ABC Construction Company began work on a contract in 2022 and completed the contract in 2023. The total contact price was P8,500,000. Information related to the construction project are as follows:
|
2022 |
2023 |
Costs incurred during the year |
P1,200,000 |
P6,250,000 |
Estimated costs to complete |
4,800,000 |
- |
Progress billings during the year |
1,450,000 |
7,050,000 |
Collections during the year |
800,000 |
6,000,000 |
How much is the gross profit to be recognized in 2023?
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by stepSolved in 2 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- ABC Corp. was contracted to construct a warehouse for a price of P34,000,000. Information below were provided by ABC: 2011 P14,625,000 P32,500,000 2012 2013 P33,750,000 Costs Incurred to date Estimated cost at completion P25,687,500 P34,250,000 How much is the realized gross profit during 2013? How much is the Construction in Progress at the end of 2013 ?arrow_forwardBeavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,850,000. The project was begun in 2023 and completed in 2024. Cost and other data are presented below: 2023 2024 Costs incurred during the year $ 435,000 $ 1,150,000 Estimated costs to complete 1,015,000 0 Billings during the year 425,000 1,425,000 Cash collections during the year 325,000 1,525,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion. Required: Compute the amount of gross profit recognized during 2023 and 2024.arrow_forwardABC Co. started work on an P8,000,000 fixed-price construction contract in 20x1. Information on the contract is as follows: 20x2 20x1 2,850,000 3,670,000 Costs incurred per year Estimated costs to complete 4,275,000 1,630,000 How much profit (loss) is recognized in 20x2?arrow_forward
- Data Section - PROVIDED BY THE CLIENT Unit Sales Sales are expected to increase by 5% every month. The total sales for the Fiscal Year 2022 is 15% higher than the total sales for 2021. April May 15,000 10,000 June 16,000 July August September 14,000 15,000 Fixed Assets Cost 12,000 Land 150,000.00 Building 205,000.00 10 year depreciation, bought on May 31, 2021, Work Ethics Gen. Mdse uses the Declining Balance Method collections from customers: Office Equipment 100,000.00 20% are acquired on May 31, 2021 Cash $8.000 20% are acquired on August 31, 2021 Accounts receivable 107,800 20% are acquired on October 31, 2021 Merchandise inventory 52,800 20% are acquired on December 31, 2021 530,000 $698,600 Fixed assets (net) 20% are acquired on March 31, 2021 Total assets Use the Straight Line Method (5 years) Machinery 75.000.00 5 year Accounts payable (merchandise) Loans Payable Owner's equity Total liabilities & equity $74,800 $400,000 5 year loan, 12% interest taken out on May 31, 2021, paid…arrow_forwardHi can someone help me with this question please?arrow_forwardE 12-9 Research and Development Cost In 2019, Lalli Corporation incurred R&D costs as follow: Materials used from inventory 100,000 Personnel in R&D lab 100,000 Allocation of the cost of utilities and maintenance costs of the R&D facility 50,000 These costs relate to a product that will be marked in 2020. The company estimates tht these costs will be recouped by December 31, 2020. Required: 1. What is the amount of R&D cost expensed in 2019? 2. Would your answer change if the materials were purchased and not used or if the utilities and maintence costs were related to the corporate offices?arrow_forward
- Q3: An engineer determined the payback period of the project contract to be 9 years. The following table presents the project contact cost information: Annual cost First cost 15 M Salvage 5 M Contract 3M Ifi-13%, do you agree with that an engineer, and why?arrow_forwardABC Co. started work on two separate projects during 20x1. Information on these projects is shown below: NIVS Project Contract price Costs incurred A B 9,000,000 8,000,000 APIE 4,000,000 5,000,000 ERST Estimated costs to complete 4,000,000 Progress billings 5,000,000 8,000,000 What amount is presented in ABC Co's. statement of financial position as contract liability? 1911arrow_forwardThree companies have provided estimates for a proposed project: Item Company A Company B Company C Capital Investment $100,000 $150,000 $125,000 Useful Life (Months) 96 144 120 Market Value $40,000 0 $30,000 Net Annual Cash $45,000 $500,000 $35,000 Flow 12% MARR 12% 12% What is the AW for each of the 3 estimates? It is thought useful life is the estimate which has the greatest volatility. If the pessimistic estimate is 8 years and the optimistic estimate is 12 years what is the worst and best case conditions for AW and which proposal would you recommend?arrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education
Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,
Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON
Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education
Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education