A system is working at its maximum kVA capacity with a lagging power factor 0·7. An anticipated increase of load can be met by one of the following two methods: By raising the p.f. of the system to 0·866 by installing phase advancing equipment. By installing extra generating plant. If the total cost of generating plant is Rs 100 per kVA, estimate the limiting cost per kVA of phase advancing equipment to make its use more economical than the additional generating plant. Interest and depreciation charges may be assumed 10% in each case.
A system is working at its maximum kVA capacity with a lagging power factor 0·7. An anticipated increase of load can be met by one of the following two methods: By raising the p.f. of the system to 0·866 by installing phase advancing equipment. By installing extra generating plant. If the total cost of generating plant is Rs 100 per kVA, estimate the limiting cost per kVA of phase advancing equipment to make its use more economical than the additional generating plant. Interest and depreciation charges may be assumed 10% in each case.
Power System Analysis and Design (MindTap Course List)
6th Edition
ISBN:9781305632134
Author:J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Publisher:J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Chapter2: Fundamentals
Section: Chapter Questions
Problem 2.32MCQ: While the instantaneous electric power delivered by a single-phase generator under balanced...
Related questions
Question
100%
A system is working at its maximum kVA capacity with a lagging power factor 0·7. An anticipated increase of load can be met by one of the following two methods:
- By raising the p.f. of the system to 0·866 by installing phase advancing equipment.
- By installing extra generating plant. If the total cost of generating plant is Rs 100 per kVA, estimate the limiting cost per kVA of phase advancing equipment to make its use more economical than the additional generating plant. Interest and depreciation charges may be assumed 10% in each case.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 2 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, electrical-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
Power System Analysis and Design (MindTap Course …
Electrical Engineering
ISBN:
9781305632134
Author:
J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Publisher:
Cengage Learning
Power System Analysis and Design (MindTap Course …
Electrical Engineering
ISBN:
9781305632134
Author:
J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Publisher:
Cengage Learning