Consider the following information for a project to add a drive-through window at Crestview Bank.
Activity Activity Time (days) Immediate Predecessor(s)
C 4 A
D 4 B, C
E 4 D
F 3 E
G 5 E
a. Draw the network diagram for this project.
b. Determine the critical path and project duration.
c. Calculate the slack for each activity.


Trending nowThis is a popular solution!
Step by stepSolved in 3 steps with 3 images

- This project has the following activities that need to be completed (see Table below) a) Draw the AOA and AON diagrams b) Find the critical path in AOA and AON Diagrams. Show calculations and table. c) Find the completion time. Show calculations d) Find the duration of each activity. Show calculations e) Show the predecessors in a table format. Activity TE AB 1 AC 3 AD 3 DC 4 CB 3 DE 8 CF 2 BF 4 IJ 2 CE 6 EF 5 FG 10 FH 11 EH 1 GH 9 EJ 3 GI 8 HJ 6 .arrow_forwardRelevant information for a project consisting of activities A, B, ..., K is provided in the table below and the project network is provided. Activity Time in Weeks Immediate Predessors A 2 ΝΑ B C D E F G H I J K 7 7 6 2 2 7 7 2 6 5 The project network is: ΝΑ A, B C с E C D, F, G D, F H I, J What is the minimum number of weeks that the project can be completed in (i e. the duration of the critical path)?arrow_forwardK Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Immediate Time Activity (weeks) Predecessor(s) Activity (weeks) ITI A A A B C D Time 5 6 2 2 Dave's earliest start (ES) and earliest finish (EF) are: Activity A E F G H ES EF 5 5 6 9 7 Immediate Predecessor(s) B B C, E D, F ncorrearrow_forward
- 2. The time estimates (in weeks) for the activities of a PERT network are given below. (i) (ii) 1-2 1-3 1-4 2-5 3-5 4-6 5-6 18 9 10 8 16 7 Activity to 24 16 3 tm 7 9 20 14 2 tp 9 20 11 11 28 18 4 Draw the project network and calculate the project length. Calculate the standard deviation and variance along the critical path. (iii) Find the probability of completing the project one day earlier and 2 days later.arrow_forwardB indicate critical path C what is expected completion for the project? D what is the probability that the project will take more than 30 days to complete?arrow_forwardA project consisting of the following activities: Activities predece.Activities day TE M K J H G E C B G KJ G I,F D D E,C B,A| B,A A 1 3 4 6. 5 2 3 9 6 2 4 3 5 1- Draw the network diagram of the project 2- Calculate (Es) and (Lc) the project events 3- Select the critical path 4 - What is the minimum time required to complete the project?arrow_forward
- BM HL Assignment 1- Due Date 24 March 2022 5. Construct an activity-on-arrow precedence diagram for each of the following cases. Note that each case requires the use of a dummy activity. ja) Draw AON diagram of the activity above! b) Determine the critical path! Activity Precedes Activity Duration (weeks) A В 3 C 4 D A E А, В F C 7 G D,E 4 H F,G 5 65Narrow_forwardParagraph 1. Draw the Activity on Node network. 2. Perform the CPM calculations using the forward and backward pass. ABCDEFGH 3. List the activities that are on the critical path. 4. Complete the table with the following headings. Activity Duration ES Q Search 62853652 EF A A, B B D. E C, D F, G LS Styles hp LF TF D FF PA IF Earrow_forwardi. a) XYZ Ltd has listed the following activities in respect of a project. Activity Preceding Activity A B C D E F G H I J K A A A B C C C and D E and F G and H I and J Draw a network diagram and determine the critical path Duration (days) 2 3 5 8 6 1 2 3 7 4 5 Page 1 of 2arrow_forward
- 2. A project for improving a billing process has the following precedence relationships and activity times: a. Choose the correct network diagram below. b. Calculate the slack for each activity. Which activities are on the critical path? (answer yes or no for drop down menu and digits for "weeks")arrow_forwardThe prime objectives of project management are cost, time andA. ScheduleB. QualityC. Customer satisfactionD. Performance.arrow_forwardProblem #2 Develop a network for the problem (below). Determine the total project completion time and the critical path(s). Activity Immediate Predecessors Time (Days) A - 3 B - 7 C A 4 D B 2 E C, D 5 F A 6 G E, F 3arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.