An IT project manager of ABC Company has developed an activity list for the purpose of tracking employees' daily activities on the project. The project's schedule is considered to be of high risk due to the possibility of sabotage by some of the employees. In addition, the IT project manager has gathered time information for each activity, as shown in the table below. Consider the following project's tasks and their identified best, likely, and worst case estimates of task duration. Assume the organization computes PERT weight average based on the standard formula. Activity Optimistic Most Pessimistic likely A 5 5 3 8 C 7 D 4 4 E 10 19 34 F 3 14 18 G 6. 16 20 H 32 44 65 I 12 17 25 J 8. 18 25

Advanced Engineering Mathematics
10th Edition
ISBN:9780470458365
Author:Erwin Kreyszig
Publisher:Erwin Kreyszig
Chapter2: Second-order Linear Odes
Section: Chapter Questions
Problem 1RQ
icon
Related questions
Question

The dependencies between the 10 activities listed in the table above are as follows:
• The project starts with two activities—A, and B—which can be done concurrently.
• When activity A is finished, activity C can start
• When activity B is finished, activities D and E can start
• When both activities C and D are finished, activity F can start
• When activity E is finished, activity G can start
• When activity F is finished, activity H can start
• When both activities G and H are finished, activity I can start
• When activity G is finished, activity J can start
• The project is complete when activities I and J are finished

 


Questions
1. Organize the information above in an activity precedence table showing the activity, precedent and duration (calculated using the PERT weighted average formula and round to the nearest integer).
2. Draw an AON network diagram and calculate its early start, early finish, late start and late finish times, floats (Free and total) for each activity. Make sure you fully label all nodes in the network.
3. Identify the project’s critical path and its length

An IT project manager of ABC Company has developed an activity list for the purpose of
tracking employees' daily activities on the project. The project's schedule is considered to be of
high risk due to the possibility of sabotage by some of the employees. In addition, the IT project
manager has gathered time information for each activity, as shown in the table below. Consider
the following project's tasks and their identified best, likely, and worst case estimates of task
duration. Assume the organization computes PERT weight average based on the standard
formula.
Activity Optimistic Most
Pessimistic
likely
A
25
В
3
5
8
C
7
5
8
D
4
4
E
10
19
34
F
3
14
18
16
20
H
32
44
65
I
12
17
25
J
2
18
Transcribed Image Text:An IT project manager of ABC Company has developed an activity list for the purpose of tracking employees' daily activities on the project. The project's schedule is considered to be of high risk due to the possibility of sabotage by some of the employees. In addition, the IT project manager has gathered time information for each activity, as shown in the table below. Consider the following project's tasks and their identified best, likely, and worst case estimates of task duration. Assume the organization computes PERT weight average based on the standard formula. Activity Optimistic Most Pessimistic likely A 25 В 3 5 8 C 7 5 8 D 4 4 E 10 19 34 F 3 14 18 16 20 H 32 44 65 I 12 17 25 J 2 18
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 1 images

Blurred answer
Similar questions
Recommended textbooks for you
Advanced Engineering Mathematics
Advanced Engineering Mathematics
Advanced Math
ISBN:
9780470458365
Author:
Erwin Kreyszig
Publisher:
Wiley, John & Sons, Incorporated
Numerical Methods for Engineers
Numerical Methods for Engineers
Advanced Math
ISBN:
9780073397924
Author:
Steven C. Chapra Dr., Raymond P. Canale
Publisher:
McGraw-Hill Education
Introductory Mathematics for Engineering Applicat…
Introductory Mathematics for Engineering Applicat…
Advanced Math
ISBN:
9781118141809
Author:
Nathan Klingbeil
Publisher:
WILEY
Mathematics For Machine Technology
Mathematics For Machine Technology
Advanced Math
ISBN:
9781337798310
Author:
Peterson, John.
Publisher:
Cengage Learning,
Basic Technical Mathematics
Basic Technical Mathematics
Advanced Math
ISBN:
9780134437705
Author:
Washington
Publisher:
PEARSON
Topology
Topology
Advanced Math
ISBN:
9780134689517
Author:
Munkres, James R.
Publisher:
Pearson,