a. Draw a project network. b. What is the critical path? c. What is the normal project cost? d. What is the total cost of the project if you need to crash it by 1 week?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
icon
Concept explainers
Topic Video
Question

a. Draw a project network.

b. What is the critical path?

c. What is the normal project cost?

d. What is the total cost of the project if you need to crash it by 1 week?

 

Chp 18 P8
Normal Time
Activity
Predecessor(s)
Crash Time (Wks)
Normal Cost
Crash Cost
(Wks)
A
5
4
$400
$750
---
A
8
6
1600
2200
C
A
7
6
800
1100
D
6
5
600
1000
E
B,D,C
8
6
1200
2200
D
3
2
800
1000
G
D
3
2
500
650
H
E
4
3
400
600
F,G,H
6.
900
1300
Transcribed Image Text:Chp 18 P8 Normal Time Activity Predecessor(s) Crash Time (Wks) Normal Cost Crash Cost (Wks) A 5 4 $400 $750 --- A 8 6 1600 2200 C A 7 6 800 1100 D 6 5 600 1000 E B,D,C 8 6 1200 2200 D 3 2 800 1000 G D 3 2 500 650 H E 4 3 400 600 F,G,H 6. 900 1300
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.