Question

Arrow and node diagram 

 

Financial data of a highway construction project is given below. You are questioned to develop a plan
such that both cost and project duration would be at optimum status. A,C,E.H are the activities that have
no float
V Office rent $ 50/- per day
V Bills $ 30/- per day
* Miscellaneous expenses $ 20/- per day
Duration (days)
NORMAL
Cost ($)
ACTIVITY
IPA
CRASH
NORMAL
400
250
700
1100
700
400
600
200
CRASH
500
400
820
1300
800
450
A
5.
11
7.
BC
6.
4.
900
G.
H.
D. F
EF
320
Transcribed Image Text:Financial data of a highway construction project is given below. You are questioned to develop a plan such that both cost and project duration would be at optimum status. A,C,E.H are the activities that have no float V Office rent $ 50/- per day V Bills $ 30/- per day * Miscellaneous expenses $ 20/- per day Duration (days) NORMAL Cost ($) ACTIVITY IPA CRASH NORMAL 400 250 700 1100 700 400 600 200 CRASH 500 400 820 1300 800 450 A 5. 11 7. BC 6. 4. 900 G. H. D. F EF 320
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Design of Structures using FEA
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning