Compute the industrial building allowances and balancing charges (if any) for both companies for all the relevant years of assessment up to the year of assessment 2021
Maju Bhd constructed a factory at a cost of RM2,800,000 of which RM1,200,000 was for the cost of the land. The building was completed on 1 November 2015 and one eleventh (1/11) of the building was used as an office.
On 1 February 2020, the building was sold to Indera Bhd for RM3,750,000 (including RM1,400,000 for the land). Indera Bhd uses the whole building as a factory. An extension to the building costing RM140,000 was constructed by Indera Bhd and completed on 2 May 2020. It was used as a warehouse for the storage of raw materials for its manufacturing business. Both companies close their accounts on 31 March annually
required :
Compute the industrial building allowances and balancing charges (if any) for both companies for all the relevant years of assessment up to the year of assessment 2021
Step by step
Solved in 4 steps