b) A construction company has identified the following two mutually exclusive projects. The company used 10% discount rate Cash flows (Project A) ($100,000) Cash flows (Project B) ($100,000) Year 1. 50,000 40,000 2 40,000 40,000 30,000 40,000 30,000 40,000 Calculate Net Present Value and Actual Rate of return for both the projects.. How will you evaluate each project using these project evaluation methods?
Q: A company is considering two projects. The discount rate is 10 percent, and the projects' cash flows…
A: IRR is the rate at which NPV is zero
Q: What is the IRR for each of this project (range: 10-16%)? Using the IRR decision rule, which project…
A: The internal rate of return is a metric used in financial analysis to estimate the profitability of…
Q: Consider the following mutually exclusive project below. Whichever project chosen, a 15 percent…
A: Capital budgeting is the process a business undertakes to evaluate potential major projects or…
Q: The following information relates to two projects of which you have to select one to invest in. Both…
A: To Find: Payback period NPV Accounting rate of return
Q: Assume a $200,000 investment and the following cash flows for two alternative capital projects: Year…
A: Pay Back period is that length of time in which the initial investment of project is recovered in…
Q: Kenny, Inc. has identified the following two mutually exclusive projects. Project A -$25,000 20,000…
A: Capital budgeting indicates the evaluation of the profitability of possible investments and projects…
Q: Quattro, Inc. has the following mutually exclusive projects available. The company has historically…
A: Mutually Exclusive Projects Required Return = 11% Cash Flows: Year Cash Flow (A) Cash Flow (B)…
Q: From the following information calculate the Net Present Value of the two projects & sugge which of…
A: Capital budgeting is a process of investing funds into long terms projects that provide benefits in…
Q: A firm is considering the following two mutually exclusive alternatives as a part of a production…
A: Present value: It is the current value of the future sum of cash flows that company will receive…
Q: Consider two mutually exclusive projects – Project X and Project Y with identical initial outlays of…
A: Capital budgeting means taking decisions related to investments. Capital investments involve the…
Q: HH Companies has identified two mutually exclusive projects. Project A has cash flows of −$40,000,…
A: Given, The project A and project B.
Q: You are evaluating projects 1 and 2. The projects have the following yearly operating profit.…
A: Definition: Net present value method: Net present value method is the method which is used to…
Q: Kenny, Inc. has identified the following two mutually exclusive projects. Project A -$25,000 20,000…
A: “Since you have posted a question with multiple sub-parts, we will solve first three sub-parts for…
Q: You are evaluating projects 1 and 2. The projects have the following yearly operating profit.…
A: Since you have posted a question with multiple sub-parts, we will solve the first three sub-parts…
Q: A company is considering two projects. The discount rate is 10 percent, and the projects' cash flows…
A: NPV =Present Value of Future Cash Flows - Initial Investment IRR is the rate at which Present Value…
Q: A company is considering two projects. The discount rate is 10 percent, and the projects' cash flows…
A: IRR is the rate at which NPV is zero
Q: calculate each project's NPV, and make a recommendation based on your findings.
A: Net Present Value: It is the present worth of the cash flows which include annual cash inflows and…
Q: George Company is evaluating two mutually exclusive projects with 3-year lives. Each project…
A: Capital budgeting process can be defined as a tool of evaluating the profitability and feasibility…
Q: George Company is evaluating two mutually exclusive projects with 3-year nves. Each project requires…
A: Disclaimer: “Since you have posted a question with multiple sub-parts, we will solve first three…
Q: Piercy, LLC, has identified the following two mutually exclusive projects: Year Cash Flow (A) Cash…
A: Calculation of IRR of both the projects and IRR of A-B: Excel workings:
Q: Consider the following cashflow of the two mutually exclusive projects. Assume that the discount…
A: The term net present value or NPV refers to the value left after deducting the initial investment…
Q: Mobil Company has hired a consultant to propose a way to increase the company's revenues. The…
A: Net Present Value = Present Value of annual cash inflows – Initial Investment Profitability Index =…
Q: b) A construction company has identified the following two mutually exclusive projects. The company…
A: Calculation of Net present value and IRR: Excel spreadsheet:
Q: The Whenworth Corporation is trying to choose between the following two mutually exclusive design…
A: Discount rate is 10% To Find: Profitability Index Net present Value
Q: George Company is evaluating two mutually exclusive projects with 3-year lives. Each project…
A: Under the capital budgeting technique, the projects are evaluated on the basis of different methods.…
Q: Consider the following two mutually exclusive projects: Year Cash Flow Cash Flow B 0…
A: NPV (Net Present Value)NPV is the method of finding the worth of an investment or project by…
Q: A company is considering investment of k1,000,000 in a project. The following are the forecasts,…
A: Year Cash Inflows PVF @10 % Present Value 1 10000 0.9091 9091 2 40000 0.8265 40000 3 60000…
Q: flows. Period (Year) Cost (Initial Net cash flow Cost (Initial Outlay) Net cash flow Outlay) $45,000…
A:
Q: hell Camping Gear, Inc., is considering two mutually exclusive projects. Each requires an initial…
A: Payback period is the period in which the overall investment incurred by the company is returned…
Q: A company is considering two projects. The discount rate is 10 percent, and the projects' cash flows…
A: Using the NPV and IRR function in Excel
Q: A company is considering two projects. The discount rate is 10 percent, and the projects' cash flows…
A: Net present value (NPV) is the difference between the present value of cash inflows and cash…
Q: Wau Sdn. Bhd, is evaluating two (2) mutually exclusive projects. The cash flows are as follows Year…
A: Year Project AA Project BB 0 -500000 -600000 1 50000 200000 2 150000 200000 3 250000 200000…
Q: A company is considering two projects. The discount rate is 10 percent, and the projects' cash flows…
A: ANSWERS OF ALL THREE QUESTIONS WILL BE STEPS PROVIDED BELOW
Q: You have been asked by MPAC Ltd to analyse two projects, X and Y. Each project costs £1,000,000, and…
A: Because you have asked question with multiple parts (MULTI PART) , we will solve the first 3 parts…
Q: Determine which of the following independent projects should be selected for investment if a maximum…
A: PW method uses discounting rate with calculate present value of cash outflow and inflow and then…
Q: A potential project involves an initial investment in machinery of RO.1,000,000 and has the…
A: Depreciation expense per year: Straight depreciation expense per year = Cost-Salavage valueUseful…
Q: If the two projects are independent, which project(s) should be chosen? If the two projects are…
A: a) To calculate NPV and IRR, we use excel By entering the following formulas,
Q: You are asked to evaluate the following two projects for the Norton Corporation. Using the net…
A: In this we have to calculate present value of cash flow and from that we can get net present value…
Q: All techniques-Decision among mutually exclusive investments Pound Industries is attempting to…
A: Capital budgeting is the process of making an investment in long-term assets. It includes the…
Q: he cash flows associated with a public works project in Buffalo, New York, are shown. Use the…
A: Benefit cost analysis is calculated by dividing the discounted benefits by the discounted costs.…
Q: George Company is evaluating two mutually exclusive projects with 3-year lives. Each project…
A: Note: Since we only answer up to 3 sub-parts, we’ll answer the first 3. Please resubmit the question…
Q: Develop a cash flow worksheet based on the following information, initial investment = 500,000,…
A: Cash flow represents the movement of cash inside and outside the organisation representing the…
Q: The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each project…
A: Standard Deviation(SD) and Coefficient of Variation(COV) are the tools used to measure uncertainty…
Q: A company is considering two projects. The discount rate is 10 percent, and the projects’ cash flows…
A: There are 3 questions answers will be provided step by step.
Q: Quattro, Inc. has the following mutually exclusive projects available. The company has historically…
A: Capital budgeting indicates the evaluation of the profitability of possible investments and projects…
Q: Moates Corporation has provided the following data concerning an investment project that it is…
A: Solution: Computation of NPV - Moates Corporation Particulars Period Amount PV factor at 10%…
Q: The data below are estimated for the project for the project study of a certain business investment.…
A: The present worth method of valuation is an equivalence method in which the cash flows of a project…
Step by step
Solved in 2 steps with 1 images
- a. Consider the following mutually exclusive project below. Whichever project chosen, a 15 percent return is required on the investment. Year Cash Flow (A) Cash Flow (B) -RM300,000 -RM40,000 1 RM20,000 RM19,000 RM50,000 RM12,000 3 RM50,000 RM18,000 4 RM390,000 RM10,500 i. Indicate which investment is chosen by applying the discounted payback criterion. th x9 ii. Indicate which investment is chosen using the NPV criterion. the' iii. Indicate which investment is chosen according to the probability index. 2.a. Consider the following mutually exclusive project below. Whichever project chosen, a 15 percent return is required on the investment. Year Cash Flow (A) Cash Flow (B) -RM300,000 -RM40,000 1 RM20,000 RM19,000 RM50,000 RM12,000 3 RM50,000 RM18,000 4 RM390,000 RM10,500 i. Indicate which investment is chosen by applying the discounted payback criterion. Indicate which investment is chosen using the NPV criterion. ii. iii. Indicate which investment is chosen according to the probability index. 2.es The Michner Corporation is trying to choose between the following two mutually exclusive design projects: Year Cash Flow (1) Cash Flow (II) -$ 0 1 2 3 Project I Project II 67,000 30,500 30,500 30,500 a-1.If the required return is 11 percent, what is the profitability index for both projects? (Do not round Intermediate calculations and round your answers to 3 decimal places, e.g., 32.161.) a. If the company applies the profitability index decision rule, which project should the 2. firm accept? Project I Project II 17,700 9,550 9,550 9.550 O Project I O Project II b- What is the NPV for both projects? (A negative answer should be Indicated by a 1. minus sign. Do not round Intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) b- If the company applies the NPV decision rule, which project should it take? 2. O Project I O Project II
- Consider the following two mutually exclusive projects: Year Cash flow project A (RM) 0 1 2 3 4 -54,000 12,700 23,200 27,600 46,500 Cash flow Project B (RM) -23,000 11,600 11,200 12,500 6,000 Whichever project you choose, if you require a 14 percent return on your investment i) Compute the payback period for both project ii) Compute the Net Present Value (NPV) for both projects. iii) Which project do you prefer and which? Fully explain the result of your analysis1. Consider the following two mutually exclusive projects, X and Y, and their cash flows information, Project X Y (a) (b) Year 0 ($2,600) ($3,100) Year 1 $1,000 $ 900 Cash Flows Year 2 $1,300 $1,500 Year 3 $ 800 $1,100 Year 4 $ 400 $ 800 Assume that the appropriate discount rate is 14%, calculate the Payback Period, the Modified IRR (McKinsey's approach) AND the Profitability Index for Project Y. State clearly the key piece of information that you need in order to make the correct investment recommendation on the two projects according to the Payback Period method. Given that Project X's IRR is 15.16%, which project should be chosen according to the IRR method? Precisely explain how you should construct the incremental project and its cash flows numerically. Precisely explain your final selection between these two mutually exclusive projects according to the incremental project (IRR) analysis.Consider the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 −$29,000 −$29000 1 14,400 4,300 2 12,300 9,800 3 9,200 15,200 4 5,100 16,800 a) What is the Internal Rate of Return (IRR) for each of these projects? b) Using the IRR decision rule, which project should the company accept? c) If the required return is 11 percent, what is the Net Present Value (NV) for each of these projects? d) Using the NPV decision rule, which project should the company accept? e) Why do you think the NPV and IRR rules do not agree on same project approval/rejection direction?
- Consider the following two mutually exclusive projects: Year Cash Flow(A) -$ 63,000 39,000 33,000 22,500 14,600 Cash Flow(B) -$ 63,000 25,700 29,700 35,000 24,700 4 1-What is the IRR for each project? Project A Project B % % 2.IF you apply the IRR decision rule, which project should ti 3.Assume the required return is 14 percent. What is the NP Project A Project B 0123Piercy, LLC, has identified the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 -$56,000 -$56000 1 32,000 19,400 2 26,000 23,400 3 19,000 28,000 4 13,200 25,400 Over what range of Discount rates would you choose Project A? Project B? (Please list percentages rounded to 2 decimal places. Hint: The answer is not the same as the IRR.) Project A ____________% Project B ____________% At what discount rate would you be indifferent between these two projects? ____________%A company is considering two projects. The discount rate is 10 percent, and the projects' cash flows would be: Years 1 3 Project A -$700 $500 $300 $100 Project B -$700 $100 $300 | $600 a. Calculate the projects' NPVS and IRRS. b. If the two projects are independent, which project(s) should be chosen? c. If the two projects are mutually exclusive, which project should be chosen?
- The Michner Corporation is trying to choose between the following two mutually exclusive design projects: Year Cash Flow (1) Cash Flow (II) 0 123 -$ 73,000 33,000 33,000 3 33,000 -$ 17,100 9,250 9,250 9,250 a-1.If the required return is 11 percent, what is the profitability index for both projects? (Do not round intermediate calculations and round your answers to 3 decimal places, e.g., 32.161.) Project I Project II - If the company applies the profitability index decision rule, which project should the 2. firm accept? O Project I O Project II b- What is the NPV for both projects? (A negative answer should be indicated by a 1. minus sign. Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) Project I Project IIConsider the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) -$ 15,456 5,225 8,223 13,013 8,705 0 1 234 -$ 276,363 26,400 51,000 57,000 402,000 Whichever project you choose, if any, you require a 6 percent return on your investment. a. What is the payback period for Project A? Payback period b. What is the payback period for Project B? Payback period c. What is the discounted payback period for Project A? Discounted payback periodConsider the following two mutually exclusive projects: Year Cash Flow Cash Flow (X) (Y) 0 -$20,800 -$20,800 1 9,050 10,500 2 9,500 8,000 3 9,000 8,900 IRR Project X: 15.49% Project Y: 15.69% What is the crossover rate for these two projects? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) Crossover rate ______%