Act. Dur. 1-2 2-3 2-4 34 3-5 4-5 3. 5-6 Find total duration to finish the project And find critical path By AoA method 3:33 PM / 2.

Traffic and Highway Engineering
5th Edition
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Garber, Nicholas J.
Chapter8: Intersection Control
Section: Chapter Questions
Problem 19P
icon
Related questions
Question
Act.
Dur.
1-2
2
2-3
2-4
3.
34
3-5
4-5
5-6
Find total duration to finish the project And find critical
path By AoA method
3:33 PM /
2.
Transcribed Image Text:Act. Dur. 1-2 2 2-3 2-4 3. 34 3-5 4-5 5-6 Find total duration to finish the project And find critical path By AoA method 3:33 PM / 2.
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Site plan requirements
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning
Residential Construction Academy: House Wiring (M…
Residential Construction Academy: House Wiring (M…
Civil Engineering
ISBN:
9781285852225
Author:
Gregory W Fletcher
Publisher:
Cengage Learning