a. Draw the network diagram in AOA and AON. b. Show the critical Path for the project?, And determine project completion time?
Q: A small, privately owned Asian company is producing a private-label soft drink called Yoggo. A…
A: Capacity alludes to the capacity of the cycle to create various units of the item in the given…
Q: [LO 5-3] 5-23 The materials handling charge for ABC Corp. is $0.50 per pound of finished product.…
A: Given- Material handling charge rate = $0.50 per poundNo. of units produced = 10,000 unitsWeight…
Q: Jefferson Distributing is analyzing distribution networks with either 4, 5, 6 or 7 warehouses to…
A: Transportation + Inventory cost for 4 warehouses = 8 + 4*SQRT(4) = $ 16 million Transportation +…
Q: What would the ROI be when using a self-service kiosk in a hotel?
A: Meaning of ROI in the hotel industry- This is where the idea of ROI or return on investment of your…
Q: A project consists of seven activities. The following table shows the estimated time of the…
A: By identifying the actions that are essential to the project schedule, the critical route technique…
Q: Tim Urban, owner/manager of Urban's Motor Court in Key West, is considering outsourcing the daily…
A: The crossover point is characterized as the degree of enrolments at which the total costs for one…
Q: Formulate an LP in general form to determine the amount to be sold and bought each day to maximize…
A: The LP formulation to maximize total profit for the warehouse problem is as follows: Maximize: Z =…
Q: 5 600 a. If only these competitive bids are received, who will receive T-bills, in what quantity,…
A: a) In Treasury auction, the bidder with the lowest interest rate and then the lowest bid amount if…
Q: Julie needs to develop knowledge about assessment tools used to diagnose ASD. She finds learning in…
A: A self-paced online course or e-learning module may be a suitable professional development…
Q: Describe what the term "productivity" implies and how to improve an organization's productivity.
A: Productivity is a efficiency of the company and worker who converts capital and labor (input) into…
Q: McDonald’s is a company that is all-in globally, having become a staple in over 100 countries around…
A: McDonald's is a global powerhouse that has become a staple in over 100 countries around the world.…
Q: Question 1: The SCO3001 Company is considering different tools to forecast the demand of its…
A: Answer a= Forecast for week 6= (47+46+32+26)/4 =37.75 Forecast for week 7= (46+32+26+33)/4 =34.25…
Q: d) If the firm operates 11 hours per day, 20 days per month, the monthly capacity of the…
A: Given- The capacity of the sawing station is 2.4 units per hourThe capacity of the sanding station…
Q: Consider the following from an estate agent business: Month Houses Sold Jan…
A: Note: - Since all the questions are different from each other and they are not subparts, we will…
Q: A project consists of seven activities. The following table shows the estimated time of the…
A: The longest series of tasks in a project plan that must be finished on time for it to be finished by…
Q: Garcia's Garage desires to create some colorful charts and graphs to illustrate how reliably its…
A: Given, Proportion of customers that return for repairs p = 0.09 The sampled customers n = 80…
Q: Bearing in mind the scope of the study, identify one hazard and its source or cause for each of the…
A: Process step: Slicing by machine Hazard & source/cause: Mechanical injury/cuts - The slicing…
Q: (a) What is the optimal solution, and what is the value of the total profit contribution? regular…
A: Linear programming is a mathematical technique that is commonly used in the operations management…
Q: Justify your reasoning for why a company would want to invest in IT infrastructure.
A: A company may invest in IT infrastructure to improve efficiency and productivity, to better manage…
Q: Decide in which periods ordering should take place (you can choose the calculation method).
A: Dynamic order size refers to the practice of adjusting the order size in response to changes in…
Q: ChocoTown has a 4,000 square foot outlet store that serves five major customer regions, denoted A,…
A: Since the variable Xij represents no of units product shipped from location i to j. Xij = no of…
Q: The control limits for the 3-sigma R-chart are (round all intermediate calculations to three…
A: Control charts are also known as process-behavior charts. It is a statistical process that helps in…
Q: What precisely is the purpose of doing a technical analysis? Explain not just how and why it is used…
A: Meaning of Technical Analysis Technical analysis is a device or technique, used to foresee the…
Q: Supplier Evatuation and selection. Explain supplier evaluation and selection and how it is used in…
A: *As per the question, not specified any industry, giving general solution.Companies operate supplier…
Q: the key elements for Operations Management in Business?
A: The management of processes and operations inside an organization is one of the functions of…
Q: 1. Is outsourcing a completely negative activity? How does its reputation tie in with insourcing?.
A: The act of allocating a company's business activities to an outside organization in order to improve…
Q: When should product strategy focus on forecasting capacity requirements? O A. at the saturation…
A: First, I would write the answer to when product strategy focuses on forecasting capacity needs, next…
Q: A production process at Kenneth Day Manufacturing is shown in the figure. The drilling operation…
A: Given- The capacity of the sawing station is 2.4 units per hourThe capacity of the sanding station…
Q: QUESTION 2: The Advanced Tech Company has a project to design an integrated information database for…
A: Path Duration Is duration maximum critical A-C-E-F 6+3+6+2 = 17 yes yes B-C-E-F 4+3+6+2 = 15 no…
Q: Which one is wrong about time horizons. Medium/long range forecasts deal with more comprehensive…
A: The following statement is wrong about time horizons: Economic forecasts: Address business cycle -…
Q: What are the international transport modes? Identify the criteria that a company might consider to…
A: Business is a very vast field where many processes are executed simultaneously to provide a good…
Q: What is the slack of activity C?
A: To find the slack of the activity we need to find the Early Start (ES), Early Finish (EF), Latest…
Q: What is a workflow chart and how is it important for business planning purposes?
A: Workflow chart:- The workflow chart is a graphical representation of the business process. There…
Q: What is the risk management of network manager?
A: Risk management in simple words can be defined as the process of distinguishing, assessing and…
Q: George Kyparisis makes bowling balls in his Miami plant. With recent increases in his costs, he has…
A: Formulas used-Labor Productivity = Units producedLabor hoursResin Productivity = Units producedResin…
Q: Case Project 3 Case Project: Think of all the tasks that you perform when you purchase a car.…
A: Estimate duration: 1. Compare different cars or models (Estimated Duration = 2 Days) 4. Discuss…
Q: The relationship between planning and controlling is intimate and mutual. Describe this statement.
A: Planning and controlling are two integral parts of any organization. Planning is the process of…
Q: Nationwide Auto Parts uses a periodic review inventory control system for one of its stock items.…
A: Safety stock management is vital in retail as recent fads arise and demand varies. Organizations can…
Q: Read the following passage and answer the question that follows Quincy Snodgrass…
A: Given- Smithburg population = 700 customersEmeryville population = 1,800 customersGolf Creek…
Q: M, Introducing the slack variables x3, x4, and x5, we get
A: Linear programming is a mathematical technique that is commonly used in the operations management…
Q: How many orders of magnitude larger is the difference between a process that operates in nanoseconds…
A: The processes of a business are very quick when it comes to using high-end technology where big…
Q: Based on the x-chart, the wire cutting process has been
A: Based on the X- chart we can see from the below Graph, it appears that the process is not in…
Q: Make a persuasive speech about savings. 500 words. AVOID PLAGIARISM
A: Savings are an important component of one's life. It is a portion of income that is not spent on…
Q: Discuss Productivity and Performance Management Why is productivity important? Next, what is the…
A: First, I will explain the terms productivity and performance management. Then, I will go over the…
Q: TMA manufactures 37-in. high definition LCD televisions in two separate locations, Locations I and…
A: Decision Variables: Suppose-x be the no. of LCD televisions to be shipped from the locations -1 to…
Q: Strategic Management. 3. What is External Opportunities and Threats for businesses? 4. What is…
A: Note: According to Bartleby's guideline, only the first three questions can be answered. Please…
Q: LOCATIONAL STRATEGY DILEMMA GEW is an electronics component manufacturer that has been located in…
A: When manufacturers make location decisions, their priority is to minimize cost. Retailers look to…
Q: Discuss the key characteristics of a private limited company and a partnership
A: Private limited company: Separate legal entity: It is viewed as a separate entity from its owners…
Q: Is a high quality product more or less expensive than a poor quality product? Consider all five…
A: A high-quality item will often cost less than a low-quality item. The five costs of quality can be…
Q: A firm cleans chemical tank cars in the Bay St. Louis area. With standard equipment, the firm…
A: As per our guidelines, we can only answer first three subparts, please post them under a different…
Step by step
Solved in 4 steps with 3 images
- The expected times and variances for the activities for a project for Test Marketers, Inc. are given below. (Assume time is provided in days.) ID 12345678 Description Pilot production Select channels of distrib. Develop mktg. program Test market Patent Full production Ad promotion Release Predecessor None None None 1 1 4 3 2,5,6,7 t₂ 6 7 4 4 10 16 3 2 Varlance [(b-a)/6]² 34225221 10A B с D E FL ד G H J K L M N P R S T U V 1 On Week 3 Forecast 4 2 a) Smell Fresh Customer Orders hand 1 2 20 20 5 3 5 PAB 20 50 30 3222 4 5 6 7 8 Problem 6: Georgia Clay and Gravel was updating the MPS record for one of its products, Smell Fresh Cat Litter. Partially-completed MPS time-phased record is given below. 20 30 30 30 30 30 Week 10 30 50 20 40 10 Item: Smell Fresh On hand 1 6 Available to Promise 7 MPS 50 50 50 50 Forecast 20 8 MPS lot size = 50 9 20 10 On Week hand 2 3 4 5 6 7 8 9 20 53 43 78 30 30 30 30 30 3220 2233 -250 30 10 30 50 6 8 45 12 13 14 PAB 15 11 b) Smell Fresh Forecast Customer Orders Available to Promise 16 MPS 17 MPS lot size=50 18 19 20 21 23 24 222 Orders Projected available balance Available-to-promise MPS MPS Lot Size = 50. 50 20 40 10 50 50 50 a) Complete the MPS time-phased record (the first table on the left). The following events occurred during week 1: • Actual demand during week 1 was 25 units. • Marketing forecasted that 40 units would be needed for…Company: ABC Civil Engineering - an engineering firmSituation: ABC company has recently made significant cuts in staff and the workload on existingemployees has increased. A major RFP is dueCharacters: Ted Waltz – Managing Director of ABC EngineeringElaine Tillman – Civil Engineer____________________________Elaine Tillman looked at her watch – it was 7:30 pm. Just then she knew she would not make it to her son’s final high school basketball game. It took her a moment to collect herself and wipe the tear that had started down her face and onto the ragged-edged 100 plus page RFP she was working on. The RFP,the largest opportunity that ABC Civil Engineering had a chance to bid on in 6 months, was far fromready for the 9:00 AM deadline the following day.Normally in this situation, Elaine would have collaborated with a proposal team putting together such a big proposal but, since the economic down turn hit, ABC has had to make significant cuts in its staff. It started with administrative…
- Company: ABC Civil Engineering - an engineering firmSituation: ABC company has recently made significant cuts in staff and the workload on existingemployees has increased. A major RFP is dueCharacters: Ted Waltz – Managing Director of ABC EngineeringElaine Tillman – Civil Engineer____________________________Elaine Tillman looked at her watch – it was 7:30 pm. Just then she knew she would not make it to her son’s final high school basketball game. It took her a moment to collect herself and wipe the tear that had started down her face and onto the ragged-edged 100 plus page RFP she was working on. The RFP,the largest opportunity that ABC Civil Engineering had a chance to bid on in 6 months, was far fromready for the 9:00 AM deadline the following day.Normally in this situation, Elaine would have collaborated with a proposal team putting together such a big proposal but, since the economic down turn hit, ABC has had to make significant cuts in its staff. It started with administrative…1.The chief engineer of firm XYZ is responsible for supervising the construction work of a road. He has identified the activities and their durations for each stage of operation. Activity Duration (days) Preceding activities A 5 - B 10 - C 1 - D 8 B E 10 B F 9 B G 3 A,D H 7 A,D I 4 F J 3 F K 5 C,J L 8 H,E,I,K M 4 CJ Draw a network diagram (AOA) for this road construction project. Which are the critical activities? How long the project will take?The following table shows the various activities of the development of a new product in your organization; Activity Event Immediate Predecesor(s) Estimates of Activity Duration (Weeks) Optimistic (To) Most Likely (Tm) Pessimistic (Tp) Average (Te) 1 A - 2 3 4 ? 2 B A 1 2 ? 2 3 C A 1 ? 4 2.2 4 D B ? 5 6 5 5 E B 3 ? 5 4 6 F C 2 3 ? 3 7 G D ? 2 4 2.2 8 H E,F,G 3 4 6 ? 9 I H 3 ? 5 4 10 J I 2 1 3…
- The following table shows the various activities of the development of a new product in your organization. Activity Event Immediate Predecessor(s) Estimates of Activity Duration (Weeks) Optimistic (To) Most Likely (Tm) Pessimistic (Tp) Average (Te) 1 A - 2 3 4 ? 3 2 B A 1 2 3 2 3 C A 1 2.05 4 2.2 4 D B 4 5 6 5 5 E B 3 4 5 4 6 F C 2 3 4 3 7 G D 1.2 2 4 2.2 8 H E,F, G 3 4 6 4.167 9 I H 3 4 5 4 10 J I 2 1 3 1.5 Questions: Draw the PERT network from the given data. (15. For the network shown: Crash Cost/week - (CC-NC)/(NT-CT) TOTAL COST-$44,000 Crash D-$1,000 Crash G-$2,000 Crash A-$3,000 0 0 ATS) Activity A B 54 C D E F 45 45 B(10) C(8) 1514 15 10 13 12 14 Normal Time 5 8 6 7 14 15 15 D(6) 21 20 19 21 a. Determine the critical path and the early completion time in weeks for the project. b. For the data shown, reduce the project completion time by three weeks. Assume a lin- ear cost per week shortened, and show, step by step, how you arrived at your schedule. 20 19 E(7) 14 13 17 F(4) 17 21 Normal Cost $7,000 12,000 5,000 4,000 3,000 6,000 7,000 21 20 21 25 G(4) 25 Crash Time 3 7 7 24 23 22 A 2 B3 C1 D1 E1 5 6 F1 3 G1 Crash Cost $13,000 18,000 7,000 5,000 6,000 7,000 9,000 A $3,000 B $2,000 C $2,000 D $1,000 E $3,000 F $1,000 G $2,000Using PERT, Adam Munson was a ble to determinethat the expected project completion time for the construction ofa pleasure yacht is 21 months, and the project va riance is 4.a) What is the probability that the project will be completed in17 months?b) What is the probability that the project will be completed in20 months?c) What is the probability that the project will be completed in23 months?d) What is the probability that the project will be completed in25 months?e) What is the due date that yields a 95% chance of completion?
- The following table shows the various activities of the development of a new product in your organization. Activity Event Immediate Predecessor(s) Estimates of Activity Duration (Weeks) Optimistic (To) Most Likely (Tm) Pessimistic (Tp) Average (Te) 1 A - 2 3 4 ? 2 B A 1 2 ? 2 3 C A 1 ? 4 2.2 4 D B ? 5 6 5 5 E B 3 ? 5 4 6 F C 2 3 ? 3 7 G D ? 2 4 2.2 8 H E,F, G 3 4 6 ? 9 I H 3 ? 5 4 10 J I 2 1 3 ? Questions: Calculate ALL the missing (?) data points. Draw the PERT network from the given data. Determine ALL the paths, the critical path and its total duration in days. Explain the limitations…What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? NORMAL CRASH TIME (DAYS) TIME (DAYS) 9 7 7 6 5 4 6 4 9 6 ACTIVITY Design (A) Wiring (B) Chip install (C) Software (D) Testing (E) The minimum cost of crashing the following project at Sawaya Robotics by. 4 days is $ NORMAL COST 200 800 600 1,100 1,200 CRASH COST 300 875 675 1,300 1,875 IMMEDIATE PREDECESSOR(S) (enter your response as a whole number). A, B CRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a num- ber of activities that must be completed before a training program of this nature could be conducted. The activities, immediate pre- decessors, and times appear in the accompanying table: 3.8 IMMEDIATE АCTIVITY PREDECESSOR(S) TIME (DAYS) A 2 5 1 10 A, D 3 F G E, F 8 a) Develop an AON network for this problem. b) What is the critical path? c) What is the total project completion time? d) What is the slack time for each individual activity? PX 6. B. B. E.