After training, Mary Fernandez, a computer technician, had an average observed time for memory-chip tests of
10 seconds. Mary's performance rating is 105%.
The firm has a personal fatigue and delay allowance of
18%.
a) The normal time for this process = ? seconds (round your response to two decimal places).
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 2 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- How would you classify the following job elements? Are they personal, fatigue, or delay?a) The operator stops to talk to you.b) The opera tor lights up a cigarette.c) The operator opens his lunch pail (i t is no t lunch time),removes a n a pple, and takes an occasional bite.arrow_forwardUnited Research Associates (URA) had received a contract to produce two units of a new cruise missile guidance control. The ?rst unit took 4,000 hours to complete and cost $30,000 in materials and equipment usage. The second took 3,200 hours and cost $21,000 in materials and equipment usage. Labor cost is charged at $18 per hour.The prime contractor has now approached URA and asked to submit a bid for the cost of producing another 20 guidance controls.a. What will the last unit cost to build?b. What will be the average time for the 20 missile guidance controls?c. What will the average cost be for guidance control for the 20 in the contract?arrow_forwardIn time study, the rating factor is applied to determine a)standard time of a job b)merit rating of the worker c)fixation of incentive rate d)normal time of a worker [Don't use chatgpt otherwise give 20downvotes]arrow_forward
- The “worker” in this scenario had to perform a candy-sorting task and the rest of the class hadto record the observed times (OT) for the task. It was decided that the rating for the “worker” was 100%. Given the following table, find the Normal Time for each element. Write your answers in order from Element #1 --> Element #5. Answers must have one decimal place: e.g. 3.0 or 12.5 Element Trail 1 Trial 2 Normal Time 1 Walk to podium 3 sec 3 sec 2 Fill mug 5 sec 6 sec 3 Walk to desk/sit 5 sec 4 sec 4 Sort Candy 12 sec 12 sec 5 Walk to desk 4 sec 4 secarrow_forward8.25. Describe the differences between a process flowchart and a worker-machine chart and what they are designed to achieve. 8.26. Pick an activity you are familiar with in your daily life such as washing a car, cutting grass, or taking a shower, and develop a process flowchart for it.arrow_forwardFor a time study of a health insurance claims-adjusting process, the analyst uses the continuous method of recording times. The job is divided into four work elements. Shown in Figure are the performance rating factors, RF, and the continuous method recorded times, r, for each work element.a. Calculate the normal time for this job. b. Calculate the standard time for this job, assuming that the allowance is 20 percent of the normal time. c. What is the appropriate sample size for estimating the time for element 2 within {10 percent of the true mean with 95 percent confidence?arrow_forward
- Of the session management best practices, which are the top three in importance? Describe each best practice with some detail.arrow_forwardClaudine Soosay recorded the following times assembling a watch: Observation No. 1 2 3 4 5 6 7 8 Performance rating is given as 95%. a) The average time of Claudine for the operation = Time (minutes) 0.11 0.09 0.11 0.09 0.15 0.10 0.09 0.10 Observation No. 9 10 11 12 13 14 15 16 minutes (round your response to three decimal places). Time (minutes) 0.11 0.09 0.11 0.10 0.11 0.12 0.14 0.10arrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.