dean, Jean AndrewsPublisher:Cengage Learning
- Concepts of Database ManagementComputer EngineeringISBN:9781337093422Author:Joy L. Starks, Philip J. Pratt, Mary Z. LastPublisher:Cengage LearningPrelude to ProgrammingComputer EngineeringISBN:9780133750423Author:VENIT, StewartPublisher:Pearson EducationSc Business Data Communications and Networking, T...Computer EngineeringISBN:9781119368830Author:FITZGERALDPublisher:WILEY
Computer Networking: A Top-Down Approach (7th Edi...
Computer Engineering
ISBN:9780133594140
Author:James Kurose, Keith Ross
Publisher:PEARSON
Computer Organization and Design MIPS Edition, Fi...
Computer Engineering
ISBN:9780124077263
Author:David A. Patterson, John L. Hennessy
Publisher:Elsevier Science
Network+ Guide to Networks (MindTap Course List)
Computer Engineering
ISBN:9781337569330
Author:Jill West, Tamara Dean, Jean Andrews
Publisher:Cengage Learning
Concepts of Database Management
Computer Engineering
ISBN:9781337093422
Author:Joy L. Starks, Philip J. Pratt, Mary Z. Last
Publisher:Cengage Learning
Prelude to Programming
Computer Engineering
ISBN:9780133750423
Author:VENIT, Stewart
Publisher:Pearson Education
Sc Business Data Communications and Networking, T...
Computer Engineering
ISBN:9781119368830
Author:FITZGERALD
Publisher:WILEY