A road can be paved with either asphalt or concrete. Concrete costs $15,000/km and lasts 20 years. What is the maximum that should be spent on asphalt if it only lasts 10 years? Annual maintenance costs for both pavements are $500/km. MARR = 12%. Demonstrate through real life examples a bridge management software you know.

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter18: Life-cycle Costing
Section: Chapter Questions
Problem 13RQ
icon
Related questions
Question
A road can be paved with either asphalt or concrete. Concrete costs $15,000/km and lasts 20 years. What is the maximum that should be spent on asphalt if it only lasts 10 years? Annual maintenance costs for both pavements are $500/km. MARR = 12%. Demonstrate through real life examples a bridge management software you know.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 1 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning